EL PASO IH 10 (2121-04-129)

Items: 17

County: EL PASO
Length: 0.0000 MILES
Highway: IH 10
District: EL PASO
Control Number: 2121-04-129
DBE Goal: 0.0%
Project: C 2121-4-129
Guaranty: $18,000.00
Time: 51 WORKING DAYS
Engineer's Estimate: $425,202.00
Date: 03/04/2025 (1 year ago)
Contract Number: 3253030
Type: PREVENTIVE MAINTENANCE
Project ID: A00212942
Project Description: FY 2025 METAL BEAM GUARD FENCE (MBGF)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$425,202.00
$276,338.00
Over/Under Est: -35.01% -$148,864.00
Over/Under Est: -18.72% -$79,581.65
Amt Left: 25.07% $69,282.35
Over/Under Est: -11.66% -$49,570.85
Amt Left: 35.93% $99,293.15
Delta: -8.68% -$30,010.80
Over/Under Est: -8.85% -$37,627.00
Amt Left: 40.25% $111,237.00
Delta: -3.18% -$11,943.85
Over/Under Est: -6.83% -$29,038.00
Amt Left: 43.36% $119,826.00
Delta: -2.22% -$8,589.00
Over/Under Est: -6.18% -$26,278.22
Amt Left: 44.36% $122,585.78
Delta: -0.70% -$2,759.78
Over/Under Est: -5.39% -$22,908.00
Amt Left: 45.58% $125,956.00
Delta: -0.84% -$3,370.22
$451,324.00
Over/Under Est: 6.14% $26,122.00
Amt Left: 63.32% $174,986.00
Delta: -12.19% -$49,030.00
Over/Under Est: 12.29% $52,242.00
Amt Left: 72.78% $201,106.00
Delta: -5.79% -$26,120.00
Subcontractor Percentage Amount
ELITE CASTLE RESOURCES LLC 45.91% $126,866.78
ELIAS CONCRETE CONSTRUCTION LLC 24.09% $66,569.82
Total: 70.00% $193,436.60

Bid Items & Bid Tabulations

17 Total 0 of 17
EL PASO  |  IH 10  |  EL PASO  |  2121-04-129  |  03/04/2025  |  $425,202.00  |  C 2121-4-129  |  PREVENT MAINT  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROSS SA ENTERPRISE LLC
APACHE BARRICADE & SIGN
DAN WILLIAMS COMPANY
B & MS CONSTRUCTION, INC.
INTERNATIONAL EAGLE ENTERPRISES, INC.
SYNERGY PROJECT CONTRACTORS, INC.
ICOS MANAGEMENT, LLC
HJC FARMS, INC.
HORIZONE CONSTRUCTION I, LTD
REMOV CONC (MOWSTRIP)
LF 199.000 $8.000 $25.000 $25.000 $7.500 $85.000 $30.000 $23.600 $66.000 $50.000 $38.000
RIPRAP (MOW STRIP)(4 IN)
CY 137.000 $803.000 $500.000 $695.000 $650.000 $620.000 $500.000 $472.000 $660.000 $800.000 $572.000
MOBILIZATION
LS 1.000 $50,730.000 $25,000.000 $1,000.000 $37,000.000 $35,000.000 $35,000.000 $47,200.000 $15,000.000 $75,000.000 $23,551.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,852.000 $3,500.000 $8,000.000 $15,000.000 $3,000.000 $15,000.000 $4,720.000 $1.000 $2,200.000 $13,200.000
TMA (STATIONARY)
DAY 51.000 $387.000 $400.000 $325.000 $200.000 $290.000 $150.000 $383.500 $275.000 $50.000 $340.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 273.000 $9.000 $15.000 $13.950 $6.000 $5.000 $12.000 $5.900 $11.000 $15.000 $24.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 273.000 $3.000 $1.000 $9.000 $2.050 $3.000 $1.000 $2.360 $6.000 $3.000 $7.000
MTL W-BEAM GD FEN (STEEL POST)
LF 2,100.000 $43.000 $30.000 $38.000 $34.500 $45.000 $38.000 $53.100 $55.000 $50.000 $74.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $3,195.000 $2,000.000 $3,045.000 $3,000.000 $1,800.000 $4,900.000 $3,567.140 $4,400.000 $3,500.000 $1,495.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,883.000 $1,500.000 $1,400.000 $1,400.000 $2,750.000 $2,500.000 $1,740.500 $2,200.000 $2,500.000 $1,683.000
REMOVE METAL BEAM GUARD FENCE
LF 3,325.000 $9.000 $1.000 $9.000 $8.000 $7.000 $5.000 $11.800 $5.000 $5.000 $12.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $389.000 $1,000.000 $150.000 $350.000 $1,400.000 $1,200.000 $236.000 $550.000 $500.000 $2,400.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 7.000 $408.000 $300.000 $150.000 $350.000 $1,400.000 $1,000.000 $354.000 $1,100.000 $500.000 $900.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $422.000 $250.000 $270.000 $350.000 $1,750.000 $1,000.000 $354.000 $550.000 $500.000 $900.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,829.000 $3,500.000 $3,800.000 $4,000.000 $2,800.000 $4,600.000 $4,248.000 $5,500.000 $5,000.000 $4,540.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $407.000 $200.000 $150.000 $350.000 $1,400.000 $1,000.000 $236.000 $550.000 $500.000 $900.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 109.000 $48.000 $30.000 $75.000 $49.000 $19.000 $30.000 $15.340 $44.000 $65.000 $50.000
Totals: $425,202.000 $276,338.000 $345,620.350 $375,631.150 $387,575.000 $396,164.000 $398,923.780 $402,294.000 $451,324.000 $477,444.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $7,000.00
Total: $15,000.00