EASTLAND US 183 (0127-02-043)

Items: 100

County: EASTLAND
Length: N/A
Highway: US 183
District: BROWNWOOD
Control Number: 0127-02-043
DBE Goal: N/A
Project: C 127-2-43
Guaranty: N/A
Time: 332 WORKING DAYS
Engineer's Estimate: $4,828,749.68
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: ADD PASSING LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$4,828,749.68
Over/Under Est: -6.27% -$302,736.72
Over/Under Est: 3.12% $150,474.49
Amt Left: 10.01% $453,211.21
Over/Under Est: 5.11% $246,888.05
Amt Left: 12.14% $549,624.77
Delta: -1.94% -$96,413.56
$5,187,502.81
Over/Under Est: 7.43% $358,753.13
Amt Left: 14.62% $661,489.85
Delta: -2.20% -$111,865.08
$5,518,284.50
Over/Under Est: 14.28% $689,534.82
Amt Left: 21.92% $992,271.54
Delta: -6.38% -$330,781.69

Bid Items & Bid Tabulations

100 Total 0 of 100
EASTLAND  |  US 183  |  BROWNWOOD  |  0127-02-043  |  04/03/2018  |  $4,828,749.68  |  C 127-2-43  |  ADD PASSING LANES  |  332 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAY MILLS CONTRACTING, INCORPORATED
J. CARROLL WEAVER, INC.
DELHUR INDUSTRIES, INC.
A. L. HELMCAMP, INC.
RAY FARIS, INC.
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 2.000 $788.380 $750.000 $5,940.000 $1,459.070 $3,500.000 $1,500.000
EXCAVATION (ROADWAY)
CY 2,639.000 $18.000 $12.000 $12.770 $4.900 $7.000 $15.260
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 9,009.000 $12.000 $12.000 $22.960 $8.660 $13.000 $16.800
EMBANK (FINAL)(DC)(TY C) CSBE
CY 342.000 $80.000 $72.000 $41.040 $57.520 $210.000 $61.800
BLADING
STA 279.000 $52.500 $90.000 $70.200 $200.400 $220.000 $141.700
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 12.360 $676.000 $525.000 $468.720 $449.400 $1,500.000 $420.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 12.360 $582.000 $495.000 $345.600 $321.000 $1,500.000 $300.000
VEGETATIVE WATERING
MG 1,343.000 $31.500 $12.250 $30.240 $37.160 $12.000 $11.720
PROOF ROLLING
HR 25.000 $71.000 $85.000 $59.400 $111.830 $75.000 $109.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 42,468.000 $34.250 $36.000 $35.600 $38.210 $42.000 $42.120
REWORK BS MATL (TY B)(11")(DENS CONT)
SY 3,574.000 $3.000 $5.000 $1.330 $1.550 $3.000 $2.720
REWORK BS MTL (TY C)(11")(DENS CONT)
SY 123,422.000 $2.250 $1.900 $1.330 $2.650 $3.000 $2.280
PRIME COAT (RC-250)
GAL 33,436.000 $3.250 $3.400 $3.430 $4.100 $3.000 $4.310
AGGR(TY-B GR-5 SAC-B)
CY 1,086.000 $65.000 $52.000 $71.430 $62.210 $65.000 $65.150
AGGR(TY-PB GR-3 SAC-B)
CY 1,689.000 $90.000 $78.000 $99.750 $89.930 $75.000 $84.160
AGGR(TY-PB GR-4 SAC-B)
CY 1,267.000 $95.200 $78.000 $89.410 $89.900 $90.000 $86.340
ASPH (AC-20-5TR OR AC-20XP)
GAL 51,674.000 $3.250 $3.000 $2.970 $3.270 $3.500 $3.240
ASPH (CRS-1P OR AC-15P)
GAL 63,833.000 $2.850 $3.000 $2.720 $3.400 $3.200 $3.450
HMCL ACP TY-F SAC-B AC-1.5
TON 245.000 $140.000 $150.000 $189.000 $184.200 $135.000 $139.400
D-GR HMA TY-D SAC-B PG70-22
TON 96.000 $140.000 $175.000 $156.600 $166.140 $135.000 $162.200
PLANE ASPH CONC PAV (1" TO 3")
SY 960.000 $10.000 $4.000 $12.960 $13.880 $6.000 $17.440
STRUCT EXCAV (BRIDGE)
CY 72.000 $51.990 $35.000 $27.000 $12.160 $38.000 $25.000
FLOWABLE BACKFILL
CY 125.900 $193.000 $155.000 $135.000 $170.430 $210.000 $150.000
TRENCH EXCAVATION PROTECTION
LF 208.000 $20.000 $4.000 $10.800 $10.700 $20.000 $10.000
TEMPORARY SPL SHORING
SF 1,600.000 $30.000 $18.000 $37.800 $34.780 $15.000 $30.000
CL C CONC (CULV)
CY 3.800 $1,469.150 $1,000.000 $2,700.000 $1,605.000 $2,100.000 $2,500.000
RIPRAP (CONC)(5 IN)
CY 45.900 $800.000 $550.000 $486.000 $535.000 $600.000 $450.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 340.000 $35.000 $33.000 $64.800 $32.100 $38.000 $30.000
MULTI-LAYER POLYMER OVERLAY
SY 960.000 $70.000 $64.000 $62.640 $73.210 $75.000 $58.000
CONC BOX CULV (5 FT X 3 FT)
LF 400.000 $236.920 $340.000 $648.000 $377.240 $310.000 $450.000
RC PIPE (CL III)(18 IN)
LF 80.000 $75.000 $54.000 $59.400 $97.860 $53.000 $52.000
RC PIPE (CL III)(30 IN)
LF 150.000 $175.000 $95.000 $140.400 $147.200 $107.000 $120.000
RC PIPE (CL III)(36 IN)
LF 93.000 $135.200 $130.000 $178.200 $186.820 $130.000 $160.000
RC PIPE (CL III)(42 IN)
LF 70.000 $290.000 $170.000 $270.000 $380.840 $160.000 $250.000
RC PIPE (CL III)(48 IN)
LF 174.000 $194.440 $225.000 $324.000 $234.950 $165.000 $300.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
EA 10.000 $8,000.000 $3,500.000 $5,940.000 $3,190.000 $8,500.000 $5,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $850.000 $725.000 $918.000 $1,118.450 $850.000 $850.000
SET (TY II) (30 IN) (CMP) (4: 1) (C)
EA 2.000 $3,500.000 $1,000.000 $2,160.000 $2,082.900 $1,500.000 $2,000.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $4,000.000 $925.000 $2,160.000 $2,011.400 $2,000.000 $2,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 8.000 $2,500.000 $1,400.000 $2,700.000 $2,456.900 $2,000.000 $2,500.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $3,200.000 $1,200.000 $2,700.000 $2,170.900 $2,300.000 $2,500.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 4.000 $5,200.000 $3,300.000 $4,320.000 $5,601.300 $3,500.000 $4,000.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 4.000 $6,000.000 $4,750.000 $5,400.000 $7,981.560 $5,000.000 $5,000.000
SET (TY II) (DES 7) (CMP) (4: 1) (C)
EA 2.000 $4,000.000 $4,000.000 $5,400.000 $1,167.960 $2,800.000 $5,000.000
DIAMOND GRINDING SLAB
SY 960.000 $20.000 $12.000 $59.400 $10.170 $23.000 $10.000
REMOV STR (PIPE)
LF 980.000 $19.920 $16.000 $16.200 $8.790 $20.000 $15.000
MOBILIZATION
LS 1.000 $435,000.000 $350,000.000 $357,213.920 $355,122.300 $400,000.000 $496,891.880
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $2,000.000 $3,500.000 $2,700.000 $7,844.130 $3,000.000 $4,626.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 150.000 $30.000 $35.000 $22.680 $36.850 $40.000 $21.000
ROCK FILTER DAMS (REMOVE)
LF 150.000 $10.000 $12.000 $10.800 $3.760 $9.000 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,746.000 $5.000 $2.500 $2.320 $3.200 $3.500 $2.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,746.000 $1.300 $0.750 $0.810 $1.000 $1.500 $0.750
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 4,890.000 $4.200 $5.000 $3.620 $6.420 $6.000 $3.350
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,890.000 $1.650 $0.800 $0.650 $2.400 $1.000 $0.600
CONSTRUCTING DETOURS
SY 15,518.000 $18.800 $17.000 $19.440 $11.970 $15.000 $27.760
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 300.000 $15.000 $10.000 $36.000 $9.450 $34.000 $33.330
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 510.000 $12.740 $10.000 $21.600 $7.560 $15.000 $20.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 300.000 $12.000 $10.000 $32.400 $9.450 $34.000 $30.000
INTERSECTIONS (SURF TREAT)
SY 1,881.000 $22.000 $18.500 $11.880 $21.300 $16.000 $28.260
DRIVEWAYS (SURF TREAT)
SY 4,105.900 $20.000 $15.000 $11.880 $22.020 $16.000 $23.080
TURNOUTS (SURF TREAT)
SY 11.000 $30.000 $25.000 $11.880 $24.520 $400.000 $36.800
MTL W-BEAM GD FEN (TIM POST)
LF 1,500.000 $25.000 $23.000 $22.200 $22.000 $23.000 $20.560
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,575.000 $2,285.000 $2,244.240 $2,223.460 $2,300.000 $2,078.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 100.000 $20.630 $24.000 $22.730 $22.520 $25.000 $21.050
REMOVE METAL BEAM GUARD FENCE
LF 1,405.000 $5.000 $2.750 $2.700 $2.680 $3.000 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,500.000 $2,885.000 $2,831.760 $2,805.540 $3,000.000 $2,622.000
CRASH CUSH ATTEN (INSTL)
EA 4.000 $10,000.000 $10,000.000 $10,260.000 $10,505.000 $11,000.000 $9,550.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $1,675.000 $2,750.000 $2,160.000 $2,200.000 $1,000.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $800.000 $2,300.000 $810.000 $825.000 $750.000 $750.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 9.000 $205.000 $187.000 $172.800 $171.200 $200.000 $160.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $550.000 $627.000 $910.130 $901.700 $630.000 $842.710
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,200.000 $814.000 $1,047.050 $1,037.360 $820.000 $969.490
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 12.000 $550.000 $352.000 $651.350 $645.320 $360.000 $603.100
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 18.000 $700.000 $451.000 $754.030 $747.060 $460.000 $698.190
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $300.000 $385.000 $756.000 $723.230 $400.000 $675.920
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $350.000 $462.000 $800.280 $792.870 $470.000 $741.000
REMOVE SM RD SN SUP&AM
EA 27.000 $110.000 $75.000 $108.000 $107.000 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $25.000 $22.000 $21.600 $21.400 $30.000 $20.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 14.000 $64.970 $60.500 $79.750 $79.010 $60.000 $73.840
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 32.000 $40.000 $33.540 $32.930 $32.620 $35.000 $30.490
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 116,760.000 $0.170 $0.110 $0.110 $0.250 $0.110 $0.100
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 116,760.000 $0.200 $0.260 $0.260 $0.250 $0.260 $0.240
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 600.000 $2.860 $3.630 $3.560 $3.850 $3.640 $3.300
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 2,075.000 $4.420 $3.630 $3.560 $3.850 $3.640 $3.300
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 1,790.000 $2.000 $3.250 $3.190 $2.570 $3.250 $2.950
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 6,210.000 $2.000 $3.250 $3.190 $2.570 $3.250 $2.950
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 70.000 $17.370 $11.000 $10.800 $19.260 $11.030 $10.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,620.000 $1.160 $1.250 $0.490 $1.520 $0.600 $1.370
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 225.000 $0.600 $1.160 $1.130 $1.440 $1.160 $1.050
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 135.000 $10.000 $12.100 $11.880 $11.770 $12.130 $11.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,620.000 $0.450 $0.390 $0.380 $0.370 $0.390 $0.350
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 56,200.000 $0.450 $0.360 $0.360 $0.340 $0.360 $0.330
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,648.000 $0.450 $0.370 $0.370 $0.370 $0.370 $0.340
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 33,300.000 $0.500 $0.360 $0.360 $0.340 $0.360 $0.330
REFL PAV MRKR TY I-C
EA 150.000 $4.000 $4.790 $4.700 $3.910 $4.800 $4.350
REFL PAV MRKR TY II-A-A
EA 663.000 $4.000 $4.790 $4.700 $3.910 $4.800 $4.350
ELIM EXT PAV MRK & MRKS (4")
LF 90,000.000 $0.440 $0.540 $0.540 $0.410 $0.690 $0.630
TEMP TRAF SIGNALS
EA 2.000 $21,000.000 $7,000.000 $28,080.000 $28,600.000 $8,000.000 $5,000.000
TMA (STATIONARY)
DAY 40.000 $300.000 $265.000 $540.000 $709.130 $400.000 $700.000
TMA (MOBILE OPERATION)
HR 96.000 $37.500 $52.000 $81.000 $141.830 $50.000 $70.000
Totals: $4,828,749.680 $4,526,012.960 $4,979,224.187 $5,075,637.749 $5,187,502.810 $5,518,284.502