Show Job Controls
Bid Cobra

EASTLAND IH 20 (0007-06-264)

Items: 12

County: EASTLAND
Length: N/A
Highway: IH 20
District: BROWNWOOD
Control Number: 0007-06-264
DBE Goal: N/A
Project: STP 2019(986)HES
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $1,146,561.00
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,146,561.00
$848,830.31
Over/Under Est: -25.97% -$297,730.69
$1,036,579.00
Over/Under Est: -9.59% -$109,982.00
Amt Left: 22.12% $187,748.69
Over/Under Est: -9.25% -$106,053.30
Amt Left: 22.58% $191,677.39
Delta: -0.38% -$3,928.70
$1,056,536.00
Over/Under Est: -7.85% -$90,025.00
Amt Left: 24.47% $207,705.69
Delta: -1.54% -$16,028.30
$1,070,301.00
Over/Under Est: -6.65% -$76,260.00
Amt Left: 26.09% $221,470.69
Delta: -1.30% -$13,765.00
$1,399,912.00
Over/Under Est: 22.1% $253,351.00
Amt Left: 64.92% $551,081.69
Delta: -30.80% -$329,611.00

Bid Items & Bid Tabulations

12 Total 0 of 12
EASTLAND  |  IH 20  |  BROWNWOOD  |  0007-06-264  |  06/05/2019  |  $1,146,561.00  |  STP 2019(986)HES  |  INSTL MEDIAN BARRIER  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRATIOT CONSTRUCTION, LTD.
HJC FARMS, INC.
SCR CIVIL CONSTRUCTION, LLC
VANN/ELLI, INC.
DBI SERVICES, LLC
FNH CONSTRUCTION, LLC
RIPRAP (MOW STRIP)(4 IN)
CY 1,107.400 $450.000 $378.160 $500.000 $428.000 $490.000 $400.000 $600.000
MOBILIZATION
LS 1.000 $121,805.000 $78,508.240 $100,000.000 $87,000.000 $100,000.000 $150,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,500.000 $2,823.530 $5,000.000 $7,000.000 $6,000.000 $3,600.000 $15,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $5.000 $8.240 $5.000 $6.700 $7.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $1.500 $7.060 $2.000 $3.350 $1.000 $2.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 780.000 $7.400 $7.240 $12.000 $22.000 $9.000 $8.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 780.000 $1.000 $1.470 $1.000 $5.600 $1.000 $3.000 $9.000
CABLE BARRIER SYSTEM (TL-4)
LF 22,051.000 $14.000 $9.950 $9.000 $11.500 $10.000 $11.000 $12.000
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 7,040.000 $15.000 $11.010 $12.000 $13.400 $12.000 $15.000 $15.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 16.000 $3,500.000 $2,017.650 $3,000.000 $2,710.000 $2,000.000 $2,300.000 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 136.000 $100.000 $5.880 $50.000 $120.000 $120.000 $250.000 $125.000
TMA (STATIONARY)
DAY 68.000 $245.000 $5.880 $200.000 $300.000 $400.000 $500.000 $500.000
Totals: $1,146,561.000 $848,830.314 $1,036,579.000 $1,040,507.700 $1,056,536.000 $1,070,301.000 $1,399,912.000