Bid Cobra

ECTOR SH 191 (2296-01-056)

Items: 17

County: ECTOR
Length: N/A
Highway: SH 191
District: ODESSA
Control Number: 2296-01-056
DBE Goal: N/A
Project: STP 2B20(122)HES
Guaranty: N/A
Time: 122 WORKING DAYS
Engineer's Estimate: $2,129,943.76
Date: 11/04/2020 (5 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$2,129,943.76
$2,056,073.16
Over/Under Est: -3.47% -$73,870.60
$2,129,943.61
Over/Under Est: 0% -$0.15
Amt Left: 3.59% $73,870.45
$2,340,527.25
Over/Under Est: 9.89% $210,583.49
Amt Left: 13.83% $284,454.09
Delta: -9.89% -$210,583.64
$2,495,086.66
Over/Under Est: 17.14% $365,142.90
Amt Left: 21.35% $439,013.50
Delta: -6.60% -$154,559.41
Over/Under Est: 21.88% $465,966.01
Amt Left: 26.26% $539,836.61
Delta: -4.04% -$100,823.11
Over/Under Est: 22.88% $487,308.22
Amt Left: 27.29% $561,178.82
Delta: -0.82% -$21,342.21
$3,158,683.60
Over/Under Est: 48.3% $1,028,739.84
Amt Left: 53.63% $1,102,610.44
Delta: -20.69% -$541,431.62
Over/Under Est: 57.57% $1,226,107.49
Amt Left: 63.23% $1,299,978.09
Delta: -6.25% -$197,367.65

Bid Items & Bid Tabulations

17 Total 0 of 17
ECTOR  |  SH 191  |  ODESSA  |  2296-01-056  |  11/04/2020  |  $2,129,943.76  |  STP 2B20(122)HES  |  INSTL MEDIAN BARRIER  |  122 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MIJELUM, L.L.C.
BT CONSTRUCTORS, LLC
HJC FARMS, INC.
DAN WILLIAMS COMPANY
B & MS CONSTRUCTION, INC.
SCR CIVIL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
DOUBLE H CONTRACTING INC.
EXCAVATION (ROADWAY)
CY 475.000 $8.250 $10.000 $15.290 $15.000 $50.000 $10.580 $30.000 $30.000 $75.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 19,294.000 $5.500 $6.000 $3.890 $15.000 $3.250 $8.630 $20.000 $30.000 $30.000
BLADING
HR 50.000 $260.000 $150.000 $270.000 $150.000 $100.000 $185.000 $290.000 $150.000 $100.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 429,593.000 $0.110 $0.120 $0.200 $0.250 $0.120 $0.250 $0.060 $0.200 $0.250
RIPRAP (MOW STRIP)(4 IN)
CY 3,006.000 $357.000 $400.000 $270.000 $400.000 $262.000 $515.000 $355.000 $500.000 $550.000
MOBILIZATION
LS 1.000 $58,466.220 $10.000 $134,000.000 $50,000.000 $245,000.000 $20,000.000 $264,000.000 $300,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,500.000 $5,000.000 $10,208.000 $3,000.000 $40,000.000 $5,000.000 $29,000.000 $8,500.000 $10,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 420.000 $8.000 $10.000 $7.460 $5.000 $10.000 $7.390 $8.400 $18.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 420.000 $2.800 $5.000 $3.770 $1.000 $3.000 $1.100 $2.700 $9.000 $5.000
CABLE BARRIER SYSTEM (TL-4)
LF 54,362.000 $9.680 $9.000 $14.000 $9.500 $14.000 $9.500 $8.700 $7.500 $9.000
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 4,340.000 $11.500 $12.000 $17.000 $11.250 $17.000 $11.900 $12.000 $8.500 $15.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 20.000 $4,300.000 $2,800.000 $2,800.000 $3,000.000 $6,000.000 $4,150.000 $3,200.000 $3,500.000 $3,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $924.490 $900.000 $628.000 $750.000 $1,500.000 $570.000 $2,000.000 $850.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 4.000 $82.200 $100.000 $120.000 $100.000 $150.000 $100.000 $200.000 $250.000 $500.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $69.410 $90.000 $381.000 $140.000 $125.000 $89.500 $200.000 $100.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $17,900.000 $1,000.000 $5,500.000 $50.000 $20,000.000 $6,300.000 $4,400.000 $12,500.000 $150.000
TMA (STATIONARY)
DAY 107.000 $210.000 $300.000 $180.000 $250.000 $300.000 $250.000 $475.000 $350.000 $250.000
Totals: $2,129,943.760 $2,056,073.160 $2,129,943.610 $2,340,527.250 $2,495,086.660 $2,595,909.770 $2,617,251.980 $3,158,683.600 $3,356,051.250