EL PASO FM 76 (0674-01-083)

Items: 44

County: EL PASO
Length: 0.0000 MILES
Highway: FM 76
District: EL PASO
Control Number: 0674-01-083
DBE Goal: 0.0%
Project: F 2026(468)
Guaranty: $26,000.00
Time: 124 WORKING DAYS
Engineer's Estimate: $1,307,462.30
Date: 04/08/2026 (2 months ago)
Contract Number: 4263223
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00212674
Contract Type: Federal
Project Description: CURB RAMP / ADA IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,307,462.30
$1,248,951.33
Over/Under Est: -4.48% -$58,510.97
Over/Under Est: -0.65% -$8,462.30
Amt Left: 4.01% $50,048.67
Over/Under Est: 5.47% $71,452.95
Amt Left: 10.41% $129,963.92
Delta: -6.15% -$79,915.25
Over/Under Est: 9% $117,662.45
Amt Left: 14.11% $176,173.42
Delta: -3.35% -$46,209.50
$1,580,000.00
Over/Under Est: 20.84% $272,537.70
Amt Left: 26.51% $331,048.67
Delta: -10.87% -$154,875.25
$1,737,742.00
Over/Under Est: 32.91% $430,279.70
Amt Left: 39.14% $488,790.67
Delta: -9.98% -$157,742.00

Bid Items & Bid Tabulations

44 Total 0 of 44
EL PASO  |  FM 76  |  EL PASO  |  0674-01-083  |  04/08/2026  |  $1,307,462.30  |  F 2026(468)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  124 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SYNERGY PROJECT CONTRACTORS, INC.
HORIZONE CONSTRUCTION I, LTD
EL PASO A.R.C. ELECTRIC, INC.
INTERNATIONAL EAGLE ENTERPRISES, INC.
HAWK CONSTRUCTION
ICOS MANAGEMENT, LLC
REMOV CONC (MEDIANS)
SY 4.000 $16.000 $12.150 $19.910 $125.000 $2,500.000 $430.000 $428.000
REMOV CONC (DRIVEWAYS)
SY 4,873.000 $17.000 $13.200 $15.710 $20.000 $45.000 $36.000 $16.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 1,982.000 $14.000 $20.660 $15.710 $20.000 $40.000 $30.000 $13.000
REMOV CONC (CURB)
LF 3,285.000 $5.000 $9.720 $19.340 $10.000 $15.000 $11.000 $11.000
DRILL SHAFT (TRF SIG POLE) (24 IN)
LF 48.000 $425.000 $243.000 $357.040 $450.000 $286.000 $345.000 $321.000
ADJUSTING MANHOLES
EA 22.000 $1,575.000 $1,093.500 $685.300 $1,500.000 $1,000.000 $1,700.000 $1,070.000
MOBILIZATION
LS 1.000 $115,000.000 $48,600.000 $46,994.180 $30,000.000 $75,000.000 $48,626.000 $57,200.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $11,000.000 $6,682.500 $14,141.230 $12,000.000 $15,000.000 $11,500.000 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 124.000 $150.000 $103.280 $90.750 $190.000 $160.000 $120.000 $161.000
TMA (STATIONARY)
DAY 124.000 $300.000 $364.500 $196.640 $380.000 $350.000 $450.000 $214.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 300.000 $5.000 $10.940 $11.540 $10.000 $18.000 $10.000 $2.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $1.000 $4.860 $3.270 $2.000 $1.000 $5.000 $1.000
COLORED TEXTURED CONC (5")
SY 24.000 $125.000 $122.720 $102.290 $200.000 $80.000 $500.000 $321.000
CONC CURB (TY II)
LF 2,346.000 $15.000 $32.810 $25.710 $20.000 $18.000 $27.000 $54.000
DRIVEWAYS (CONC)
SY 4,843.000 $85.000 $87.480 $84.060 $85.000 $70.000 $95.000 $161.000
CONC SIDEWALKS (5")
SY 1,535.000 $72.000 $57.110 $67.550 $70.000 $50.000 $94.000 $77.000
CURB RAMPS (TY 1)
EA 10.000 $2,800.000 $2,490.750 $1,790.290 $2,500.000 $1,800.000 $2,250.000 $3,210.000
CURB RAMPS (TY 2)
EA 20.000 $2,200.000 $2,430.000 $1,630.900 $3,500.000 $1,800.000 $2,300.000 $3,210.000
CURB RAMPS (TY 7)
EA 17.000 $2,000.000 $3,037.500 $1,740.630 $3,100.000 $1,800.000 $2,100.000 $3,424.000
CURB RAMPS (TY 21)
EA 10.000 $2,800.000 $2,673.000 $1,838.190 $3,400.000 $2,000.000 $2,600.000 $3,745.000
CONC MEDIAN
SY 13.000 $130.000 $87.480 $89.780 $130.000 $1,000.000 $500.000 $321.000
CONDT (PVC) (SCH 40) (3")
LF 200.000 $30.000 $27.950 $29.140 $30.000 $23.500 $28.000 $32.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 175.000 $35.000 $32.810 $40.230 $50.000 $32.250 $40.000 $80.000
CONDUIT (PREPARE)
LF 765.000 $5.000 $2.430 $3.120 $5.000 $2.500 $3.500 $4.000
ELEC CONDR (NO.8) INSULATED
LF 360.000 $2.000 $3.650 $4.910 $4.100 $4.000 $5.000 $3.000
GROUND BOX TY A (122311)
EA 1.000 $1,200.000 $972.000 $1,784.900 $1,200.000 $1,450.000 $1,800.000 $1,391.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $1,700.000 $1,579.500 $2,710.060 $2,100.000 $2,175.000 $2,650.000 $1,605.000
REMOVE GROUND BOX
EA 1.000 $500.000 $364.500 $1,589.930 $400.000 $1,275.000 $1,600.000 $910.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 12.000 $700.000 $668.250 $1,823.330 $500.000 $1,500.000 $1,800.000 $1,284.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 2,390.000 $11.000 $12.150 $13.750 $13.000 $13.000 $13.500 $12.000
RE PM TY II (W) 24" (SLD)
LF 2,390.000 $5.000 $6.080 $6.880 $8.000 $7.000 $7.000 $6.000
ELIM EXT PM & MRKS (6")
LF 181.000 $1.800 $2.730 $3.090 $3.250 $5.000 $3.000 $3.000
ELIM EXT PM & MRKS (24")
LF 1,293.000 $2.000 $8.510 $9.630 $9.000 $10.000 $10.000 $8.000
PAV SURF PREP FOR MRK (24")
LF 2,390.000 $2.000 $2.430 $2.750 $4.000 $3.500 $2.650 $3.000
INSTALL HWY TRF SIG (UPGRADE)
EA 1.000 $19,000.000 $9,112.500 $35,122.750 $45,000.000 $28,000.000 $33,650.000 $41,730.000
PED SIG SEC (LED)(COUNTDOWN)
EA 10.000 $1,000.000 $1,093.500 $2,078.080 $1,200.000 $1,675.000 $2,000.000 $1,070.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 1,690.000 $3.750 $4.860 $4.480 $4.000 $3.750 $5.000 $4.000
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
LF 2,040.000 $6.000 $3.650 $2.960 $2.100 $2.500 $3.000 $3.000
PED POLE ASSEMBLY
EA 7.000 $2,500.000 $2,794.500 $2,139.950 $3,000.000 $1,720.000 $2,050.000 $2,996.000
RELOCATE PED POLE ASSEMBLY
EA 1.000 $6,000.000 $4,617.000 $979.740 $2,500.000 $785.000 $950.000 $2,996.000
RELOCATE PED PUSH BUTTON POST ASSEM
EA 1.000 $10,000.000 $4,252.500 $532.840 $500.000 $430.000 $525.000 $2,996.000
PED DETECT PUSH BUTTON (APS)
EA 8.000 $1,400.000 $729.000 $1,675.870 $900.000 $1,340.000 $1,600.000 $1,391.000
PED DETECTOR CONTROLLER UNIT
EA 2.000 $4,100.000 $3,796.880 $6,961.300 $4,000.000 $5,575.000 $6,700.000 $5,778.000
GROUND BOX (PREPARE)
EA 8.000 $600.000 $1,215.000 $1,123.140 $300.000 $900.000 $1,100.000 $535.000
Totals: $1,307,462.300 $1,248,951.330 $1,299,000.000 $1,378,915.250 $1,425,124.750 $1,580,000.000 $1,737,742.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $15,000.00