Bid Cobra

ECTOR SH 302 (0463-07-055)

Items: 58

County: ECTOR
Length: 0.4970 MILES
Highway: SH 302
District: ODESSA
Control Number: 0463-07-055
DBE Goal: 0.0%
Project: F 2B25(099)
Guaranty: $26,000.00
Time: 46 WORKING DAYS
Engineer's Estimate: $1,299,947.36
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263225
Type: INTERSECTION IMPROVEMENTS WITH LEFT TURN LANE
Project ID: A00213810
Contract Type: Federal
Project Description: WIDEN ROADWAY FOR LEFT-TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
FREW BOGALE
ODA-PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,299,947.36
$1,275,100.00
Over/Under Est: -1.91% -$24,847.36
$1,351,117.69
Over/Under Est: 3.94% $51,170.33
Amt Left: 5.96% $76,017.69
Over/Under Est: 59.84% $777,830.41
Amt Left: 62.95% $802,677.77
Delta: -53.78% -$726,660.08

Bid Items & Bid Tabulations

58 Total 0 of 58
ECTOR  |  SH 302  |  ODESSA  |  0463-07-055  |  05/07/2026  |  $1,299,947.36  |  F 2B25(099)  |  INTERS IMPRVS WITH LEFT TURN LANE  |  46 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
REECE ALBERT, INC.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
EXCAV (ROADWAY)
CY 250.000 $40.000 $100.000 $15.410 $92.980
SUBGR WIDEN (OC)
STA 18.000 $780.000 $1,500.000 $3,154.150 $3,500.000
EMBANK (FNL)(OC)(TY B)
CY 250.000 $35.000 $100.000 $9.130 $72.650
BACKFILL (TY B)
STA 18.000 $196.820 $500.000 $208.130 $1,017.330
BLADING
HR 20.000 $147.000 $160.000 $615.310 $450.000
PROOF ROLLING
HR 20.000 $129.480 $136.000 $124.550 $175.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 1,940.000 $30.000 $11.000 $21.890 $39.940
PRIME COAT (AE-P)
GAL 388.000 $5.200 $7.100 $7.730 $14.290
FOG SEAL (CSS-1H)
GAL 369.000 $6.000 $8.500 $7.590 $14.680
SP MIXES SP-B SAC-B PG70-22
TON 1,121.000 $200.000 $130.000 $180.950 $228.000
TACK COAT
GAL 388.000 $3.040 $7.100 $2.670 $14.290
TOM-C PG76-22 SAC-A
TON 874.000 $300.000 $170.000 $228.030 $252.000
FLOWABLE BACKFILL
CY 2.000 $1,500.000 $700.000 $822.010 $3,000.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 80.000 $450.000 $550.000 $289.260 $660.000
RIPRAP (CONC)(CL B)
CY 3.000 $396.950 $1,500.000 $2,475.820 $2,640.000
CMP (ALUMINUM 24")
LF 8.000 $500.000 $227.000 $751.300 $600.500
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 1.000 $2,250.000 $3,500.000 $9,762.700 $18,000.000
CLEAN EXIST CULVERTS
EA 1.000 $2,466.000 $2,500.000 $7,531.800 $4,200.600
MOBILIZATION
LS 1.000 $118,179.000 $130,000.000 $107,640.210 $208,557.520
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $25,000.000 $24,500.000 $5,050.630 $50,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $20,000.000 $6,100.000 $6,721.140 $23,125.000
TMA (STATIONARY)
DAY 46.000 $347.000 $287.000 $292.360 $175.000
TMA (MOBILE OPERATION)
DAY 15.000 $900.000 $250.000 $741.390 $1,075.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 210.000 $14.000 $9.000 $8.170 $28.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 210.000 $4.000 $4.000 $3.070 $18.000
PORT CTB (FURN & INST)(TL-3 LPCB)
LF 2,000.000 $50.000 $150.000 $150.890 $240.000
PORT CTB (REMOVE) (TL-3 LPCB)
LF 2,000.000 $30.000 $13.000 $21.470 $24.000
DRIVEWAYS (ACP)
SY 285.000 $102.000 $124.000 $222.610 $87.370
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 3,600.000 $0.200 $0.420 $1.470 $1.800
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 2,800.000 $0.230 $0.540 $1.470 $2.400
IN RD IL (TY SA) 50T-12 (400W EQ) LED
EA 8.000 $7,000.000 $8,500.000 $6,658.540 $10,200.000
CONDT (PVC) (SCH 40) (2")
LF 1,990.000 $11.690 $7.000 $17.470 $8.400
ELEC CONDR (NO.6) BARE
LF 2,115.000 $1.470 $2.500 $1.910 $3.000
ELEC CONDR (NO.6) INSULATED
LF 4,230.000 $2.500 $2.750 $2.130 $3.300
GROUND BOX TY A (122311)W/APRON
EA 1.000 $2,048.440 $2,250.000 $1,315.340 $2,700.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $11,100.000 $14,000.000 $8,186.730 $16,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $703.570 $1,600.000 $1,746.510 $1,920.000
REMOVE SM RD SN SUP&AM
EA 2.000 $113.380 $150.000 $127.520 $241.870
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 2.000 $120.000 $150.000 $163.740 $180.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $135.000 $100.000 $109.160 $241.870
INSTL OM SM RD SIGN (1-OM-CON)R
EA 2.000 $30.000 $50.000 $54.580 $60.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 5,000.000 $0.480 $0.450 $1.530 $1.680
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 5,000.000 $0.380 $0.450 $1.530 $1.680
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 150.000 $1.000 $1.770 $3.070 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 275.000 $1.440 $1.840 $3.310 $6.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 700.000 $0.960 $2.000 $1.640 $1.800
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 1,000.000 $1.000 $1.000 $1.640 $1.800
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 3,700.000 $1.310 $1.000 $1.640 $1.800
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 6,000.000 $1.500 $1.000 $1.640 $1.800
PREFAB PM TY C (W)(24")(SLD)
LF 40.000 $16.080 $15.000 $21.830 $24.000
PREFAB PM TY C (W)(ARROW)
EA 2.000 $213.430 $180.000 $327.470 $360.000
PREFAB PM TY C (W)(WORD)
EA 2.000 $264.050 $240.000 $436.630 $480.000
REFL PAV MRKR TY I-C
EA 70.000 $5.540 $5.000 $7.640 $8.400
REFL PAV MRKR TY II-A-A
EA 60.000 $4.280 $5.000 $7.640 $8.400
REFL PAV MRKR TY II-C-R
EA 70.000 $4.390 $5.000 $7.640 $8.400
ELIM EXT PM & MRKS (4")
LF 2,000.000 $0.650 $3.000 $3.270 $4.500
BONDING COURSE
GAL 1,588.000 $3.210 $5.800 $2.680 $7.190
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $12,350.000 $17,500.000 $1,721.510 $10,000.000
Totals: $1,299,947.360 $1,275,100.000 $1,351,117.690 $2,077,777.770
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
PUBLIC UTILITY FORCE ACCT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $30,000.00