EL PASO SL 375 (2552-01-064)
Items: 63
County: EL PASO
Length: 0.0000 MILES
Highway: SL 375
District: EL PASO
Control Number: 2552-01-064
DBE Goal: 4.0%
Project: F 2025(768)
Guaranty: $32,000.00
Time: 99 WORKING DAYS
Engineer's Estimate: $2,097,643.75
Date: 05/02/2025 (1 year ago)
Contract Number: 5253221
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206608
Contract Type: Federal
Project Description: INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION), INSTALL ADVANCED WARNING SIGNALS AND SIGNS, TRANSVERSE RUMBLE STRIPS, RUNWAY RAMP
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EL PASO SL 375 (2552-01-064)
Project Name: N/A
Project: F 2025(768)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: IH 10
Limits To: 0.7 MI E OF US 54
Project Description: INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION), INSTALL ADVANCED WARNING SIGNALS AND SIGNS, TRANSVERSE RUMBLE STRIPS, RUNWAY RAMP
Bidders (2)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,097,643.75 | |||
| $2,780,753.75 |
32.57%
$683,110.00
|
|||
| $2,979,989.25 |
42.06%
$882,345.50
|
7.16%
$199,235.50
|
E
Engineer's Estimate
$2,097,643.75
1
$2,780,753.75
Over/Under Est:
32.57%
$683,110.00
$2,979,989.25
Over/Under Est:
42.06%
$882,345.50
Amt Left:
7.16%
$199,235.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRI STATE ELECTRIC, LTD. | 17.60% | $489,412.66 |
| HARDY HOLE DRILLING | 6.16% | $171,294.43 |
| BAG REINFORCING LLC | 1.37% | $38,096.33 |
| PAVEMENT MARKINGS INC. | 1.06% | $29,475.99 |
| PMI PAVEMENT MARKING, LLC | 1.06% | $29,475.99 |
| MAJOR MOTION LOGISTICS, LLC | 0.90% | $25,026.78 |
| Total: | 28.15% | $782,782.18 |
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $50,000.00 |
| Total: | $65,000.00 |