Show Job Controls
Bid Cobra

ECTOR VA (0906-00-200)

Items: 18

County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-200
DBE Goal: N/A
Project: C 906-00-200
Guaranty: N/A
Time: 37 WORKING DAYS
Engineer's Estimate: $440,650.59
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: CULVERT REPAIR PROGRAM (2021)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$440,650.59
$334,501.00
Over/Under Est: -24.09% -$106,149.59
Over/Under Est: -12.15% -$53,555.75
Amt Left: 15.72% $52,593.84
$522,030.00
Over/Under Est: 18.47% $81,379.41
Amt Left: 56.06% $187,529.00
Delta: -34.86% -$134,935.16
Over/Under Est: 26.06% $114,849.41
Amt Left: 66.07% $220,999.00
Delta: -6.41% -$33,470.00
Over/Under Est: 44.77% $197,284.41
Amt Left: 90.71% $303,434.00
Delta: -14.84% -$82,435.00
Over/Under Est: 57.65% $254,056.41
Amt Left: 107.68% $360,206.00
Delta: -8.90% -$56,772.00

Bid Items & Bid Tabulations

18 Total 0 of 18
ECTOR  |  VA  |  ODESSA  |  0906-00-200  |  06/03/2021  |  $440,650.59  |  C 906-00-200  |  CULVERT REPAIR PROGRAM (2021)  |  37 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
12TWELVE ROAD AND BRIDGE LLC
DAVIS CONSTRUCTION TEXAS INC.
RELMCO, INC.
O. TREVINO CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 58.000 $31.280 $20.000 $32.170 $100.000 $65.000 $20.000 $146.000
FL BS (CMP IN PLACE)(TY A GR 4)(IN VEH)
CY 835.000 $49.680 $50.000 $41.660 $150.000 $68.000 $85.000 $120.000
CEM STABIL BKFL
CY 85.000 $203.550 $75.000 $234.090 $300.000 $298.000 $350.000 $292.000
CUT & RESTORE ASPH PAVING
SY 124.000 $65.000 $55.000 $274.080 $150.000 $254.000 $200.000 $450.000
TRENCH EXCAVATION PROTECTION
LF 175.000 $20.390 $20.000 $1.180 $50.000 $33.000 $10.000 $40.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,068.000 $211.070 $120.000 $108.320 $110.000 $163.000 $250.000 $178.000
RIPRAP (CONC)(5 IN)
CY 7.000 $563.240 $165.000 $910.300 $1,500.000 $1,105.000 $650.000 $1,455.000
RC PIPE (CL III)(30 IN)
LF 210.000 $130.230 $300.000 $142.300 $125.000 $224.000 $180.000 $200.000
RC PIPE (CL III)(36 IN)
LF 35.000 $184.680 $127.000 $175.000 $250.000 $335.000 $200.000 $250.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 6.000 $2,702.580 $1,500.000 $3,108.530 $5,400.000 $6,000.000 $6,500.000 $8,500.000
SET (TY II) (36 IN) (CMP) (4: 1) (C)
EA 1.000 $2,800.000 $3,000.000 $3,213.140 $6,000.000 $7,600.000 $8,500.000 $7,500.000
SET (REMOV & REINSTALL)
EA 1.000 $926.150 $100.000 $1,180.000 $3,500.000 $1,100.000 $2,000.000 $900.000
CLEAN EXIST CULVERTS
EA 3.000 $2,017.980 $3,000.000 $11,438.160 $3,500.000 $11,000.000 $10,000.000 $12,200.000
REMOV STR (PIPE)
LF 175.000 $20.040 $10.000 $20.250 $50.000 $63.000 $30.000 $80.000
MOBILIZATION
LS 1.000 $33,816.680 $55,000.000 $35,990.000 $50,000.000 $55,500.000 $60,000.000 $67,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $1.000 $11,611.200 $10,000.000 $10,000.000 $8,500.000 $23,000.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 20.000 $30.000 $10.000 $165.200 $100.000 $75.000 $100.000 $60.000
TMA (STATIONARY)
DAY 84.000 $253.890 $1.000 $177.000 $500.000 $310.000 $350.000 $270.000
Totals: $440,650.590 $334,501.000 $387,094.840 $522,030.000 $555,500.000 $637,935.000 $694,707.000