ECTOR VA (0906-00-156)

Items: 12

County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-156
DBE Goal: N/A
Project: STP 2017(795)
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $1,149,063.07
Date: 03/08/2017 (9 years ago)
Contract Number: N/A
Type: NON-IH PAVEMENT MARKING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,149,063.07
1
$960,040.86
Over/Under Est: -16.45% -$189,022.21
$982,593.12
Over/Under Est: -14.49% -$166,469.95
Amt Left: 2.35% $22,552.26
$989,915.35
Over/Under Est: -13.85% -$159,147.72
Amt Left: 3.11% $29,874.49
Delta: -0.75% -$7,322.23
Over/Under Est: -11.03% -$126,771.96
Amt Left: 6.48% $62,250.25
Delta: -3.27% -$32,375.76
$1,391,702.17
Over/Under Est: 21.12% $242,639.10
Amt Left: 44.96% $431,661.31
Delta: -36.14% -$369,411.06
Over/Under Est: 27.59% $317,028.73
Amt Left: 52.71% $506,050.94
Delta: -5.35% -$74,389.63
Over/Under Est: 64.71% $743,508.26
Amt Left: 97.13% $932,530.47
Delta: -29.09% -$426,479.53

Bid Items & Bid Tabulations

12 Total 0 of 12
ECTOR  |  VA  |  ODESSA  |  0906-00-156  |  03/08/2017  |  $1,149,063.07  |  STP 2017(795)  |  NON-IH PAVMT MRK  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L&L COMPANY
VIZCAINO, L.P.
FLAT LINE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
STRIPE-A-ZONE, INC.
TRP CONSTRUCTION GROUP, LLC
PMI PAVEMENT MARKING, INC.
MOBILIZATION
LS 1.000 $30,000.000 $1.000 $1.000 $1.000 $1.000 $25,000.000 $100,000.000 $24,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $1.000 $1.000 $1.000 $1.000 $5,000.000 $1,500.000 $200.000
REFL PAV MRK TY I (W)4"(LNDP)(090MIL)
LF 1,085.000 $0.550 $1.000 $0.220 $0.500 $0.550 $1.000 $2.000 $0.350
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 96,000.000 $0.290 $0.400 $0.300 $0.260 $0.450 $0.775 $0.600 $0.350
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 267,170.000 $0.180 $0.170 $0.170 $0.170 $0.190 $0.335 $0.300 $0.350
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 4,033,632.000 $0.150 $0.120 $0.120 $0.127 $0.123 $0.155 $0.160 $0.230
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 445,266.000 $0.170 $0.170 $0.170 $0.170 $0.190 $0.335 $0.300 $0.350
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 345,734.000 $0.160 $0.130 $0.130 $0.127 $0.125 $0.155 $0.160 $0.230
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,587,578.000 $0.170 $0.160 $0.180 $0.170 $0.180 $0.210 $0.230 $0.350
REFL PAV MRKR TY I-C
EA 1,770.000 $2.600 $2.100 $2.200 $2.200 $2.300 $2.600 $2.650 $2.750
REFL PAV MRKR TY II-A-A
EA 5,480.000 $2.600 $2.100 $2.200 $2.200 $2.300 $2.600 $2.650 $2.750
REFL PAV MRKR TY II-C-R
EA 580.000 $3.000 $2.100 $3.000 $2.200 $2.300 $2.600 $2.650 $2.750
Totals: $1,149,063.070 $960,040.860 $982,593.120 $989,915.362 $1,022,291.116 $1,391,702.170 $1,466,091.800 $1,892,571.330