DEWITT FM 682 (0840-02-024)
Items: 55
County: DEWITT
Length: N/A
Highway: FM 682
District: YOAKUM
Control Number: 0840-02-024
DBE Goal: N/A
Project: BR 2024(116)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $2,088,924.60
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
COVEY MORROW
CHASE HERMES
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,088,924.60 | |||
| $2,141,121.59 |
2.5%
$52,196.99
|
|||
| $2,181,760.45 |
4.44%
$92,835.85
|
1.9%
$40,638.86
|
||
| $2,659,821.15 |
27.33%
$570,896.55
|
24.23%
$518,699.56
|
-21.91%
-$478,060.70
|
|
| $2,921,708.80 |
39.87%
$832,784.20
|
36.46%
$780,587.21
|
-9.85%
-$261,887.65
|
|
| $2,978,730.30 |
42.6%
$889,805.70
|
39.12%
$837,608.71
|
-1.95%
-$57,021.50
|
E
Engineer's Estimate
$2,088,924.60
1
Awarded
$2,141,121.59
Over/Under Est:
2.5%
$52,196.99
$2,181,760.45
Over/Under Est:
4.44%
$92,835.85
Amt Left:
1.9%
$40,638.86
$2,659,821.15
Over/Under Est:
27.33%
$570,896.55
Amt Left:
24.23%
$518,699.56
Delta:
-21.91%
-$478,060.70
$2,921,708.80
Over/Under Est:
39.87%
$832,784.20
Amt Left:
36.46%
$780,587.21
Delta:
-9.85%
-$261,887.65
$2,978,730.30
Over/Under Est:
42.6%
$889,805.70
Amt Left:
39.12%
$837,608.71
Delta:
-1.95%
-$57,021.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| LONE STAR PAVING COMPANY | 21.65% | $463,552.82 |
| ZENITH SITE SERVICES | 13.74% | $294,190.11 |
| M & D FOUNDATION DRILLING INDUSTRIES, INC. | 6.34% | $135,747.11 |
| TRAFFIC SIGNS & LINES, LLC | 3.24% | $69,372.34 |
| AARON CONCRETE CONTRACTORS, LLC | 2.62% | $56,097.39 |
| EGGEMEYER LAND CLEARING, LLC | 2.31% | $49,459.91 |
| J. R. (JOE) RAMON & SONS, INC. | 1.82% | $38,968.41 |
| LONE STAR EROSION CONTROL | 0.84% | $17,985.42 |
| TORO BRAVO CONSTRUCTION, LLC | 0.66% | $14,131.40 |
| HOUSTON SAWING & DRILLING | 0.28% | $5,995.14 |
| PRIMATE CONSTRUCTION, LP | 0.23% | $4,924.58 |
| TORO BRAVO CONSTRUCTION, LLC | 0.23% | $4,924.58 |
| SOUTH TEXAS TRAFFIC ALLIANCE INC. | 0.06% | $1,284.67 |
| Total: | 54.02% | $1,156,633.88 |