EASTLAND IH 20 (0007-06-258)

Items: 16

County: EASTLAND
Length: N/A
Highway: IH 20
District: BROWNWOOD
Control Number: 0007-06-258
DBE Goal: N/A
Project: BR 2022(597)
Guaranty: N/A
Time: 17 WORKING DAYS
Engineer's Estimate: $551,820.25
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: REHABILITATE BRIDGE
Mail/Deliver Bids To: N/A
JORDAN PERRY
HANNAH FOWLER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$551,820.25
$606,937.92
Over/Under Est: 9.99% $55,117.67
Over/Under Est: 22.85% $126,087.75
Amt Left: 11.69% $70,970.08
$686,028.00
Over/Under Est: 24.32% $134,207.75
Amt Left: 13.03% $79,090.08
Delta: -1.20% -$8,120.00

Bid Items & Bid Tabulations

16 Total 0 of 16
EASTLAND  |  IH 20  |  BROWNWOOD  |  0007-06-258  |  06/01/2022  |  $551,820.25  |  BR 2022(597)  |  REHAB BRIDGE  |  17 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALTUS CONSTRUCTION LLC
EARTH BUILDERS, L.P.
3LW CIVIL LLC
REMOVING CONC (RIPRAP)
CY 72.000 $100.000 $126.530 $80.000 $320.000
EXCAVATION (ROADWAY)
CY 4,094.000 $25.000 $23.540 $25.000 $50.000
BOND FBR MTRX SEED(PERM)(RURAL)(CLAY)
AC 1.000 $6,000.000 $4,826.680 $6,500.000 $12,000.000
VEGETATIVE WATERING
MG 30.000 $30.000 $36.200 $100.000 $325.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $300,000.000 $385,307.730 $440,000.000 $280,500.000
MOBILIZATION
LS 1.000 $75,000.000 $60,333.520 $60,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $25,000.000 $14,480.050 $20,000.000 $41,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,800.000 $5.000 $4.810 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,800.000 $1.000 $1.510 $1.000 $2.000
REMOVE METAL BEAM GUARD FENCE
LF 1,637.000 $3.250 $3.520 $4.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $250.000 $603.340 $350.000 $272.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $250.000 $603.340 $250.000 $245.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $320.000 $603.340 $500.000 $320.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 2.000 $1,250.000 $1,406.640 $750.000 $3,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $105.000 $72.400 $100.000 $50.000
TMA (STATIONARY)
DAY 8.000 $220.000 $168.930 $1,000.000 $400.000
Totals: $551,820.250 $606,937.920 $677,908.000 $686,028.000