Bid Cobra

EL PASO IH 10 (2121-02-179)

Items: 43

County: EL PASO
Length: 0.0000 MILES
Highway: IH 10
District: EL PASO
Control Number: 2121-02-179
DBE Goal: 7.0%
Project: STP 2025(290)HES
Guaranty: $100,000.00
Time: 340 WORKING DAYS
Engineer's Estimate: $6,053,315.43
Date: 12/03/2024 (1 year ago)
Contract Number: 12243007
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184481
Project Description: SAFETY LIGHTING
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$6,053,315.43
$6,226,703.14
Over/Under Est: 2.86% $173,387.71
Over/Under Est: 10.27% $621,619.84
Amt Left: 7.2% $448,232.13

Bid Items & Bid Tabulations

43 Total 0 of 43
EL PASO  |  IH 10  |  EL PASO  |  2121-02-179  |  12/03/2024  |  $6,053,315.43  |  STP 2025(290)HES  |  HAZARD ELIM & SAFETY  |  340 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRI STATE ELECTRIC, LTD.
MARTINEZ BROS. CONTRACTORS, LLC
EXCAV (SPECIAL)
CY 10.650 $1,800.000 $1,000.000 $1,150.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 480.000 $770.000 $1,050.000 $862.500
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 1,222.000 $396.000 $349.670 $460.000
RIPRAP (CONC)(4 IN)
CY 38.400 $600.000 $926.180 $345.000
RIPRAP (CONC) (CL B) (6 IN)
CY 8.000 $455.660 $1,250.000 $910.800
MOBILIZATION
LS 1.000 $35,000.000 $225,000.000 $522,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $8,500.000 $12,000.000 $20,102.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 260.000 $150.000 $138.360 $115.000
TMA (STATIONARY)
DAY 260.000 $220.000 $726.510 $511.750
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 105.000 $8.290 $8.980 $9.200
BIODEG EROSN CONT LOGS (REMOVE)
LF 105.000 $3.200 $2.900 $1.150
MTL W-BEAM GD FEN (STEEL POST)
LF 550.000 $58.000 $56.500 $42.550
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 14.000 $3,950.000 $2,960.000 $2,300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 14.000 $4,185.000 $6,055.000 $3,795.000
REMOVE RD IL ASM (CTB MOUNT)
EA 48.000 $550.000 $968.630 $1,150.000
REMOVE RD IL ASM (TRANS-BASE)
EA 38.000 $1,200.000 $725.000 $1,150.000
REPLACE LUMINAIRE W/(150W EQ) LED
EA 31.000 $500.000 $750.000 $690.000
REPLACE LUMINAIRE W/(250W EQ) LED
EA 47.000 $600.000 $783.330 $690.000
IN RD IL (TY SA) 30T-4-4 (250W EQ) LED
EA 32.000 $5,750.000 $5,950.000 $5,865.000
IN RD IL (TY SA) 30T-8 (250W EQ) LED
EA 8.000 $3,862.000 $4,693.000 $4,830.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 5.000 $4,568.000 $4,840.500 $5,520.000
IN RD IL (TY SA) 40T-8-8 (250W EQ) LED
EA 7.000 $6,350.000 $6,054.200 $6,900.000
IN RD IL (TY SA) 40T-12 (250W EQ) LED
EA 20.000 $5,890.000 $6,203.000 $5,635.000
IN RD IL (TY SA) 50T-12-12(400W EQ)LED
EA 61.000 $7,800.000 $7,000.000 $7,705.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 15.000 $50,733.000 $52,000.000 $56,350.000
LED HI MST IL ASM (6 FIXT) (TY B)
EA 15.000 $35,000.000 $36,000.000 $49,450.000
REPLC LED HI MST IL(6 FIXT) (TY B)
EA 2.000 $12,500.000 $11,270.000 $8,970.000
CONDT (PVC) (SCH 40) (2")
LF 20,136.000 $32.000 $19.550 $14.950
CONDT (PVC) (SCH 40) (2") (BORE)
LF 21,417.000 $39.000 $38.500 $29.900
CONDUIT (PREPARE)
LF 11.000 $15.000 $3.840 $5.750
ELEC CONDR (NO.8) INSULATED
LF 15,672.000 $3.100 $2.150 $2.875
ELEC CONDR (NO.6) INSULATED
LF 117,360.000 $3.250 $3.040 $3.450
GROUND BOX TY A (122311)W/APRON
EA 112.000 $1,480.000 $1,693.780 $1,150.000
REMOVE GROUND BOX
EA 11.000 $350.000 $476.440 $345.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $680.000 $914.900 $920.000
ELC SRV TY A 240/480 060(NS)SS(E)GC(O)
EA 14.000 $10,150.000 $10,000.000 $12,650.000
ELC SRV TY A 240/480 100(NS)SS(E)GC(O)
EA 7.000 $11,000.000 $11,400.000 $12,650.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1
EA 50.000 $30.000 $36.430 $34.500
REMOVAL OF CABLES
LF 19,355.000 $3.500 $1.700 $1.725
INSTALL CIRCUIT BREAKER
EA 1.000 $605.000 $198.000 $345.000
IRRIG SYS OPERATION AND REPAIR
MO 5.000 $5,000.000 $1,350.000 $1,725.000
PLANT BED MAINTENANCE
CYC 5.000 $3,000.000 $1,450.000 $1,150.000
GROUND BOX (PREPARE)
EA 11.000 $250.000 $659.000 $575.000
Totals: $6,053,315.430 $6,226,703.142 $6,674,935.275