Bid Cobra

EASTLAND IH 20 (0007-06-281)

Items: 77

County: EASTLAND
Length: 0.0000 MILES
Highway: IH 20
District: BROWNWOOD
Control Number: 0007-06-281
DBE Goal: 0.0%
Project: C 7-6-281
Guaranty: $0.00
Time: 91 WORKING DAYS
Engineer's Estimate: $8,646,114.75
Date: 10/08/2025 (8 months ago)
Contract Number: 10253009
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00212622
Project Description: FOR CONSTRUCTION OF REHABILITATION OF EXISTING ROADWAY INCLUDING CONCRETE PAVEMENT REPAIR AND PAVEMENT MARKINGS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JORDAN PERRY
MATTHEW CLOPTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$8,646,114.75
$7,760,918.61
Over/Under Est: -10.24% -$885,196.14
Over/Under Est: -1.16% -$99,991.02
Amt Left: 10.12% $785,205.12
Over/Under Est: 4.08% $352,929.36
Amt Left: 15.95% $1,238,125.50
Delta: -5.30% -$452,920.38
Over/Under Est: 7.63% $659,589.55
Amt Left: 19.9% $1,544,785.69
Delta: -3.41% -$306,660.19
$9,542,600.06
Over/Under Est: 10.37% $896,485.31
Amt Left: 22.96% $1,781,681.45
Delta: -2.55% -$236,895.76
Subcontractor Percentage Amount
DUSTIN ALLEN, INC. 1.68% $130,383.43
MAVERICK REBAR COMPANY LLC 0.82% $63,639.53
STRIPE-A-ZONE, LLC 0.78% $60,535.17
ANTIGO CONSTRUCTION, INC. 0.47% $36,476.32
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 0.45% $34,924.13
A BROTHERS MILLING, LLC 0.44% $34,148.04
SK CONCRETE SERVICES LLC 0.39% $30,267.58
SURFACE PREPARATION TECHNOLOGIES, LLC 0.14% $10,865.29
PEYSON TRANSPORT, LLC 0.09% $6,984.83
Total: 5.26% $408,224.32

Bid Items & Bid Tabulations

77 Total 0 of 77
EASTLAND  |  IH 20  |  BROWNWOOD  |  0007-06-281  |  10/08/2025  |  $8,646,114.75  |  C 7-6-281  |  SURF/ROADWAY RESTOR  |  91 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
TEXAS MATERIALS GROUP, INC.
NORTHEASTERN PAVERS, LLC
GREY SKY CONSTRUCTION LLC
A. L. HELMCAMP, INC.
REMOV CONC (PAV)
SY 20,760.000 $35.000 $20.000 $25.000 $22.000 $20.000 $18.000
REMOV CONC (MOWSTRIP)
LF 4,300.000 $15.000 $3.500 $12.000 $15.000 $50.000 $20.000
EXCAV (ROADWAY)
CY 1,028.000 $85.000 $125.000 $30.000 $32.000 $20.000 $20.000
EMBANK (FNL)(DC)(TY C)
CY 2,398.000 $45.000 $60.000 $46.000 $50.000 $50.000 $58.000
BLADING
STA 75.000 $250.000 $800.000 $431.320 $275.000 $250.000 $140.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 484.000 $1.250 $1.000 $4.000 $3.000 $3.000 $4.500
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 484.000 $1.250 $1.000 $4.000 $3.000 $3.000 $4.500
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 968.000 $3.000 $1.000 $4.000 $3.000 $3.000 $4.500
PROOF ROLLING
HR 6.000 $300.000 $105.000 $300.000 $375.000 $150.000 $220.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 941.000 $95.000 $89.000 $68.000 $75.000 $100.000 $97.000
PRIME COAT (MC-30)
GAL 6,228.000 $7.000 $5.400 $7.000 $7.000 $10.000 $10.000
D-GR HMA TY-B SAC-B PG70-22
TON 2,480.000 $225.000 $120.000 $170.000 $200.000 $165.000 $210.000
TACK COAT
GAL 665.000 $10.000 $8.900 $5.480 $4.000 $10.000 $9.000
PFC-C PG76-22 SAC-A
TON 1,676.000 $215.000 $190.000 $290.000 $300.000 $225.000 $280.000
PFC-C PG76-22 SAC-B
TON 841.000 $200.000 $180.000 $290.000 $300.000 $225.000 $270.000
SP MIXES SP-C PG76-22
TON 2,325.000 $150.000 $130.000 $250.000 $250.000 $185.000 $217.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 169.000 $235.000 $286.000 $380.000 $575.000 $250.000 $380.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,176.000 $135.000 $66.000 $90.000 $110.000 $80.000 $170.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 1,000.000 $150.000 $102.000 $140.000 $140.000 $120.000 $270.000
PLANE ASPH CONC PAV (1.5")
SY 27,107.000 $4.000 $1.600 $5.560 $10.000 $3.500 $3.000
PLANE ASPH CONC PAV (0" TO 2-1/2")
SY 7,817.000 $5.000 $3.400 $8.930 $12.750 $3.000 $3.100
CONC PVMT (CRCP) (10")
SY 20,760.000 $115.000 $124.000 $121.750 $115.000 $110.000 $147.000
CL C CONC (RAIL FOUNDATION)
CY 421.000 $1,000.000 $534.000 $940.000 $950.000 $1,500.000 $660.000
RIPRAP (MOW STRIP)(4 IN)
CY 122.000 $700.000 $664.000 $680.000 $750.000 $550.000 $1,200.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 376.000 $75.000 $19.000 $52.000 $75.000 $100.000 $55.000
RAIL (TY SSTR)
LF 3,009.000 $130.000 $61.000 $92.000 $100.000 $200.000 $120.000
MOBILIZATION
LS 1.000 $786,000.000 $770,000.000 $850,000.000 $950,000.000 $900,000.000 $800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $20,000.000 $100,000.000 $8,000.000 $50,000.000 $12,500.000 $22,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 204.000 $150.000 $106.000 $81.190 $125.000 $150.000 $200.000
TMA (STATIONARY)
DAY 94.000 $180.000 $244.000 $310.680 $300.000 $250.000 $200.000
TMA (MOBILE OPERATION)
DAY 132.000 $205.000 $576.000 $310.680 $0.010 $550.000 $50.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 500.000 $25.000 $35.000 $40.000 $40.000 $30.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 500.000 $15.000 $11.000 $13.000 $12.000 $15.000 $14.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,685.000 $5.000 $4.110 $5.000 $5.000 $4.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,685.000 $1.250 $0.810 $1.000 $1.500 $2.000 $1.100
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 300.000 $7.000 $6.110 $6.000 $7.500 $11.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $3.000 $0.810 $2.000 $1.500 $9.000 $2.500
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 2,250.000 $23.000 $10.000 $22.000 $21.500 $35.000 $35.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 3,475.000 $18.000 $10.000 $21.000 $20.000 $25.000 $35.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 3,275.000 $23.000 $10.000 $21.000 $1.000 $25.000 $30.000
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 3,819.000 $154.000 $123.000 $135.000 $135.000 $250.000 $210.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 15,596.000 $0.450 $0.700 $0.520 $1.500 $0.300 $0.360
MTL W-BEAM GD FEN (STEEL POST)
LF 2,466.000 $35.000 $27.000 $32.250 $36.000 $35.000 $31.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $3,500.000 $1,885.000 $2,885.000 $3,300.000 $1,850.000 $2,200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,250.000 $1,130.000 $1,900.000 $1,850.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 4,030.000 $3.000 $2.000 $3.000 $2.500 $3.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $1,000.000 $200.000 $220.000 $195.000 $500.000 $240.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $250.000 $200.000 $230.000 $195.000 $500.000 $240.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $300.000 $200.000 $260.000 $195.000 $500.000 $240.000
CABLE BARRIER TERM SEC (INSTL)(TL-3)
EA 1.000 $6,500.000 $5,700.000 $5,700.000 $6,500.000 $4,500.000 $6,600.000
CABLE BARRIER (REMOVE)
LF 2,639.000 $5.500 $6.000 $3.900 $15.000 $5.000 $7.000
CABLE BARRIER TERMINAL SECTION (REMOVE)
EA 3.000 $1,250.000 $1,500.000 $680.000 $3,200.000 $500.000 $1,800.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $4,000.000 $3,000.000 $3,235.000 $4,400.000 $3,850.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $300.000 $200.000 $480.000 $250.000 $1,500.000 $240.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $2,500.000 $1,500.000 $1,520.000 $2,550.000 $6,500.000 $1,200.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $3,500.000 $1,200.000 $810.000 $1,925.000 $2,500.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 5.000 $10,000.000 $15,000.000 $7,900.000 $11,500.000 $21,000.000 $10,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 594.000 $18.000 $27.000 $45.250 $35.000 $100.000 $32.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 25.000 $29.000 $35.000 $45.250 $35.000 $100.000 $40.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 40.000 $22.000 $27.000 $45.250 $60.000 $100.000 $32.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 15.000 $30.000 $40.000 $25.000 $25.000 $50.000 $21.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,240.000 $2.000 $1.700 $1.620 $2.000 $6.000 $0.600
RE PM TY II (W) 6" (BRK)
LF 1,960.000 $0.600 $0.650 $0.840 $0.840 $3.000 $1.000
RE PM TY II (W) 6" (SLD)
LF 7,798.000 $0.600 $0.410 $0.840 $0.840 $3.000 $1.000
RE PM TY II (Y) 6" (SLD)
LF 7,798.000 $0.600 $0.410 $0.840 $0.840 $3.000 $1.000
RE PM TY III (W)(6")(SLD)
LF 7,798.000 $1.400 $1.250 $1.500 $1.500 $3.000 $1.700
RE PM TY III (W)(6")(BRK)
LF 7,661.000 $1.400 $0.800 $1.500 $1.500 $3.000 $1.700
RE PM TY III (W)(6")(DOT)
LF 932.000 $4.500 $1.000 $3.650 $3.650 $3.000 $4.000
RE PM TY III (W)(8")(SLD)
LF 1,728.000 $2.250 $3.000 $1.750 $1.750 $6.000 $2.000
RE PM TY III (W)(12")(SLD)
LF 734.000 $6.500 $10.000 $8.800 $8.800 $6.000 $10.000
RE PM TY III (Y)(6")(SLD)
LF 9,174.000 $1.400 $1.250 $1.500 $1.500 $3.000 $2.000
RE PM TY III (W)(ARROW)
EA 2.000 $600.000 $300.000 $402.000 $402.000 $250.000 $460.000
RE PM TY III (W)(WORD)
EA 5.000 $500.000 $350.000 $410.000 $410.000 $250.000 $470.000
PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)LG
EA 2.000 $500.000 $550.000 $412.000 $412.000 $1,500.000 $470.000
REFL PAV MRKR TY II-C-R
EA 392.000 $6.000 $7.250 $7.000 $7.000 $6.000 $8.000
BONDING COURSE
GAL 7,330.000 $7.500 $6.000 $8.090 $4.000 $3.000 $8.500
TEMP Q-DETECT (TY2) (1 SYS)
DAY 105.000 $1,000.000 $186.670 $351.810 $225.000 $550.000 $150.000
Totals: $8,646,114.750 $7,760,918.610 $8,546,123.730 $8,999,044.110 $9,305,704.300 $9,542,600.060
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $175,000.00
Total: $178,000.00