EASTLAND US 183 (0127-02-141)

Items: 67

County: EASTLAND
Length: N/A
Highway: US 183
District: BROWNWOOD
Control Number: 0127-02-141
DBE Goal: N/A
Project: STP 2018(542)
Guaranty: N/A
Time: 260 WORKING DAYS
Engineer's Estimate: $4,198,880.06
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: ADD PASSING LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$4,198,880.06
$3,673,746.04
Over/Under Est: -12.51% -$525,134.02
Over/Under Est: -12.37% -$519,249.56
Amt Left: 0.16% $5,884.46
Over/Under Est: -9.64% -$404,736.44
Amt Left: 3.28% $120,397.58
Delta: -3.11% -$114,513.12
$3,924,208.59
Over/Under Est: -6.54% -$274,671.47
Amt Left: 6.82% $250,462.55
Delta: -3.43% -$130,064.97
Over/Under Est: -5.52% -$231,850.69
Amt Left: 7.98% $293,283.33
Delta: -1.09% -$42,820.78
$4,411,316.60
Over/Under Est: 5.06% $212,436.54
Amt Left: 20.08% $737,570.56
Delta: -11.20% -$444,287.23

Bid Items & Bid Tabulations

67 Total 0 of 67
EASTLAND  |  US 183  |  BROWNWOOD  |  0127-02-141  |  02/02/2018  |  $4,198,880.06  |  STP 2018(542)  |  ADD PASSING LANES  |  260 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAY FARIS, INC.
JAY MILLS CONTRACTING, INCORPORATED
NOBLES ROAD CONSTRUCTION, INC.
A. L. HELMCAMP, INC.
J. CARROLL WEAVER, INC.
GILVIN-TERRILL, LTD.
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 4.000 $700.790 $2,000.000 $1,875.000 $792.000 $1,200.000 $1,296.000 $1,000.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 9.000 $3,000.000 $1,000.000 $1,000.000 $525.000 $1,000.000 $1,296.000 $850.000
EXCAVATION (ROADWAY)
CY 507.000 $18.000 $10.040 $14.000 $5.110 $12.000 $11.840 $4.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 7,756.000 $12.000 $10.040 $10.000 $11.890 $15.000 $27.880 $15.000
BLADING
STA 257.400 $270.000 $68.610 $160.000 $52.500 $150.000 $70.200 $100.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 9.780 $676.000 $434.000 $675.000 $350.000 $450.000 $468.720 $450.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 9.780 $582.000 $320.000 $550.000 $350.000 $450.000 $345.600 $320.000
VEGETATIVE WATERING
MG 1,062.000 $20.000 $10.560 $12.000 $31.500 $15.000 $30.240 $22.000
PROOF ROLLING
HR 25.000 $71.000 $53.500 $100.000 $78.000 $75.000 $59.400 $85.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 40,722.000 $35.000 $36.620 $35.400 $34.250 $36.000 $34.000 $30.000
REWORK BS MTL (TY C)(11")(DENS CONT)
SY 114,404.000 $2.250 $1.600 $1.810 $2.200 $1.900 $1.240 $5.300
PRIME COAT (RC-250)
GAL 28,853.000 $3.900 $3.560 $3.600 $3.250 $3.800 $3.780 $3.500
AGGR(TY-B GR-5 SAC-B)
CY 1,031.000 $65.000 $52.060 $42.600 $69.200 $100.000 $62.400 $55.750
AGGR(TY-PB GR-3 SAC-B)
CY 1,603.000 $90.000 $73.590 $74.000 $86.200 $80.000 $97.230 $88.700
AGGR(TY-PB GR-4 SAC-B)
CY 1,202.000 $85.000 $76.360 $70.000 $95.200 $90.000 $87.600 $88.700
ASPH (AC-20-5TR OR AC-20XP)
GAL 49,050.000 $3.250 $2.930 $3.000 $3.200 $3.200 $3.620 $3.500
ASPH (CRS-1P OR AC-15P)
GAL 60,591.000 $3.750 $2.660 $3.100 $2.850 $3.200 $3.590 $3.000
HMCL ACP TY-F SAC-B AC-1.5
TON 68.000 $140.000 $117.310 $150.000 $124.200 $130.000 $189.000 $244.000
D-GR HMA TY-D SAC-B PG70-22
TON 96.000 $140.000 $111.310 $150.000 $151.200 $160.000 $156.600 $237.000
CEM STABIL BKFL
CY 54.000 $77.190 $150.000 $200.000 $240.000 $160.000 $108.000 $150.000
FLOWABLE BACKFILL
CY 202.200 $250.000 $150.000 $200.000 $193.000 $165.000 $218.380 $150.000
TRENCH EXCAVATION PROTECTION
LF 92.000 $20.000 $15.000 $10.000 $26.200 $16.000 $8.640 $20.000
RC PIPE (CL III)(18 IN)
LF 355.000 $75.000 $55.000 $47.000 $48.300 $58.000 $51.840 $100.000
RC PIPE (CL III)(24 IN)
LF 86.000 $150.000 $75.000 $70.000 $73.500 $78.000 $95.040 $120.000
RC PIPE (CL III)(36 IN)
LF 367.000 $200.000 $140.000 $160.000 $135.200 $150.000 $151.200 $180.000
RC PIPE (ARCH)(CL III)(DES 5)
LF 5.000 $1,000.000 $450.000 $285.000 $420.000 $550.000 $378.000 $300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $700.000 $1,000.000 $800.000 $875.000 $1,000.000 $864.000 $2,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,200.000 $1,050.000 $975.000 $990.000 $1,100.000 $864.000 $3,000.000
SET (TY II) (36 IN) (CMP) (4: 1) (C)
EA 8.000 $2,690.000 $3,000.000 $1,800.000 $1,825.000 $3,000.000 $3,240.000 $4,000.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 8.000 $3,200.000 $3,500.000 $1,900.000 $2,620.000 $3,600.000 $3,240.000 $4,000.000
SET (TY II) (60 IN) (CMP) (4: 1) (C)
EA 2.000 $2,500.000 $4,000.000 $9,500.000 $3,700.000 $4,500.000 $5,940.000 $4,500.000
SET (TY II) (DES 5) (CMP) (4: 1) (C)
EA 4.000 $2,200.000 $3,000.000 $2,250.000 $1,955.000 $3,200.000 $3,780.000 $5,000.000
SET (TY II) (DES 7) (CMP) (4: 1) (C)
EA 8.000 $4,000.000 $4,100.000 $3,350.000 $3,235.000 $4,500.000 $5,238.000 $5,500.000
SET (TY II) (DES 8) (CMP) (4: 1) (C)
EA 6.000 $2,500.000 $4,200.000 $3,900.000 $4,060.000 $4,500.000 $6,480.000 $6,000.000
REMOV STR (PIPE)
LF 490.000 $19.920 $10.000 $24.000 $10.500 $11.000 $16.200 $20.000
MOBILIZATION
LS 1.000 $378,232.170 $287,821.610 $250,000.000 $379,000.000 $310,000.000 $429,452.600 $420,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $7,000.000 $1,942.570 $5,000.000 $2,000.000 $5,000.000 $2,268.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 30.000 $30.000 $43.000 $52.000 $31.500 $40.000 $46.440 $45.000
ROCK FILTER DAMS (REMOVE)
LF 30.000 $10.000 $10.000 $20.000 $10.500 $8.000 $8.640 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,146.000 $5.000 $2.500 $4.000 $2.350 $4.000 $2.700 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,146.000 $1.300 $0.850 $2.600 $0.530 $1.000 $0.540 $0.850
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 4,415.000 $6.500 $3.110 $5.000 $4.200 $5.500 $3.360 $3.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,415.000 $1.650 $0.600 $0.800 $0.530 $1.000 $0.540 $0.520
CONSTRUCTING DETOURS
SY 14,433.000 $22.000 $22.640 $17.000 $18.800 $19.000 $19.320 $19.750
INTERSECTIONS (SURF TREAT)
SY 1,838.000 $22.000 $16.560 $19.000 $18.900 $16.000 $12.960 $34.450
DRIVEWAYS (SURF TREAT)
SY 4,280.700 $20.000 $18.700 $19.000 $18.600 $16.000 $10.800 $34.450
TURNOUTS (SURF TREAT)
SY 44.000 $25.000 $17.630 $19.000 $41.000 $25.000 $5.400 $34.450
MAILBOX INSTALL-S (WC-POST) TY 3
EA 7.000 $205.000 $150.000 $225.000 $210.000 $220.000 $378.000 $210.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $550.000 $545.000 $950.000 $840.000 $370.000 $378.000 $610.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,200.000 $690.000 $1,000.000 $890.000 $530.000 $540.000 $950.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 24.000 $550.000 $330.000 $725.000 $680.000 $320.000 $324.000 $240.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 22.000 $700.000 $420.000 $850.000 $785.000 $370.000 $378.000 $330.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $300.000 $345.000 $650.000 $575.000 $300.000 $297.000 $470.000
REMOVE SM RD SN SUP&AM
EA 46.000 $110.000 $70.000 $115.000 $52.000 $110.000 $108.000 $45.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 24.000 $80.000 $45.000 $75.000 $68.000 $80.000 $91.800 $50.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 103,740.000 $0.170 $0.170 $0.190 $0.180 $0.160 $0.180 $0.150
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 103,740.000 $0.200 $0.170 $0.190 $0.180 $0.160 $0.180 $0.150
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,969.000 $1.160 $1.140 $1.110 $1.550 $0.600 $0.950 $1.250
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 225.000 $0.600 $1.600 $1.780 $1.680 $1.700 $1.730 $1.630
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 150.000 $10.000 $12.000 $13.330 $12.600 $6.000 $12.960 $4.970
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 3,583.000 $0.450 $0.350 $0.390 $0.370 $0.480 $0.380 $0.450
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 51,480.000 $0.450 $0.320 $0.360 $0.340 $0.370 $0.350 $0.340
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,890.000 $0.450 $0.320 $0.360 $0.340 $0.480 $0.350 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 37,730.000 $0.450 $0.320 $0.360 $0.340 $0.370 $0.350 $0.350
REFL PAV MRKR TY I-C
EA 197.000 $4.000 $4.000 $4.440 $4.200 $4.000 $4.320 $3.820
REFL PAV MRKR TY II-A-A
EA 568.000 $4.000 $4.000 $4.440 $4.200 $3.500 $4.320 $3.000
ELIM EXT PAV MRK & MRKS (4")
LF 33,565.000 $0.750 $0.500 $0.520 $0.440 $0.650 $0.540 $0.320
Totals: $4,198,880.070 $3,673,746.044 $3,679,630.500 $3,794,143.620 $3,924,208.590 $3,967,029.386 $4,411,316.605