ECTOR IH0020 (6436-80-001)

Items: 26

County: ECTOR
Length: N/A
Highway: IH0020
District: ODESSA
Control Number: 6436-80-001
DBE Goal: N/A
Project: RMC - 643680001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $469,000.00
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: TRAFFIC CONTROL SERVICES
Mail/Deliver Bids To: N/A
SERGIO MIRANDA
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$469,000.00
$404,325.00
Over/Under Est: -13.79% -$64,675.00
Over/Under Est: -9.3% -$43,625.00
Amt Left: 5.21% $21,050.00

Bid Items & Bid Tabulations

26 Total 0 of 26
ECTOR  |  IH0020  |  ODESSA  |  6436-80-001  |  05/05/2023  |  $469,000.00  |  RMC - 643680001  |  TRAF CONTROL SERVICES  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NIXON ENGINEERING
BARRICADES UNLIMITED
MOBILIZATION (CALLOUT)
EA 200.000 $500.000 $100.000 $800.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 125.000 $100.000 $100.000 $50.000
TMA (STATIONARY)
DAY 150.000 $250.000 $200.000 $200.000
TMA (MOBILE OPERATION)
HR 750.000 $125.000 $160.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 50.000 $750.000 $850.000 $500.000
LANE CLOSURE (SETUP AND REMOV)(TY 2)
EA 35.000 $1,000.000 $1,800.000 $500.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 30.000 $800.000 $200.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 5)
EA 25.000 $800.000 $200.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 9)
EA 10.000 $500.000 $200.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 11)
EA 5.000 $500.000 $800.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 12)
EA 5.000 $100.000 $500.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 16)
EA 5.000 $100.000 $250.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 17)
EA 5.000 $100.000 $250.000 $300.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 125.000 $100.000 $40.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 200.000 $90.000 $50.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 125.000 $25.000 $50.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 100.000 $25.000 $25.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 9)
HR 50.000 $90.000 $25.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 11)
HR 15.000 $50.000 $25.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 12)
HR 15.000 $50.000 $25.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 16)
HR 25.000 $25.000 $25.000 $25.000
LANE CLOSURE (MAINTENANCE) (TY 17)
HR 10.000 $50.000 $25.000 $25.000
MOBILE OPERATIONS
HR 300.000 $100.000 $70.000 $90.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 200.000 $50.000 $80.000 $50.000
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 200.000 $60.000 $80.000 $50.000
INST/REMV WKZN SPEED REDUCTION SIGNS
EA 150.000 $30.000 $98.000 $150.000
Totals: $469,000.000 $404,325.000 $425,375.000