EL PASO IH 10 (2121-04-110)

Items: 86

County: EL PASO
Length: N/A
Highway: IH 10
District: EL PASO
Control Number: 2121-04-110
DBE Goal: N/A
Project: BR 2023(885)
Guaranty: N/A
Time: 124 WORKING DAYS
Engineer's Estimate: $2,466,921.45
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,466,921.45
$2,756,557.25
Over/Under Est: 11.74% $289,635.80
Over/Under Est: 11.92% $293,934.80
Amt Left: 0.16% $4,299.00
Over/Under Est: 32.92% $812,106.08
Amt Left: 18.95% $522,470.28
Delta: -18.77% -$518,171.28
Subcontractor Percentage Amount
HARDY HOLE DRILLING 6.15% $169,528.27
TRI STATE ELECTRIC, LTD. 5.22% $143,892.29
NATIONWIDE REBAR INC. 4.21% $116,051.06
MAJOR MOTION LOGISTICS, LLC 1.28% $35,283.93
PENHALL COMPANY 0.24% $6,615.74
PMI PAVEMENT MARKING, LLC 0.23% $6,340.08
Total: 17.33% $477,711.37

Bid Items & Bid Tabulations

86 Total 0 of 86
EL PASO  |  IH 10  |  EL PASO  |  2121-04-110  |  06/02/2023  |  $2,466,921.45  |  BR 2023(885)  |  BRIDGE REPL  |  124 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
INTERNATIONAL EAGLE ENTERPRISES, INC.
SPARTAN CONSTRUCTION OF TEXAS, INC.
PREPARING ROW
STA 7.000 $2,000.000 $5,000.000 $1,000.000 $7,919.800
REMOVING CONC (PAV)
SY 74.000 $10.000 $45.000 $100.000 $43.556
REMOVING CONC (RIPRAP)
SY 341.000 $10.000 $15.000 $28.000 $29.038
REMOVING CONC (CURB)
LF 663.000 $5.000 $4.000 $4.000 $9.679
REMOVING CONC (CTB)
LF 380.000 $20.000 $35.000 $25.000 $48.396
REMOVING STAB BASE & ASPH PAV (9")
SY 1,312.000 $9.000 $2.500 $10.000 $8.580
EXCAVATION (ROADWAY)
CY 55.000 $20.000 $35.000 $100.000 $181.485
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,197.000 $20.000 $40.000 $12.000 $77.328
FL BS (CMP IN PLC)(RAP) (6")
SY 1,534.000 $10.000 $7.000 $18.000 $14.217
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 1,591.000 $30.000 $20.000 $24.000 $17.613
PRIME COAT (MULTI OPTION)
GAL 318.000 $10.000 $10.000 $8.000 $12.319
CEM STABIL BKFL
CY 180.000 $120.000 $175.000 $200.000 $139.690
CUT & RESTORING PAV
SY 8.000 $150.000 $190.000 $500.000 $608.830
DRILL SHAFT (36 IN)
LF 639.000 $300.000 $350.000 $400.000 $356.921
DRILL SHAFT (42 IN)
LF 21.000 $400.000 $530.000 $575.000 $435.564
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $320.000 $400.000 $440.000 $362.970
CL C CONC (ABUT)(HPC)
CY 52.400 $1,100.000 $1,500.000 $1,100.000 $907.425
CL C CONC (CAP)(HPC)
CY 59.700 $1,200.000 $1,900.000 $1,500.000 $1,330.890
CL C CONC (COLUMN)(HPC)
CY 55.400 $1,000.000 $1,400.000 $1,100.000 $1,814.850
CL C CONC (RAIL FOUNDATION)
CY 82.000 $600.000 $500.000 $800.000 $626.980
REINF CONC SLAB (HPC)
SF 11,730.000 $22.000 $30.000 $24.000 $33.163
APPROACH SLAB (HPC)
CY 71.000 $600.000 $700.000 $600.000 $670.140
PRESTR CONC GIRDER (TX28)
LF 1,518.120 $250.000 $240.000 $250.000 $373.203
RIPRAP (CONC)(4 IN)
CY 1.500 $1,650.000 $850.000 $2,000.000 $2,325.040
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 104.000 $450.000 $725.000 $400.000 $577.485
RAIL (TY SSTR)(HPC)
LF 558.000 $80.000 $75.000 $80.000 $124.297
RAIL (TY T80SS)
LF 510.000 $90.000 $125.000 $75.000 $126.497
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 137.000 $200.000 $210.000 $250.000 $291.478
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $150,000.000 $150,000.000 $150,000.000 $108,891.000
REMOV STR (APPROACH SLAB)
EA 2.000 $9,000.000 $1,750.000 $30,000.000 $5,142.075
MOBILIZATION
LS 1.000 $200,000.000 $205,000.000 $150,000.000 $244,238.500
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $15,000.000 $8,000.000 $7,864.350
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 90.000 $40.000 $33.250 $50.000 $48.947
ROCK FILTER DAMS (REMOVE)
LF 90.000 $15.000 $12.000 $15.000 $18.424
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 623.000 $20.000 $24.500 $20.000 $42.622
CONSTRUCTION EXITS (REMOVE)
SY 623.000 $10.000 $12.750 $10.000 $18.424
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 1,320.000 $68.000 $35.000 $96.000 $104.658
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 1,320.000 $20.000 $10.000 $8.000 $18.975
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $30.000 $30.000 $28.000 $36.297
MTL W-BEAM GD FEN (STEEL POST)
LF 512.500 $40.000 $35.000 $35.000 $50.816
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $3,200.000 $2,650.000 $3,024.750
TRANSITION ADJUSTMENT
EA 1.000 $2,000.000 $1,400.000 $5,000.000 $483.960
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $3,300.000 $1,400.000 $1,500.000 $2,056.830
REMOVE METAL BEAM GUARD FENCE
LF 1,487.500 $4.000 $4.000 $1.500 $8.469
REMOVE TERMINAL ANCHOR SECTION
EA 7.000 $350.000 $350.000 $400.000 $302.475
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 2.000 $3,000.000 $4,500.000 $5,000.000 $604.950
REMOVE CABLE BARRIER
LF 200.000 $4.000 $5.000 $4.000 $8.469
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,500.000 $3,400.000 $3,200.000 $3,629.700
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $400.000 $350.000 $500.000 $802.965
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $1,000.000 $1,000.000 $1,127.480
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $30,000.000 $30,000.000 $30,000.000 $31,146.555
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $10,000.000 $10,000.000 $25,000.000 $10,064.325
RELOCATE RD IL ASM (TRANS-BASE)
EA 1.000 $2,500.000 $2,600.000 $2,860.000 $5,928.510
CONDT (PVC) (SCH 40) (2")
LF 595.000 $20.000 $32.000 $35.000 $36.297
CONDT (PVC) (SCH 40) (2") (BORE)
LF 605.000 $40.000 $40.000 $43.500 $48.396
ELEC CONDR (NO.8) INSULATED
LF 2,355.000 $2.000 $3.200 $3.750 $3.146
ELEC CONDR (NO.4) INSULATED
LF 1,275.000 $3.000 $5.700 $6.250 $4.840
GROUND BOX TY A (122311)W/APRON
EA 7.000 $1,000.000 $1,725.000 $1,895.000 $1,935.840
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $825.000 $915.000 $1,200.000 $1,107.059
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $3,000.000 $5,000.000 $5,485.000 $6,033.771
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $750.000 $825.000 $480.000 $982.439
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $800.000 $825.000 $480.000 $990.908
REMOVE SM RD SN SUP&AM
EA 3.000 $150.000 $450.000 $150.000 $544.455
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 6.000 $20.000 $60.000 $22.000 $26.618
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $20.000 $60.000 $30.000 $48.396
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,321.000 $0.400 $0.600 $1.750 $1.210
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,321.000 $0.400 $0.600 $1.750 $1.210
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 731.000 $0.750 $1.450 $2.750 $1.210
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 731.000 $1.000 $1.450 $2.750 $1.210
REFL PAV MRKR TY II-A-A
EA 14.000 $6.000 $8.850 $35.000 $24.198
PAV SURF PREP FOR MRK (6")
LF 2,642.000 $0.200 $0.600 $2.000 $0.605
REMOVAL OF CONDUIT
LF 211.000 $10.000 $9.000 $10.000 $10.889
D-GR HMA TY-C SAC-A PG70-22
TON 425.000 $185.000 $155.000 $140.000 $149.096
TACK COAT
GAL 232.000 $10.000 $10.000 $8.000 $36.297
INSTALL ELECTRICAL SPLICE
EA 1.000 $200.000 $295.000 $325.000 $72.594
INSTALL CIRCUIT BREAKER
EA 1.000 $500.000 $440.000 $485.000 $725.940
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $8,000.000 $10,000.000 $15,000.000 $18,148.500
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
EA 1.000 $2,500.000 $1,950.000 $2,145.000 $2,419.800
REMOVE CCTV FIELD EQUIPMENT
EA 1.000 $300.000 $1,250.000 $1,375.000 $1,209.900
CONDUIT (PREPARE)
LF 10.000 $3.000 $25.000 $28.000 $12.099
GROUND BOX (PREPARE)
EA 2.000 $400.000 $650.000 $715.000 $846.930
ITS POLE (55 FT)(90 MPH)
EA 1.000 $20,000.000 $28,000.000 $29,600.000 $30,247.500
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 1.000 $4,000.000 $8,000.000 $8,620.000 $9,679.200
ITS POLE MNT CAB (TY 2)(CONF 2)(REM)
EA 1.000 $500.000 $600.000 $660.000 $3,629.700
TMA (STATIONARY)
DAY 40.000 $300.000 $285.000 $200.000 $423.465
INSTALLATION OF CELLULAR MODEM
EA 1.000 $2,500.000 $950.000 $1,045.000 $907.425
Totals: $2,466,921.450 $2,756,557.250 $2,760,856.250 $3,279,027.700