EL PASO VARIOUS (0924-00-162)
Items: 33
County: EL PASO
Length: 0.2000 MILES
Highway: VARIOUS
District: EL PASO
Control Number: 0924-00-162
DBE Goal: 0.0%
Project: F 2026(667)
Guaranty: $15,000.00
Time: 50 WORKING DAYS
Engineer's Estimate: $769,257.28
Date: 06/02/2026 (8 days ago)
Contract Number: 6263029
Type: BRIDGE MAINTENANCE
Project ID: A00188372
Contract Type: Federal
Project Description: FY 2026 BRIDGE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EL PASO VARIOUS (0924-00-162)
Project Name: N/A
Project: F 2026(667)
Length: 0.2000 MILES
Project Type: CONSTRUCTION
Limits From: DISTRICTWIDE (BRIDGE MAINTENANCE)
Limits To: .
Project Description: FY 2026 BRIDGE MAINTENANCE
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$769,257.28 | |||
| $812,409.50 |
5.61%
$43,152.22
|
|||
| $1,020,230.00 |
32.63%
$250,972.72
|
25.58%
$207,820.50
|
||
| $1,075,145.90 |
39.76%
$305,888.62
|
32.34%
$262,736.40
|
-5.38%
-$54,915.90
|
|
| $1,133,660.50 |
47.37%
$364,403.22
|
39.54%
$321,251.00
|
-5.44%
-$58,514.60
|
|
| $1,143,917.44 |
48.7%
$374,660.16
|
40.81%
$331,507.94
|
-0.90%
-$10,256.94
|
|
| $1,268,268.00 |
64.87%
$499,010.72
|
56.11%
$455,858.50
|
-10.87%
-$124,350.56
|
E
Engineer's Estimate
$769,257.28
$812,409.50
Over/Under Est:
5.61%
$43,152.22
$1,020,230.00
Over/Under Est:
32.63%
$250,972.72
Amt Left:
25.58%
$207,820.50
$1,075,145.90
Over/Under Est:
39.76%
$305,888.62
Amt Left:
32.34%
$262,736.40
Delta:
-5.38%
-$54,915.90
$1,133,660.50
Over/Under Est:
47.37%
$364,403.22
Amt Left:
39.54%
$321,251.00
Delta:
-5.44%
-$58,514.60
$1,143,917.44
Over/Under Est:
48.7%
$374,660.16
Amt Left:
40.81%
$331,507.94
Delta:
-0.90%
-$10,256.94
$1,268,268.00
Over/Under Est:
64.87%
$499,010.72
Amt Left:
56.11%
$455,858.50
Delta:
-10.87%
-$124,350.56
Bid Items & Bid Tabulations
33
Total
0 of 33
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $37,500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| Total: | $87,500.00 |