ECTOR VA (0906-00-239)
Items: 9
County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-239
DBE Goal: 0.0%
Project: C 906-00-239
Guaranty: N/A
Time: 21 WORKING DAYS
Engineer's Estimate: $1,001,506.85
Date: 03/06/2024 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,001,506.85 | |||
| $705,606.10 |
-29.55%
-$295,900.75
|
|||
| $711,007.88 |
-29.01%
-$290,498.97
|
0.77%
$5,401.78
|
||
| $766,276.12 |
-23.49%
-$235,230.73
|
8.6%
$60,670.02
|
-7.77%
-$55,268.24
|
|
| $841,347.12 |
-15.99%
-$160,159.73
|
19.24%
$135,741.02
|
-9.80%
-$75,071.00
|
|
| $849,227.40 |
-15.21%
-$152,279.45
|
20.35%
$143,621.30
|
-0.94%
-$7,880.28
|
|
| $961,201.12 |
-4.02%
-$40,305.73
|
36.22%
$255,595.02
|
-13.19%
-$111,973.72
|
|
| $965,729.70 |
-3.57%
-$35,777.15
|
36.87%
$260,123.60
|
-0.47%
-$4,528.58
|
|
| $967,131.74 |
-3.43%
-$34,375.11
|
37.06%
$261,525.64
|
-0.15%
-$1,402.04
|
E
Engineer's Estimate
$1,001,506.85
$705,606.10
Over/Under Est:
-29.55%
-$295,900.75
$711,007.88
Over/Under Est:
-29.01%
-$290,498.97
Amt Left:
0.77%
$5,401.78
$766,276.12
Over/Under Est:
-23.49%
-$235,230.73
Amt Left:
8.6%
$60,670.02
Delta:
-7.77%
-$55,268.24
$841,347.12
Over/Under Est:
-15.99%
-$160,159.73
Amt Left:
19.24%
$135,741.02
Delta:
-9.80%
-$75,071.00
$849,227.40
Over/Under Est:
-15.21%
-$152,279.45
Amt Left:
20.35%
$143,621.30
Delta:
-0.94%
-$7,880.28
$961,201.12
Over/Under Est:
-4.02%
-$40,305.73
Amt Left:
36.22%
$255,595.02
Delta:
-13.19%
-$111,973.72
$965,729.70
Over/Under Est:
-3.57%
-$35,777.15
Amt Left:
36.87%
$260,123.60
Delta:
-0.47%
-$4,528.58
$967,131.74
Over/Under Est:
-3.43%
-$34,375.11
Amt Left:
37.06%
$261,525.64
Delta:
-0.15%
-$1,402.04
Bid Items & Bid Tabulations
9
Total
0 of 9