ECTOR IH0020 (6319-11-001)

Items: 17

County: ECTOR
Length: N/A
Highway: IH0020
District: ODESSA
Control Number: 6319-11-001
DBE Goal: N/A
Project: RMC - 631911001
Guaranty: N/A
Time: 40 W
Engineer's Estimate: $521,063.25
Date: 08/09/2017 (8 years ago)
Contract Number: N/A
Type: SPECIALTY MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$521,063.25
$549,273.52
Over/Under Est: 5.41% $28,210.27
Over/Under Est: 8.72% $45,452.15
Amt Left: 3.14% $17,241.88
$577,772.80
Over/Under Est: 10.88% $56,709.55
Amt Left: 5.19% $28,499.28
Delta: -1.99% -$11,257.40
Over/Under Est: 24.97% $130,105.15
Amt Left: 18.55% $101,894.88
Delta: -12.70% -$73,395.60
Over/Under Est: 38.1% $198,504.90
Amt Left: 31% $170,294.63
Delta: -10.50% -$68,399.75
$863,429.40
Over/Under Est: 65.71% $342,366.15
Amt Left: 57.19% $314,155.88
Delta: -19.99% -$143,861.25

Bid Items & Bid Tabulations

17 Total 0 of 17
ECTOR  |  IH0020  |  ODESSA  |  6319-11-001  |  08/09/2017  |  $521,063.25  |  RMC - 631911001  |  SPECIALTY MRK  |  40 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
PMI PAVEMENT MARKING, INC.
DOUBLE A CONTRACTING, L.P.
MIJELUM, L.L.C.
TOTAL HIGHWAY MAINTENANCE, LLC
BARRICADES UNLIMITED
STRIPE-A-ZONE, INC.
MOBILIZATION
LS 1.000 $5,000.000 $1,925.280 $5,000.000 $1.000 $35,000.000 $5,000.000 $48,500.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 462.000 $7.000 $5.890 $6.000 $7.000 $6.300 $6.950 $8.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 21,193.000 $9.000 $11.620 $11.800 $10.000 $12.100 $15.000 $15.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 712.000 $190.000 $163.290 $175.000 $195.000 $215.000 $230.000 $255.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 19.000 $350.000 $276.140 $290.000 $300.000 $350.000 $405.000 $450.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 9.000 $250.000 $309.350 $260.000 $310.000 $400.000 $415.000 $500.000
PREFAB PAV MRK TY C (W) (WORD)
EA 305.000 $250.000 $219.540 $215.000 $240.000 $290.000 $300.000 $305.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 16.000 $500.000 $400.170 $460.000 $530.000 $650.000 $595.000 $900.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 555.000 $30.000 $19.550 $20.000 $40.000 $55.000 $27.000 $55.550
ELIM EXT PAV MRK & MRKS (12")
LF 1,129.000 $1.000 $1.230 $1.500 $1.000 $1.100 $1.550 $2.000
ELIM EXT PAV MRK & MRKS (24")
LF 21,241.000 $1.250 $2.420 $2.500 $1.800 $1.600 $3.300 $2.400
ELIM EXT PAV MRK & MRKS (ARROW)
EA 725.000 $35.000 $29.050 $27.000 $45.000 $20.000 $25.000 $47.850
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 15.000 $45.000 $46.460 $50.000 $55.000 $30.000 $28.000 $71.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 305.000 $45.000 $34.870 $40.000 $50.000 $25.000 $30.000 $145.000
ELIM EXT PAV MRK & MRKS (RR XING)
EA 16.000 $100.000 $98.780 $100.000 $100.000 $80.000 $35.000 $350.000
ELIM EXT PAV MRK & MRKS (36")(YLD TRI)
EA 472.000 $16.000 $4.880 $5.000 $45.000 $10.000 $4.000 $22.000
ELIM EXT PAV MRK & MRKS (UTURN ARROW)
EA 9.000 $45.000 $87.690 $100.000 $55.000 $35.000 $31.000 $75.000
Totals: $521,063.250 $549,273.520 $566,515.400 $577,772.800 $651,168.400 $719,568.150 $863,429.400