Show Job Controls
Bid Cobra

EL PASO IH 10 (2121-02-182)

Items: 31

County: EL PASO
Length: N/A
Highway: IH 10
District: EL PASO
Control Number: 2121-02-182
DBE Goal: 0.0%
Project: F 2024(503)
Guaranty: N/A
Time: 51 WORKING DAYS
Engineer's Estimate: $831,503.40
Date: 12/05/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$831,503.40
$722,722.00
Over/Under Est: -13.08% -$108,781.40
$757,086.00
Over/Under Est: -8.95% -$74,417.40
Amt Left: 4.75% $34,364.00
Over/Under Est: 25.46% $211,675.60
Amt Left: 44.34% $320,457.00
Delta: -37.79% -$286,093.00
Subcontractor Percentage Amount
FC TRAFFIC CONTROL, INC. 16.57% $119,755.04
HAWK CONSTRUCTION 16.57% $119,755.04
DUSTROL, INC. 3.91% $28,258.43
STRAIGHT EDGE CONTRACTORS LLC 0.85% $6,143.14
Total: 37.90% $273,911.65

Bid Items & Bid Tabulations

31 Total 0 of 31
EL PASO  |  IH 10  |  EL PASO  |  2121-02-182  |  12/05/2023  |  $831,503.40  |  F 2024(503)  |  REHAB BRIDGE  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
HAWK CONSTRUCTION
INTERNATIONAL EAGLE ENTERPRISES, INC.
PLANE ASPH CONC PAV (0" TO 1/2" MICRO)
SY 3,140.000 $20.000 $9.000 $8.000 $12.000
FLOWABLE BACKFILL
CY 15.000 $250.000 $650.000 $1,050.000 $200.000
CONC STR REPAIR (EPOXY MORTAR)
SF 70.000 $300.000 $250.000 $440.000 $320.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 40.000 $500.000 $400.000 $550.000 $450.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 130.000 $250.000 $375.000 $300.000 $350.000
CONC STR REPAIR (STANDARD)
SF 130.000 $350.000 $430.000 $175.000 $350.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 702.000 $45.000 $57.000 $33.000 $35.000
MULTI-LAYER POLYMER OVERLAY
SY 3,140.000 $120.000 $45.000 $86.000 $125.000
SHOT BLASTING
SY 3,140.000 $10.000 $4.000 $12.000 $40.000
MOBILIZATION
LS 1.000 $72,409.400 $219,073.000 $45,000.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $35,000.000 $8,800.000 $36,000.000 $50,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 30.000 $3.000 $175.000 $145.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 30.000 $4.000 $125.000 $90.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 480.000 $3.500 $21.000 $30.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 480.000 $1.500 $11.000 $10.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 215.000 $6.000 $27.000 $12.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 215.000 $6.000 $11.000 $9.000 $1.000
REFL PAV MRK TY II (W) 6" (BRK)
LF 680.000 $0.300 $2.000 $2.750 $4.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 680.000 $0.300 $2.000 $2.750 $3.800
REFL PAV MRK TY II (W) 8" (SLD)
LF 500.000 $0.600 $2.000 $3.250 $5.000
REFL PAV MRK TY II (W) (ARROW)
EA 2.000 $100.000 $75.000 $220.000 $800.000
REFL PAV MRK TY II (W) (DBL ARROW)
EA 2.000 $150.000 $150.000 $250.000 $800.000
REFL PAV MRK TY II (W) (WORD)
EA 4.000 $150.000 $100.000 $220.000 $600.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 700.000 $0.300 $2.000 $3.500 $4.000
REFL PAV MRK TY II (Y) 8" (SLD)
LF 120.000 $0.800 $2.000 $9.000 $5.000
REPLACE (STEEL RAIL)
LF 10.000 $100.000 $1,200.000 $1,200.000 $1,200.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 60.000 $125.000 $125.000 $400.000 $65.000
CARBON FIBER REINF POLYMER PROTECTION
SF 45.000 $150.000 $475.000 $500.000 $600.000
TMA (STATIONARY)
DAY 8.000 $300.000 $2,000.000 $600.000 $150.000
TMA (MOBILE OPERATION)
HR 4.000 $200.000 $500.000 $100.000 $400.000
BRIDGE SUBSTRUCTURE CLEANING (BENT)
EA 6.000 $500.000 $1,600.000 $2,100.000 $3,000.000
Totals: $831,503.400 $722,722.000 $757,086.000 $1,043,179.000