EASTLAND FM 2461 (0714-05-021)

Items: 52

County: EASTLAND
Length: N/A
Highway: FM 2461
District: BROWNWOOD
Control Number: 0714-05-021
DBE Goal: N/A
Project: STP 2020(347)
Guaranty: N/A
Time: 85 WORKING DAYS
Engineer's Estimate: $1,450,595.91
Date: 12/04/2019 (6 years ago)
Contract Number: N/A
Type: REHABILITATION OF AN EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,450,595.91
Over/Under Est: 6.01% $87,235.34
$1,948,231.43
Over/Under Est: 34.31% $497,635.52
Amt Left: 26.69% $410,400.18
Over/Under Est: 63.21% $916,873.67
Amt Left: 53.95% $829,638.33
Delta: -21.52% -$419,238.15

Bid Items & Bid Tabulations

52 Total 0 of 52
EASTLAND  |  FM 2461  |  BROWNWOOD  |  0714-05-021  |  12/04/2019  |  $1,450,595.91  |  STP 2020(347)  |  REHAB OF AN EXIST ROAD  |  85 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAY MILLS CONTRACTING, INCORPORATED
A. L. HELMCAMP, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
EXCAVATION (ROADWAY)
CY 15,203.000 $11.070 $17.000 $25.500 $25.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 166.000 $10.450 $10.000 $45.000 $40.000
BLADING
STA 43.000 $126.420 $150.000 $800.000 $1,000.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 9,594.000 $0.170 $0.300 $0.250 $2.000
DRILL SEEDING (TEMP) (WARM)
SY 4,797.000 $0.120 $0.400 $0.370 $1.000
DRILL SEEDING (TEMP) (COOL)
SY 4,797.000 $0.120 $0.400 $0.380 $1.000
VEGETATIVE WATERING
MG 216.000 $15.560 $30.000 $20.000 $1.000
PROOF ROLLING
HR 2.000 $175.000 $400.000 $85.000 $100.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 3,890.100 $43.480 $44.000 $60.000 $80.000
PRIME COAT (RC-250)
GAL 2,451.000 $4.610 $5.500 $5.000 $10.000
AGGR(TY-B GR-5 SAC-B)
CY 90.000 $104.000 $100.000 $180.000 $500.000
AGGR(TY-PB GR-3 SAC-B)
CY 131.000 $116.070 $125.000 $170.000 $500.000
AGGR(TY-PB GR-4 SAC-B)
CY 93.000 $128.660 $125.000 $210.000 $500.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 8,465.000 $5.100 $5.000 $5.000 $8.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 1,241.000 $120.000 $115.000 $100.000 $140.000
CEM STABIL BKFL
CY 62.000 $198.970 $180.000 $175.000 $220.000
TRENCH EXCAVATION PROTECTION
LF 96.000 $8.500 $12.000 $16.000 $15.000
CL C CONC (CULV)
CY 94.100 $1,500.000 $1,325.000 $1,050.000 $1,500.000
REINF CONC SLAB
SF 2,572.160 $15.000 $20.000 $17.850 $28.000
RIPRAP (CONC)(CL C)
CY 65.200 $570.000 $575.000 $600.000 $600.000
RIPRAP (STONE PROTECTION)(30 IN)
CY 1,063.500 $168.500 $90.000 $165.000 $220.000
CMP AR (GAL STL DES 3)
LF 54.000 $117.680 $90.000 $90.000 $100.000
SET (TY I)(S=10 FT)(HW=6FT)(4:1)(C)
EA 10.000 $12,500.000 $11,500.000 $11,050.000 $14,000.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 2.000 $1,251.000 $2,200.000 $2,100.000 $4,000.000
REMOV STR (PIPE)
EA 1.000 $350.000 $1,000.000 $160.000 $500.000
MOBILIZATION
LS 1.000 $95,000.000 $150,000.000 $190,000.000 $195,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,250.000 $12,500.000 $38,000.000 $25,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 120.000 $27.360 $35.000 $26.000 $5.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $10.160 $12.000 $6.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 600.000 $2.310 $4.500 $3.500 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 600.000 $1.000 $2.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 4,060.000 $4.570 $4.750 $3.500 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,060.000 $0.860 $1.000 $0.750 $2.000
DRIVEWAYS (SURF TREAT)
SY 747.000 $25.590 $25.000 $22.000 $30.000
MTL W-BEAM GD FEN (STEEL POST)
LF 2,217.500 $26.620 $25.000 $23.000 $25.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 100.000 $26.650 $24.500 $34.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 2,700.000 $3.200 $2.250 $3.500 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,665.000 $2,750.000 $2,900.000 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $762.740 $1,705.000 $840.000 $800.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 16.000 $377.460 $935.000 $420.000 $800.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 3.000 $347.720 $1,050.000 $570.000 $800.000
REMOVE SM RD SN SUP&AM
EA 21.000 $87.390 $115.000 $110.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 33.000 $77.670 $25.000 $41.000 $40.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 4.000 $100.000 $110.000 $130.000 $40.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 10.000 $10.000 $110.000 $26.000 $30.000
PAVEMENT SEALER 4"
LF 1,535.000 $16.000 $0.760 $0.500 $1.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 10,800.000 $0.410 $0.610 $0.580 $0.600
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 426.000 $0.420 $2.650 $0.580 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 9,110.000 $0.400 $0.610 $0.580 $0.600
REFL PAV MRKR TY I-C
EA 850.000 $3.760 $6.500 $5.000 $5.000
REFL PAV MRKR TY II-A-A
EA 115.000 $4.250 $6.500 $5.500 $5.000
PAV SURF PREP FOR MRK (4")
LF 1,535.000 $0.150 $0.750 $1.050 $1.200
Totals: $1,450,595.908 $1,537,831.250 $1,948,231.436 $2,367,469.580