EASTLAND IH0020 (6377-63-001)
Items: 7
County: EASTLAND
Length: N/A
Highway: IH0020
District: BROWNWOOD
Control Number: 6377-63-001
DBE Goal: N/A
Project: RMC - 637763001
Guaranty: N/A
Time: 44 W
Engineer's Estimate: $1,230,583.57
Date: 10/07/2021 (4 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,230,583.57 | |||
| $1,442,402.92 |
17.21%
$211,819.35
|
|||
| $1,515,433.20 |
23.15%
$284,849.63
|
5.06%
$73,030.28
|
||
| $1,593,735.16 |
29.51%
$363,151.59
|
10.49%
$151,332.24
|
-5.17%
-$78,301.96
|
|
| $1,603,120.57 |
30.27%
$372,537.00
|
11.14%
$160,717.65
|
-0.59%
-$9,385.41
|
|
| $1,658,053.00 |
34.74%
$427,469.43
|
14.95%
$215,650.08
|
-3.43%
-$54,932.43
|
|
| $1,705,518.45 |
38.59%
$474,934.88
|
18.24%
$263,115.53
|
-2.86%
-$47,465.45
|
E
Engineer's Estimate
$1,230,583.57
1
Awarded
$1,442,402.92
Over/Under Est:
17.21%
$211,819.35
$1,515,433.20
Over/Under Est:
23.15%
$284,849.63
Amt Left:
5.06%
$73,030.28
$1,593,735.16
Over/Under Est:
29.51%
$363,151.59
Amt Left:
10.49%
$151,332.24
Delta:
-5.17%
-$78,301.96
$1,603,120.57
Over/Under Est:
30.27%
$372,537.00
Amt Left:
11.14%
$160,717.65
Delta:
-0.59%
-$9,385.41
$1,658,053.00
Over/Under Est:
34.74%
$427,469.43
Amt Left:
14.95%
$215,650.08
Delta:
-3.43%
-$54,932.43
$1,705,518.45
Over/Under Est:
38.59%
$474,934.88
Amt Left:
18.24%
$263,115.53
Delta:
-2.86%
-$47,465.45
Bid Items & Bid Tabulations
7
Total
0 of 7