DEWITT VA (0913-00-104)

Items: 14

County: DEWITT
Length: N/A
Highway: VA
District: YOAKUM
Control Number: 0913-00-104
DBE Goal: N/A
Project: STP 2019(002)
Guaranty: N/A
Time: 111 WORKING DAYS
Engineer's Estimate: $2,508,625.31
Date: 01/08/2019 (7 years ago)
Contract Number: N/A
Type: PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,508,625.31
$2,484,164.82
Over/Under Est: -0.98% -$24,460.49
Over/Under Est: -0.55% -$13,711.25
Amt Left: 0.43% $10,749.24
$2,747,924.12
Over/Under Est: 9.54% $239,298.81
Amt Left: 10.62% $263,759.30
Delta: -10.14% -$253,010.06
Over/Under Est: 15.57% $390,711.44
Amt Left: 16.71% $415,171.93
Delta: -5.51% -$151,412.63

Bid Items & Bid Tabulations

14 Total 0 of 14
DEWITT  |  VA  |  YOAKUM  |  0913-00-104  |  01/08/2019  |  $2,508,625.31  |  STP 2019(002)  |  PAVMT MRK  |  111 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BATTERSON, LLP
TRP CONSTRUCTION GROUP, LLC
STRIPE-A-ZONE, INC.
INTERSTATE BARRICADES & MARKINGS, INC.
MOBILIZATION
LS 1.000 $25,000.000 $100.000 $220,000.000 $63,500.000 $87,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $1,000.000 $500.000 $2,000.000 $1,650.000 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,116.000 $0.450 $0.350 $1.230 $2.000 $2.500
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 12,220.000 $0.650 $0.500 $1.430 $0.950 $1.250
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 143,653.000 $0.480 $0.490 $0.680 $0.675 $0.750
REFL PAV MRKR TY II-C-R
EA 11,534.000 $3.100 $2.700 $2.600 $2.750 $4.000
HPPM W/RET REQ TY I(W)4"(BRK)(100MIL)
LF 177,827.000 $0.350 $0.410 $0.330 $0.450 $0.350
HPPM W/RET REQ TY I(W)4"(SLD)(100MIL)
LF 2,398,879.000 $0.300 $0.330 $0.280 $0.335 $0.350
HPPM W/RET REQ TY I(W)6"(BRK)(100MIL)
LF 230,558.000 $0.450 $0.460 $0.460 $0.610 $0.450
HPPM W/RET REQ TY I(W)6"(SLD)(100MIL)
LF 922,211.000 $0.460 $0.460 $0.400 $0.500 $0.450
HPPM W/RET REQ TY I(Y)4"(BRK)(100MIL)
LF 151,988.000 $0.400 $0.330 $0.350 $0.450 $0.400
HPPM W/RET REQ TY I(Y)4"(SLD)(100MIL)
LF 1,516,959.000 $0.300 $0.330 $0.300 $0.335 $0.400
HPPM W/RET REQ TY I(Y)6"(SLD)(100MIL)
LF 922,211.000 $0.460 $0.460 $0.430 $0.500 $0.550
TMA (MOBILE OPERATION)
DAY 225.000 $500.000 $10.000 $10.000 $25.000 $200.000
Totals: $2,508,625.310 $2,484,164.820 $2,494,914.060 $2,747,924.135 $2,899,336.750