PREPARING ROW
|
STA
|
7.000
|
$2,000.000
|
$5,000.000
|
$1,000.000
|
$7,919.800
|
|
|
REMOVING CONC (PAV)
|
SY
|
74.000
|
$10.000
|
$45.000
|
$100.000
|
$43.556
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
341.000
|
$10.000
|
$15.000
|
$28.000
|
$29.038
|
|
|
REMOVING CONC (CURB)
|
LF
|
663.000
|
$5.000
|
$4.000
|
$4.000
|
$9.679
|
|
|
REMOVING CONC (CTB)
|
LF
|
380.000
|
$20.000
|
$35.000
|
$25.000
|
$48.396
|
|
|
REMOVING STAB BASE & ASPH PAV (9")
|
SY
|
1,312.000
|
$9.000
|
$2.500
|
$10.000
|
$8.580
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
55.000
|
$20.000
|
$35.000
|
$100.000
|
$181.485
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
1,197.000
|
$20.000
|
$40.000
|
$12.000
|
$77.328
|
|
|
FL BS (CMP IN PLC)(RAP) (6")
|
SY
|
1,534.000
|
$10.000
|
$7.000
|
$18.000
|
$14.217
|
|
|
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
|
SY
|
1,591.000
|
$30.000
|
$20.000
|
$24.000
|
$17.613
|
|
|
PRIME COAT (MULTI OPTION)
|
GAL
|
318.000
|
$10.000
|
$10.000
|
$8.000
|
$12.319
|
|
|
CEM STABIL BKFL
|
CY
|
180.000
|
$120.000
|
$175.000
|
$200.000
|
$139.690
|
|
|
CUT & RESTORING PAV
|
SY
|
8.000
|
$150.000
|
$190.000
|
$500.000
|
$608.830
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
639.000
|
$300.000
|
$350.000
|
$400.000
|
$356.921
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
21.000
|
$400.000
|
$530.000
|
$575.000
|
$435.564
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
8.000
|
$320.000
|
$400.000
|
$440.000
|
$362.970
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
52.400
|
$1,100.000
|
$1,500.000
|
$1,100.000
|
$907.425
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
59.700
|
$1,200.000
|
$1,900.000
|
$1,500.000
|
$1,330.890
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
55.400
|
$1,000.000
|
$1,400.000
|
$1,100.000
|
$1,814.850
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
82.000
|
$600.000
|
$500.000
|
$800.000
|
$626.980
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
11,730.000
|
$22.000
|
$30.000
|
$24.000
|
$33.163
|
|
|
APPROACH SLAB (HPC)
|
CY
|
71.000
|
$600.000
|
$700.000
|
$600.000
|
$670.140
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
1,518.120
|
$250.000
|
$240.000
|
$250.000
|
$373.203
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
1.500
|
$1,650.000
|
$850.000
|
$2,000.000
|
$2,325.040
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
104.000
|
$450.000
|
$725.000
|
$400.000
|
$577.485
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
558.000
|
$80.000
|
$75.000
|
$80.000
|
$124.297
|
|
|
RAIL (TY T80SS)
|
LF
|
510.000
|
$90.000
|
$125.000
|
$75.000
|
$126.497
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
137.000
|
$200.000
|
$210.000
|
$250.000
|
$291.478
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$150,000.000
|
$150,000.000
|
$150,000.000
|
$108,891.000
|
|
|
REMOV STR (APPROACH SLAB)
|
EA
|
2.000
|
$9,000.000
|
$1,750.000
|
$30,000.000
|
$5,142.075
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$200,000.000
|
$205,000.000
|
$150,000.000
|
$244,238.500
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$10,000.000
|
$15,000.000
|
$8,000.000
|
$7,864.350
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
90.000
|
$40.000
|
$33.250
|
$50.000
|
$48.947
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
90.000
|
$15.000
|
$12.000
|
$15.000
|
$18.424
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
623.000
|
$20.000
|
$24.500
|
$20.000
|
$42.622
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
623.000
|
$10.000
|
$12.750
|
$10.000
|
$18.424
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
1,320.000
|
$68.000
|
$35.000
|
$96.000
|
$104.658
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
1,320.000
|
$20.000
|
$10.000
|
$8.000
|
$18.975
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
500.000
|
$30.000
|
$30.000
|
$28.000
|
$36.297
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
512.500
|
$40.000
|
$35.000
|
$35.000
|
$50.816
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,500.000
|
$3,200.000
|
$2,650.000
|
$3,024.750
|
|
|
TRANSITION ADJUSTMENT
|
EA
|
1.000
|
$2,000.000
|
$1,400.000
|
$5,000.000
|
$483.960
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$3,300.000
|
$1,400.000
|
$1,500.000
|
$2,056.830
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,487.500
|
$4.000
|
$4.000
|
$1.500
|
$8.469
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
7.000
|
$350.000
|
$350.000
|
$400.000
|
$302.475
|
|
|
CABLE BARRIER TERMINAL SECTION (TL-4)
|
EA
|
2.000
|
$3,000.000
|
$4,500.000
|
$5,000.000
|
$604.950
|
|
|
REMOVE CABLE BARRIER
|
LF
|
200.000
|
$4.000
|
$5.000
|
$4.000
|
$8.469
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
5.000
|
$3,500.000
|
$3,400.000
|
$3,200.000
|
$3,629.700
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$400.000
|
$350.000
|
$500.000
|
$802.965
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
6.000
|
$1,000.000
|
$1,000.000
|
$1,000.000
|
$1,127.480
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
2.000
|
$30,000.000
|
$30,000.000
|
$30,000.000
|
$31,146.555
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$10,000.000
|
$10,000.000
|
$25,000.000
|
$10,064.325
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
1.000
|
$2,500.000
|
$2,600.000
|
$2,860.000
|
$5,928.510
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
595.000
|
$20.000
|
$32.000
|
$35.000
|
$36.297
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
605.000
|
$40.000
|
$40.000
|
$43.500
|
$48.396
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
2,355.000
|
$2.000
|
$3.200
|
$3.750
|
$3.146
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
1,275.000
|
$3.000
|
$5.700
|
$6.250
|
$4.840
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
7.000
|
$1,000.000
|
$1,725.000
|
$1,895.000
|
$1,935.840
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$825.000
|
$915.000
|
$1,200.000
|
$1,107.059
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
2.000
|
$3,000.000
|
$5,000.000
|
$5,485.000
|
$6,033.771
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
1.000
|
$750.000
|
$825.000
|
$480.000
|
$982.439
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$800.000
|
$825.000
|
$480.000
|
$990.908
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
3.000
|
$150.000
|
$450.000
|
$150.000
|
$544.455
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
6.000
|
$20.000
|
$60.000
|
$22.000
|
$26.618
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
10.000
|
$20.000
|
$60.000
|
$30.000
|
$48.396
|
|
REFL PAV MRK TY II (W) 6" (SLD)
|
LF
|
1,321.000
|
$0.400
|
$0.600
|
$1.750
|
$1.210
|
|
REFL PAV MRK TY II (Y) 6" (SLD)
|
LF
|
1,321.000
|
$0.400
|
$0.600
|
$1.750
|
$1.210
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
731.000
|
$0.750
|
$1.450
|
$2.750
|
$1.210
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
731.000
|
$1.000
|
$1.450
|
$2.750
|
$1.210
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
14.000
|
$6.000
|
$8.850
|
$35.000
|
$24.198
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,642.000
|
$0.200
|
$0.600
|
$2.000
|
$0.605
|
|
|
REMOVAL OF CONDUIT
|
LF
|
211.000
|
$10.000
|
$9.000
|
$10.000
|
$10.889
|
|
|
D-GR HMA TY-C SAC-A PG70-22
|
TON
|
425.000
|
$185.000
|
$155.000
|
$140.000
|
$149.096
|
|
|
TACK COAT
|
GAL
|
232.000
|
$10.000
|
$10.000
|
$8.000
|
$36.297
|
|
|
INSTALL ELECTRICAL SPLICE
|
EA
|
1.000
|
$200.000
|
$295.000
|
$325.000
|
$72.594
|
|
|
INSTALL CIRCUIT BREAKER
|
EA
|
1.000
|
$500.000
|
$440.000
|
$485.000
|
$725.940
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
8.000
|
$8,000.000
|
$10,000.000
|
$15,000.000
|
$18,148.500
|
|
|
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
|
EA
|
1.000
|
$2,500.000
|
$1,950.000
|
$2,145.000
|
$2,419.800
|
|
|
REMOVE CCTV FIELD EQUIPMENT
|
EA
|
1.000
|
$300.000
|
$1,250.000
|
$1,375.000
|
$1,209.900
|
|
|
CONDUIT (PREPARE)
|
LF
|
10.000
|
$3.000
|
$25.000
|
$28.000
|
$12.099
|
|
|
GROUND BOX (PREPARE)
|
EA
|
2.000
|
$400.000
|
$650.000
|
$715.000
|
$846.930
|
|
|
ITS POLE (55 FT)(90 MPH)
|
EA
|
1.000
|
$20,000.000
|
$28,000.000
|
$29,600.000
|
$30,247.500
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)
|
EA
|
1.000
|
$4,000.000
|
$8,000.000
|
$8,620.000
|
$9,679.200
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)(REM)
|
EA
|
1.000
|
$500.000
|
$600.000
|
$660.000
|
$3,629.700
|
|
|
TMA (STATIONARY)
|
DAY
|
40.000
|
$300.000
|
$285.000
|
$200.000
|
$423.465
|
|
|
INSTALLATION OF CELLULAR MODEM
|
EA
|
1.000
|
$2,500.000
|
$950.000
|
$1,045.000
|
$907.425
|
|
Totals: |
$2,466,921.450
|
$2,756,557.250
|
$2,760,856.250
|
$3,279,027.700
|