ECTOR VARIOUS (0906-00-292)

Items: 16

County: ECTOR
Length: 0.0000 MILES
Highway: VARIOUS
District: ODESSA
Control Number: 0906-00-292
DBE Goal: 0.0%
Project: C 906-00-292
Guaranty: $30,000.00
Time: 151 WORKING DAYS
Engineer's Estimate: $727,299.59
Date: 01/06/2026 (5 months ago)
Contract Number: 1263024
Type: BRIDGE MAINTENANCE
Project ID: A00214748
Project Description: BRIDGE MAINTENANCE PROGRAM (2026) - SOUTH SEGMENT
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (12)
E
Engineer's Estimate
$727,299.59
$498,387.00
Over/Under Est: -31.47% -$228,912.59
Over/Under Est: -18.69% -$135,937.59
Amt Left: 18.66% $92,975.00
$630,895.00
Over/Under Est: -13.26% -$96,404.59
Amt Left: 26.59% $132,508.00
Delta: -6.69% -$39,533.00
$719,890.00
Over/Under Est: -1.02% -$7,409.59
Amt Left: 44.44% $221,503.00
Delta: -14.11% -$88,995.00
Over/Under Est: -0.48% -$3,521.59
Amt Left: 45.22% $225,391.00
Delta: -0.54% -$3,888.00
Over/Under Est: 0.78% $5,671.41
Amt Left: 47.07% $234,584.00
Delta: -1.27% -$9,193.00
Over/Under Est: 7.39% $53,740.41
Amt Left: 56.71% $282,653.00
Delta: -6.56% -$48,069.00
Over/Under Est: 7.88% $57,300.41
Amt Left: 57.43% $286,213.00
Delta: -0.46% -$3,560.00
Over/Under Est: 19.2% $139,650.41
Amt Left: 73.95% $368,563.00
Delta: -10.50% -$82,350.00
Over/Under Est: 29.44% $214,150.41
Amt Left: 88.9% $443,063.00
Delta: -8.59% -$74,500.00
Over/Under Est: 34.39% $250,090.41
Amt Left: 96.11% $479,003.00
Delta: -3.82% -$35,940.00
Over/Under Est: 53.39% $388,300.41
Amt Left: 123.84% $617,213.00
Delta: -14.14% -$138,210.00

Bid Items & Bid Tabulations

16 Total 0 of 16
ECTOR  |  VARIOUS  |  ODESSA  |  0906-00-292  |  01/06/2026  |  $727,299.59  |  C 906-00-292  |  BRIDGE MAINT  |  151 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PREMIER CONTRACTORS LLC
BK FIELD OPERATIONS LLC
MPB, INC.
RELMCO, INC.
PATHFIELD INVESTMENTS LLC
BECK-REIT & SONS, LTD.
RAGLE CONSTRUCTION, INC.
TI-ZACK CONCRETE, LLC
BLACKSMITH VENTURES LLC
GREY SKY CONSTRUCTION LLC
SCR CIVIL CONSTRUCTION, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
EMBANK (FNL)(OC)(TY C)
CY 59.000 $16.370 $100.000 $100.000 $250.000 $150.000 $110.000 $110.000 $85.000 $68.750 $750.000 $100.000 $135.000 $100.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 18.000 $29.210 $100.000 $400.000 $400.000 $250.000 $760.000 $250.000 $550.000 $187.500 $300.000 $500.000 $400.000 $500.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,278.000 $150.000 $200.000 $100.000 $100.000 $165.000 $200.000 $150.000 $125.000 $168.750 $150.000 $250.000 $200.000 $300.000
CONC STR REPAIR (STANDARD)
SF 27.000 $150.000 $200.000 $200.000 $85.000 $190.000 $240.000 $180.000 $190.000 $312.500 $150.000 $500.000 $250.000 $325.000
CLEANING AND SEALING EXISTING JOINTS
LF 365.000 $35.000 $45.000 $55.000 $37.000 $55.000 $25.000 $65.000 $42.000 $125.000 $45.000 $80.000 $25.000 $75.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 170.000 $44.950 $45.000 $60.000 $106.000 $72.000 $65.000 $55.000 $23.000 $96.250 $45.000 $80.000 $40.000 $75.000
GABION MATTRESSES (GALV) (24 IN)
SY 95.000 $200.000 $250.000 $225.000 $400.000 $225.000 $260.000 $310.000 $270.000 $193.750 $300.000 $250.000 $175.000 $500.000
GABIONS (PVC)( 3FT X 3 FT)
CY 75.000 $360.000 $250.000 $400.000 $500.000 $350.000 $300.000 $500.000 $310.000 $687.500 $300.000 $500.000 $405.000 $500.000
CLEAN EXIST CULVERTS
EA 13.000 $3,000.000 $650.000 $5,000.000 $5,225.000 $4,500.000 $1,500.000 $9,500.000 $1,900.000 $1,875.000 $3,000.000 $2,500.000 $16,625.000 $10,000.000
MOBILIZATION
LS 1.000 $61,014.630 $50,000.000 $55,000.000 $57,000.000 $60,000.000 $70,000.000 $85,000.000 $78,000.000 $12,500.000 $75,000.000 $80,000.000 $97,700.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $15,000.000 $1.000 $1.000 $750.000 $5,000.000 $1,000.000 $1,200.000 $15,000.000 $9,375.000 $5,000.000 $8,500.000 $5,250.000 $3,750.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 140.000 $130.000 $1.000 $1.000 $50.000 $200.000 $1.000 $11.000 $10.000 $125.000 $125.000 $150.000 $150.000 $50.000
TMA (STATIONARY)
DAY 263.000 $200.000 $1.000 $1.000 $100.000 $200.000 $1.000 $11.000 $10.000 $125.000 $450.000 $250.000 $200.000 $300.000
CONCRETE RAIL REPAIR (MISC)
LF 105.000 $95.970 $150.000 $500.000 $295.000 $500.000 $280.000 $300.000 $250.000 $166.250 $400.000 $250.000 $400.000 $500.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 75.000 $50.000 $60.000 $140.000 $105.000 $80.000 $78.000 $65.000 $175.000 $93.750 $75.000 $100.000 $153.000 $150.000
REPLACING ELASTOMERIC BEARING PADS
EA 24.000 $6,000.000 $3,500.000 $7,500.000 $7,000.000 $4,500.000 $10,000.000 $6,887.000 $10,500.000 $9,375.000 $8,500.000 $7,500.000 $6,200.000 $5,000.000
Totals: $727,299.590 $498,387.000 $591,362.000 $630,895.000 $719,890.000 $723,778.000 $732,971.000 $781,040.000 $784,600.000 $866,950.000 $941,450.000 $977,390.000 $1,115,600.000