ECTOR SH 302 (0572-01-076)

Items: 33

County: ECTOR
Length: 0.0000 MILES
Highway: SH 302
District: ODESSA
Control Number: 0572-01-076
DBE Goal: 0.0%
Project: F 2026(387)
Guaranty: $100,000.00
Time: 175 WORKING DAYS
Engineer's Estimate: $10,581,431.98
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263010
Type: HIGHWAY IMPROVEMENT
Project ID: A00200125
Contract Type: Federal
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
FREW BOGALE
ODA-PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$10,581,431.98
Over/Under Est: -12.26% -$1,296,888.51
Over/Under Est: 5.27% $557,324.65
Amt Left: 19.97% $1,854,213.16
$11,146,628.88
Over/Under Est: 5.34% $565,196.90
Amt Left: 20.06% $1,862,085.41
Delta: -0.07% -$7,872.25
$11,715,699.81
Over/Under Est: 10.72% $1,134,267.83
Amt Left: 26.18% $2,431,156.34
Delta: -5.11% -$569,070.93
$12,957,365.79
Over/Under Est: 22.45% $2,375,933.81
Amt Left: 39.56% $3,672,822.32
Delta: -10.60% -$1,241,665.98

Bid Items & Bid Tabulations

33 Total 0 of 33
ECTOR  |  SH 302  |  ODESSA  |  0572-01-076  |  05/06/2026  |  $10,581,431.98  |  F 2026(387)  |  HWY IMPRV  |  175 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
RAGLE CONSTRUCTION, INC.
REECE ALBERT, INC.
RK HALL, LLC
FNF CONSTRUCTION, INC.
SUBGR WIDEN (OC)
STA 122.000 $1,100.000 $1,150.000 $1,600.000 $1,771.480 $1,681.510 $2,500.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 20,118.000 $15.000 $22.270 $12.000 $21.970 $29.660 $21.000
PRIME COAT (AE-P)
GAL 2,012.000 $5.000 $5.630 $6.500 $3.590 $8.910 $5.500
FOG SEAL (CSS-1H)
GAL 29,662.000 $4.000 $3.950 $5.200 $2.890 $3.380 $4.000
SP MIXES SP-B SAC-B PG70-22
TON 4,369.000 $120.000 $125.000 $140.000 $155.950 $123.640 $286.000
TOM-C PG76-22 SAC-A
TON 33,665.000 $180.000 $148.000 $160.000 $186.310 $187.980 $175.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 58,547.000 $33.000 $35.000 $35.000 $41.430 $35.690 $40.000
CLEAN EXIST CULVERTS
EA 3.000 $3,020.000 $1,650.000 $2,000.000 $3,371.760 $9,313.110 $4,100.000
MOBILIZATION
LS 1.000 $630,513.000 $155,000.000 $1,000,000.000 $212,708.110 $775,442.470 $1,294,600.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $15,000.000 $15,000.000 $60,000.000 $8,187.800 $19,524.220 $54,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $19,250.000 $25,000.000 $4,659.690 $14,967.940 $6,900.000
TMA (STATIONARY)
DAY 175.000 $200.000 $82.500 $300.000 $263.920 $372.760 $200.000
TMA (MOBILE OPERATION)
DAY 175.000 $300.000 $8.500 $400.000 $64.370 $532.840 $445.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,030.000 $8.500 $12.000 $10.750 $9.540 $8.820 $10.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,030.000 $1.200 $4.000 $1.000 $2.230 $1.880 $1.300
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 265,812.000 $0.100 $0.190 $0.070 $0.160 $0.180 $0.120
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 28.000 $841.000 $886.600 $806.000 $948.410 $943.400 $825.000
REMOVE SM RD SN SUP&AM
EA 6.000 $120.000 $110.000 $100.000 $139.920 $106.000 $125.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 48.000 $65.000 $89.100 $81.000 $95.310 $106.000 $83.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 92.000 $100.000 $90.200 $82.000 $96.490 $106.000 $84.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 140.000 $22.000 $10.000 $25.000 $35.880 $15.900 $50.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 265,812.000 $0.200 $0.180 $0.160 $0.190 $0.170 $0.170
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 265,812.000 $0.240 $0.180 $0.160 $0.190 $0.170 $0.170
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 375.000 $1.000 $0.940 $0.850 $1.000 $2.120 $2.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,354.000 $1.000 $0.940 $0.850 $1.000 $0.800 $0.800
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 33,227.000 $0.750 $0.700 $0.640 $0.750 $0.630 $0.610
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 132,906.000 $0.500 $0.700 $0.640 $0.750 $0.600 $0.600
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 132,906.000 $0.600 $0.690 $0.630 $0.740 $0.600 $0.600
PREFAB PM TY C (W)(24")(SLD)
LF 27.000 $20.000 $17.600 $16.000 $18.830 $23.320 $23.000
PREFAB PM TY C (W)(ARROW)
EA 7.000 $300.000 $247.500 $225.000 $264.750 $286.200 $280.000
REFL PAV MRKR TY I-C
EA 1,661.000 $4.750 $5.500 $5.000 $5.880 $3.980 $3.900
BONDING COURSE
GAL 58,547.000 $2.700 $2.550 $5.500 $3.240 $3.950 $5.000
TMSP RADAR SPEED CONTROL MONITOR
EA 4.000 $10,000.000 $6,500.000 $9,500.000 $2,965.260 $5,196.020 $5,100.000
Totals: $10,581,431.980 $9,284,543.470 $11,138,756.630 $11,146,628.880 $11,715,699.810 $12,957,365.790
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
Total: $45,000.00