Show Job Controls
Bid Cobra

EL PASO SL 375 (2552-04-059)

Items: 82

County: EL PASO
Length: 0.0000 MILES
Highway: SL 375
District: EL PASO
Control Number: 2552-04-059
DBE Goal: 0.0%
Project: F 2026(120)
Guaranty: $100,000.00
Time: 228 WORKING DAYS
Engineer's Estimate: $7,749,232.96
Date: 02/04/2026 (4 months ago) Changed
Contract Number: 11253210
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00210422
Contract Type: Federal
Project Description: BASE REPAIR & HMA OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JONATHAN CONCHA
ALDO MADRID
MONICA RUIZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$7,749,232.96
$7,195,638.49
Over/Under Est: -7.14% -$553,594.47
Over/Under Est: 3.14% $243,460.22
Amt Left: 11.08% $797,054.69

Bid Items & Bid Tabulations

82 Total 0 of 82
EL PASO  |  SL 375  |  EL PASO  |  2552-04-059  |  02/04/2026  |  $7,749,232.96  |  F 2026(120)  |  SURF/ROADWAY RESTOR  |  228 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
INTERNATIONAL EAGLE ENTERPRISES, INC.
REMOV CONC (RIPRAP)
SY 1,659.000 $40.000 $23.000 $30.000
EXCAV (SPECIAL)
CY 170.000 $315.000 $10.000 $300.000
EMBANK (FNL)(OC)(TY A)
CY 700.000 $50.000 $14.000 $120.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 480.000 $315.000 $200.000 $190.000
TACK COAT
GAL 1,325.000 $4.300 $8.000 $8.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 9,730.000 $160.000 $151.150 $151.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 48,350.000 $45.000 $48.000 $56.000
PLANE ASPH CONC PAV(0" TO 2")
SY 7,050.000 $4.750 $6.000 $3.000
PLANE ASPH CONC PAV(0" TO 0.5" MICRO)
SY 2,546.000 $7.000 $9.000 $3.500
PLANE ASPH CONC PAV(2")
SY 142,685.000 $2.000 $2.000 $2.750
RIPRAP (CONC)(CL B)
CY 315.000 $450.000 $525.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 334.000 $645.000 $600.000 $580.000
ADJUSTING MANHOLES
EA 1.000 $1,465.000 $1,500.000 $8,000.000
ADJUSTING INLETS
EA 6.000 $1,630.000 $2,100.000 $6,000.000
ADJUSTING MANHOLES (UTILITY BOX)
EA 12.000 $930.000 $915.000 $2,000.000
MOBILIZATION
LS 1.000 $694,657.540 $150,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $9,000.000 $15,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 56.000 $150.000 $150.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $9,000.000 $12,000.000 $14,000.000
TMA (STATIONARY)
DAY 138.000 $225.000 $225.000 $300.000
TMA (MOBILE OPERATION)
HR 480.000 $60.000 $65.000 $75.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $45.000 $24.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $20.000 $10.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 283.000 $13.000 $16.500 $20.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 283.000 $2.500 $4.750 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 13,005.000 $32.000 $28.000 $31.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 17.000 $2,200.000 $3,000.000 $3,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 9.000 $1,530.000 $1,500.000 $2,000.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $675.000 $1,500.000 $2,000.000
CONNECTOR PLATE FOR THRIE BEAM
EA 12.000 $500.000 $1,200.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 13,160.000 $2.300 $2.000 $2.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 9.000 $275.000 $425.000 $850.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 9.000 $280.000 $425.000 $850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 14.000 $3,150.000 $4,000.000 $3,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $270.000 $425.000 $1,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 226.000 $21.250 $25.000 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 414.000 $32.000 $45.000 $10.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 776.000 $20.600 $25.000 $10.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 388.000 $13.200 $30.000 $10.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 7.000 $20.000 $30.000 $100.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 10,693.000 $1.400 $2.550 $3.200
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 24,396.000 $0.500 $2.550 $3.200
WK ZN PAV MRK REMOV (W)12"(LNDP)
LF 4,948.000 $5.200 $5.000 $6.250
WK ZN PAV MRK REMOV (W)(ENTR GORE)
EA 3.000 $545.000 $4,900.000 $6,125.000
WK ZN PAV MRK REMOV (W)(EXIT GORE)
EA 4.000 $500.000 $5,800.000 $7,250.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 24,396.000 $0.500 $2.550 $3.200
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 206.000 $1.700 $2.250 $6.250
REFL PAV MRK TY I (W)6"(DOT)(090MIL)
LF 445.000 $1.600 $0.750 $0.940
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 2,989.000 $2.750 $3.000 $3.750
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 2.000 $350.000 $145.000 $181.250
REFL PAV MRK TY I(W)(DBL ARROW)(090MIL)
EA 6.000 $190.000 $195.000 $245.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 6.000 $390.000 $185.000 $230.000
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
EA 4.000 $595.000 $1,000.000 $1,250.000
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
EA 5.000 $830.000 $1,700.000 $2,125.000
RE PM TY II (W) 6" (BRK)
LF 9,175.000 $0.410 $0.230 $0.290
RE PM TY II (W) 6" (DOT)
LF 445.000 $0.950 $0.230 $0.290
RE PM TY II (W) 6" (SLD)
LF 35,586.000 $0.580 $0.230 $0.290
RE PM TY II (W) 12" (DOT)
LF 2,807.000 $0.750 $1.550 $1.940
RE PM TY II (W) 12" (SLD)
LF 2,989.000 $2.500 $1.550 $1.940
RE PM TY II (W) (ARROW)
EA 2.000 $103.000 $90.000 $115.000
RE PM TY II (W) (DBL ARROW)
EA 6.000 $100.000 $110.000 $140.000
RE PM TY II (W) (WORD)
EA 6.000 $125.000 $120.000 $150.000
RE PM TY II (W) (ENTR GORE)
EA 4.000 $1,900.000 $320.000 $400.000
RE PM TY II (W) (EXIT GORE)
EA 5.000 $250.000 $500.000 $625.000
RE PM TY II (Y) 6" (SLD)
LF 29,352.000 $0.490 $0.230 $0.290
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 34,336.000 $0.950 $1.200 $1.500
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 34,172.000 $0.950 $1.200 $1.500
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 9,175.000 $0.650 $0.850 $1.060
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 1,252.000 $1.250 $0.850 $1.060
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 2,807.000 $2.550 $3.000 $3.750
PREFAB PM TY C (MULTI)(SHIELD)
EA 9.000 $2,600.000 $2,600.000 $3,250.000
REFL PAV MRKR TY II-C-R
EA 1,511.000 $6.600 $5.500 $6.880
ELIM EXT PM & MRKS (4")
LF 15,548.000 $0.700 $0.450 $0.560
PAV SURF PREP FOR MRK (6")
LF 63,823.000 $0.140 $0.150 $0.190
PAV SURF PREP FOR MRK (12")
LF 7,904.000 $0.810 $0.500 $0.630
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $30.000 $50.000 $80.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 6.000 $50.000 $55.000 $80.000
PAV SURF PREP FOR MRK (WORD)
EA 6.000 $75.000 $85.000 $106.000
PAV SURF PREP FOR MRK (ENTR GORE)
EA 4.000 $150.000 $140.000 $175.000
PAV SURF PREP FOR MRK (EXIT GORE)
EA 5.000 $150.000 $200.000 $250.000
MEMBRANE UNDERSEAL
GAL 28,545.000 $3.000 $5.500 $8.000
SP-BMD SP-C SAC-A PG 70-22
TON 5,990.000 $180.000 $141.150 $90.000
Totals: $7,749,232.960 $7,195,638.490 $7,992,693.180
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $70,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $75,000.00
Total: $195,000.00