DONLEY US 287 (0042-06-074)

Items: 42

County: DONLEY
Length: N/A
Highway: US 287
District: CHILDRESS
Control Number: 0042-06-074
DBE Goal: N/A
Project: C 42-6-74
Guaranty: N/A
Time: 184 WORKING DAYS
Engineer's Estimate: $3,632,174.65
Date: 06/04/2020 (6 years ago)
Contract Number: N/A
Type: MISCELLANOUS CONSTRUCTION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$3,632,174.65
Over/Under Est: 1.33% $48,245.70
$4,113,566.66
Over/Under Est: 13.25% $481,392.01
Amt Left: 11.77% $433,146.31
$5,482,265.45
Over/Under Est: 50.94% $1,850,090.80
Amt Left: 48.96% $1,801,845.10
Delta: -33.27% -$1,368,698.79

Bid Items & Bid Tabulations

42 Total 0 of 42
DONLEY  |  US 287  |  CHILDRESS  |  0042-06-074  |  06/04/2020  |  $3,632,174.65  |  C 42-6-74  |  MISCELLANOUS CONSTRUCTION  |  184 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L A FULLER & SONS CONSTRUCTION, LTD.
GILVIN-TERRILL, LTD.
J. LEE MILLIGAN, INC.
REMOVING CONC (RIPRAP)
SY 532.000 $20.000 $15.800 $20.000 $16.700
REMOVING CONC (CURB AND GUTTER)
LF 1,100.000 $11.000 $8.450 $5.000 $5.250
EXCAVATION (ROADWAY)
CY 11,826.000 $16.000 $7.800 $22.500 $35.000
EXCAVATION (SPECIAL)
CY 30.000 $30.000 $163.000 $50.000 $52.850
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 8,228.000 $15.000 $19.050 $22.500 $35.000
BLADING
HR 45.000 $125.000 $140.000 $210.000 $345.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 8.800 $450.000 $1,145.000 $550.000 $725.000
VEGETATIVE WATERING
MG 344.000 $20.000 $37.000 $34.000 $55.000
FL BS (CMP IN PLC)(TY A OR B GR 5)(12")
SY 30,318.000 $25.000 $25.450 $30.000 $56.200
PRIME COAT (MC-30)
GAL 9,095.000 $6.000 $4.650 $4.000 $5.750
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 8,517.000 $3.250 $5.150 $4.500 $4.950
PLANE ASPH CONC PAV (3")
SY 37,247.000 $4.500 $4.500 $6.000 $6.900
RIPRAP (MOW STRIP)(4 IN)
CY 18.000 $600.000 $955.000 $850.000 $835.000
CMP (GAL STL 24 IN)
LF 24.000 $150.000 $175.000 $100.000 $420.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 22.000 $750.000 $703.000 $1,500.000 $1,030.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 10.000 $800.000 $856.000 $1,750.000 $1,835.000
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $10,000.000 $6,410.000 $15,000.000 $28,965.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $17,000.000 $11,215.000 $20,000.000 $58,900.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $2,500.000 $1,520.000 $3,000.000 $3,500.000
CLEAN EXIST CULVERTS
EA 2.000 $2,800.000 $7,180.000 $10,000.000 $2,125.000
MOBILIZATION
LS 1.000 $360,000.000 $304,800.000 $405,500.000 $541,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $13,000.000 $6,140.000 $15,100.000 $35,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 100.000 $8.000 $4.450 $10.000 $16.500
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $35.000 $41.000 $28.750 $35.600
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $2,300.000 $1,910.000 $1,250.000 $1,665.000
REMOVE METAL BEAM GUARD FENCE
LF 150.000 $5.500 $5.100 $3.000 $4.450
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $400.000 $510.000 $3.000 $445.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,200.000 $4,200.000 $2,750.000 $3,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $400.000 $510.000 $3.000 $445.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 39.000 $650.000 $955.000 $270.000 $770.000
INSTL DEL ASSM (D-DW)SZ 2(WC)GND
EA 297.000 $75.000 $115.000 $30.000 $76.350
INSTL DEL ASSM (D-DY)SZ 2(WC)GND
EA 112.000 $60.000 $115.000 $40.000 $80.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 2.000 $110.000 $127.000 $95.000 $220.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,211.000 $1.200 $1.000 $1.000 $1.250
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 2,200.000 $0.650 $1.250 $1.100 $1.120
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 32,793.000 $0.600 $1.250 $1.100 $1.120
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 29,634.000 $0.300 $0.700 $0.520 $0.580
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 10,959.000 $0.300 $0.700 $0.520 $0.580
D-GR HMA TY-D SAC-A PG70-28
TON 11,164.000 $135.000 $145.500 $140.000 $120.350
TACK COAT
GAL 5,413.000 $5.000 $5.100 $4.000 $3.350
TMA (STATIONARY)
DAY 184.000 $280.000 $320.000 $200.000 $600.000
TMA (MOBILE OPERATION)
HR 36.000 $95.000 $120.000 $95.000 $85.000
Totals: $3,632,174.650 $3,680,420.350 $4,113,566.660 $5,482,265.450