ECTOR SH 158 (0463-01-024)
Items: 65
County: ECTOR
Length: 0.0000 MILES
Highway: SH 158
District: ODESSA
Control Number: 0463-01-024
DBE Goal: 3.0%
Project: STP 2024(816)HES
Guaranty: $100,000.00
Time: 290 WORKING DAYS
Engineer's Estimate: $10,589,342.70
Date: 06/04/2025 (1 year ago)
Contract Number: 6253008
Type: INSTALL CONTINUOUS LEFT TURN LANE
Project ID: A00184365
Contract Type: Federal
Project Description: INSTALL CONTINUOUS LEFT TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ODA-PRELETTINGQUESTIONS
ECTOR SH 158 (0463-01-024)
Project Name: N/A
Project: STP 2024(816)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: ASTER AVE
Limits To: MIDLAND COUNTY LINE
Project Description: INSTALL CONTINUOUS LEFT TURN LANE
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$10,589,342.70 | |||
| $5,970,353.45 |
-43.62%
-$4,618,989.25
|
|||
| $7,330,796.70 |
-30.77%
-$3,258,546.00
|
22.79%
$1,360,443.25
|
||
| $10,833,154.62 |
2.3%
$243,811.92
|
81.45%
$4,862,801.17
|
-47.78%
-$3,502,357.92
|
E
Engineer's Estimate
$10,589,342.70
$5,970,353.45
Over/Under Est:
-43.62%
-$4,618,989.25
$7,330,796.70
Over/Under Est:
-30.77%
-$3,258,546.00
Amt Left:
22.79%
$1,360,443.25
$10,833,154.62
Over/Under Est:
2.3%
$243,811.92
Amt Left:
81.45%
$4,862,801.17
Delta:
-47.78%
-$3,502,357.92
| Subcontractor | Percentage | Amount |
|---|---|---|
| DESERT PAVING, INC. | 13.26% | $791,668.87 |
| DOUBLE A CONTRACTING, L.P. | 2.90% | $173,140.25 |
| CONTRACTORS SERVICE, LTD. | 1.45% | $86,570.13 |
| MARCOMS CONSTRUCTION LLC | 1.28% | $76,420.52 |
| DUSTROL, INC. | 0.19% | $11,343.67 |
| WIMS ENVIRONMENTAL CONSTRUCTION, LTD. | 0.10% | $5,970.35 |
| R.E.B.D. TRUCKING LLC | 0.01% | $597.04 |
| Total: | 19.19% | $1,145,710.83 |
Bid Items & Bid Tabulations
65
Total
0 of 65
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $20,000.00 |