DEWITT FM 2980 (3012-01-005)

Items: 44

County: DEWITT
Length: N/A
Highway: FM 2980
District: YOAKUM
Control Number: 3012-01-005
DBE Goal: N/A
Project: BR 2022(012)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $1,146,301.83
Date: 09/02/2021 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$1,146,301.83
$913,751.50
Over/Under Est: -20.29% -$232,550.33
Over/Under Est: -9.54% -$109,312.25
Amt Left: 13.49% $123,238.08
Over/Under Est: -1.79% -$20,569.51
Amt Left: 23.2% $211,980.82
Delta: -8.56% -$88,742.74
$1,237,261.40
Over/Under Est: 7.94% $90,959.57
Amt Left: 35.4% $323,509.90
Delta: -9.91% -$111,529.08
Over/Under Est: 9.04% $103,646.59
Amt Left: 36.79% $336,196.92
Delta: -1.03% -$12,687.02
$1,523,601.50
Over/Under Est: 32.91% $377,299.67
Amt Left: 66.74% $609,850.00
Delta: -21.89% -$273,653.08

Bid Items & Bid Tabulations

44 Total 0 of 44
DEWITT  |  FM 2980  |  YOAKUM  |  3012-01-005  |  09/02/2021  |  $1,146,301.83  |  BR 2022(012)  |  REPLACE BRIDGE AND APPROACHES  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CONSTAR CONSTRUCTION
DEAN WORD COMPANY, LTD.
HILL COUNTRY BRIDGE, INC.
CK NEWBERRY, LLC
ACME BRIDGE COMPANY, INC.
EARTH BUILDERS, L.P.
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 7.000 $450.000 $2,300.000 $1,773.200 $2,260.000 $2,500.000 $1,360.000 $2,000.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 1.000 $4,100.000 $3,400.000 $2,605.200 $5,650.000 $7,000.000 $4,130.000 $3,000.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,004.000 $20.000 $20.000 $35.530 $84.000 $30.000 $50.000 $30.000
BLADING
HR 60.000 $100.000 $100.000 $99.000 $162.000 $110.000 $152.000 $100.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 4,734.000 $0.500 $1.000 $0.250 $0.270 $0.300 $0.250 $2.000
BROADCAST SEED (TEMP) (WARM)
SY 1,184.000 $0.500 $1.000 $1.040 $1.130 $0.150 $1.050 $2.000
BROADCAST SEED (TEMP) (COOL)
SY 1,184.000 $0.500 $1.000 $1.040 $1.130 $0.150 $1.050 $2.000
VEGETATIVE WATERING
MG 39.850 $30.000 $170.000 $44.000 $95.000 $20.000 $89.400 $50.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 71.000 $75.000 $95.000 $191.208 $188.000 $300.000 $222.000 $100.000
CEM STABIL BKFL
CY 501.000 $140.000 $70.000 $105.600 $92.700 $140.000 $147.000 $300.000
CUT & RESTORING PAV
SY 574.000 $200.000 $54.000 $69.410 $134.200 $150.000 $130.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 126.000 $35.000 $11.000 $7.700 $21.000 $20.000 $22.400 $10.000
TEMPORARY SPL SHORING
SF 200.000 $25.000 $14.000 $13.200 $26.000 $50.000 $27.600 $20.000
RIPRAP (CONC)(5 IN)
CY 40.800 $450.000 $340.000 $407.000 $825.000 $600.000 $580.000 $800.000
CMP (GAL STL 18 IN)
LF 16.000 $95.000 $65.000 $114.400 $194.000 $100.000 $119.000 $100.000
CONC BOX CULV (7 FT X 3 FT)
LF 408.000 $650.000 $585.000 $637.164 $545.000 $650.000 $800.000 $1,075.000
CONC BOX CULV (8 FT X 4 FT)
LF 280.000 $675.000 $710.000 $718.751 $580.000 $750.000 $900.000 $1,250.000
RC PIPE (CL III)(18 IN)
LF 32.000 $85.000 $50.000 $61.600 $75.000 $100.000 $90.000 $100.000
RC PIPE (CL III)(24 IN)
LF 44.000 $90.000 $70.000 $71.500 $85.000 $120.000 $100.000 $125.000
SET (TY I)(S= 7 FT)(HW= 4 FT)(3:1) (C)
EA 12.000 $9,850.000 $7,000.000 $9,878.000 $5,585.000 $11,500.000 $8,500.000 $3,000.000
SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1) (C)
EA 10.000 $11,500.000 $8,000.000 $8,404.000 $4,555.000 $12,000.000 $8,500.000 $3,500.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 2.000 $1,200.000 $1,400.000 $3,217.500 $1,625.000 $2,300.000 $2,500.000 $2,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,600.000 $1,700.000 $1,595.000 $1,615.000 $2,500.000 $2,500.000 $2,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,900.000 $1,800.000 $1,815.000 $1,925.000 $2,800.000 $2,500.000 $4,000.000
REMOV STR (BOX CULVERT)
EA 3.000 $8,500.000 $9,000.000 $11,550.000 $36,120.000 $15,000.000 $11,000.000 $15,000.000
REMOV STR (SMALL)
EA 2.000 $4,500.000 $600.000 $330.000 $1,300.000 $700.000 $1,050.000 $2,000.000
MOBILIZATION
LS 1.000 $103,000.000 $81,000.000 $96,249.701 $112,500.000 $107,000.000 $105,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $4,500.000 $1,400.000 $1,677.512 $8,575.000 $5,000.000 $5,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 125.000 $35.000 $22.000 $24.960 $57.300 $28.000 $25.400 $50.000
ROCK FILTER DAMS (REMOVE)
LF 125.000 $11.000 $10.000 $8.320 $26.600 $8.500 $8.500 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 550.000 $3.000 $5.000 $2.860 $11.000 $3.250 $2.900 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 550.000 $1.000 $1.000 $1.300 $2.300 $1.500 $1.300 $1.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 1.000 $185.000 $600.000 $780.000 $550.000 $600.000 $371.000 $500.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 2.000 $65.000 $354.000 $156.000 $200.000 $125.000 $26.500 $250.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $40.000 $35.000 $26.000 $175.000 $25.000 $10.600 $50.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 12.000 $75.000 $35.000 $78.000 $200.000 $125.000 $106.000 $150.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 28.000 $2.000 $35.000 $2.530 $17.000 $1.000 $5.300 $5.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 40.000 $1.000 $18.000 $20.800 $15.250 $16.000 $52.000 $15.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 261.000 $1.000 $18.000 $5.200 $15.250 $16.000 $13.000 $15.000
REFL PAV MRKR TY II-A-A
EA 6.000 $5.000 $35.000 $52.000 $28.250 $30.000 $130.000 $30.000
TREE TRIMMING / BRUSH REMOVAL
MI 0.080 $21,666.670 $24,000.000 $18,096.000 $16,960.000 $60,000.000 $53,155.380 $50,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $4,000.000 $5,500.000 $8,750.000 $5,000.000 $3,640.000 $7,500.000
TMA (STATIONARY)
DAY 15.000 $275.000 $400.000 $220.000 $725.000 $150.000 $80.800 $250.000
TMA (MOBILE OPERATION)
DAY 2.000 $350.000 $700.000 $495.000 $790.000 $200.000 $808.000 $500.000
Totals: $1,146,301.834 $913,751.500 $1,036,989.597 $1,125,732.320 $1,237,261.400 $1,249,948.420 $1,523,601.500