ECTOR VA (0906-00-205)

Items: 19

County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-205
DBE Goal: N/A
Project: C 906-00-205
Guaranty: N/A
Time: 260 WORKING DAYS
Engineer's Estimate: $1,593,135.34
Date: 01/06/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,593,135.34
Over/Under Est: 5.31% $84,617.66
Over/Under Est: 14.01% $223,157.66
Amt Left: 8.26% $138,540.00
Over/Under Est: 15.92% $253,609.66
Amt Left: 10.07% $168,992.00
Delta: -1.68% -$30,452.00
Over/Under Est: 16.81% $267,789.16
Amt Left: 10.92% $183,171.50
Delta: -0.77% -$14,179.50

Bid Items & Bid Tabulations

19 Total 0 of 19
ECTOR  |  VA  |  ODESSA  |  0906-00-205  |  01/06/2023  |  $1,593,135.34  |  C 906-00-205  |  BRIDGE MAINT  |  260 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
RAGLE CONSTRUCTION, INC.
SCR CIVIL CONSTRUCTION, LLC
B & MS CONSTRUCTION, INC.
CL C CONC (RAIL FOUNDATION)
CY 26.000 $1,053.290 $1,816.000 $1,000.000 $1,400.000 $650.000
CL C CONC (MISC)
CY 17.000 $1,250.000 $2,315.000 $391.000 $300.000 $1,725.000
CL C CONC (VEH DEFL WALL)
CY 70.000 $1,860.000 $2,357.000 $1,500.000 $2,270.000 $1,150.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,690.000 $250.000 $172.000 $77.000 $225.000 $285.000
RIPRAP (CONC)(4 IN)
CY 5.000 $568.000 $2,864.000 $750.000 $600.000 $600.000
CLEANING AND SEALING EXISTING JOINTS
LF 5,873.000 $13.000 $27.000 $52.000 $37.000 $34.000
CLEANING EXISTING JOINTS
LF 1,432.000 $7.000 $25.000 $25.000 $17.000 $30.000
RAIL (TY T222)
LF 204.000 $126.680 $310.000 $175.000 $350.000 $550.000
HEADER TYPE EXPANSION JOINT
CF 426.000 $465.000 $358.000 $300.000 $550.000 $345.000
JOINT SEALANT
LF 1,730.000 $11.670 $28.000 $30.000 $25.000 $38.000
RAISING EXIST STRUCT
LS 1.000 $64,310.700 $63,328.000 $60,000.000 $140,000.000 $95,000.000
MOBILIZATION
LS 1.000 $215,942.930 $167,750.000 $160,000.000 $184,000.000 $95,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $7,500.000 $10,806.000 $34,000.000 $10,000.000 $5,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $941.800 $3,659.000 $1,200.000 $5,000.000 $1,380.000
CRASH CUSHION ATTEN (INSTALL) (QUAD)(N)
EA 2.000 $25,000.000 $35,944.000 $27,000.000 $37,000.000 $42,500.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 140.000 $85.000 $164.000 $45.000 $105.000 $125.000
REPLACE ELASTOMERIC BEARING PADS
EA 20.000 $5,375.000 $796.000 $3,500.000 $900.000 $3,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 725.000 $75.590 $62.000 $80.000 $50.000 $172.500
TMA (STATIONARY)
DAY 437.000 $125.000 $293.000 $310.000 $150.000 $275.000
Totals: $1,593,135.340 $1,677,753.000 $1,816,293.000 $1,846,745.000 $1,860,924.500