Show Job Controls
Bid Cobra

DENTON SH0114 (6309-58-001)

Items: 19

County: DENTON
Length: N/A
Highway: SH0114
District: DALLAS
Control Number: 6309-58-001
DBE Goal: N/A
Project: RMC - 630958001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $387,057.18
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: RETROREFLECTORIZED PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$387,057.18
$235,675.25
Over/Under Est: -39.11% -$151,381.93
Over/Under Est: -10.72% -$41,480.60
Amt Left: 46.63% $109,901.33
Over/Under Est: -10.07% -$38,976.33
Amt Left: 47.7% $112,405.60
Delta: -0.72% -$2,504.27

Bid Items & Bid Tabulations

19 Total 0 of 19
DENTON  |  SH0114  |  DALLAS  |  6309-58-001  |  01/05/2017  |  $387,057.18  |  RMC - 630958001  |  RETROREFLECTORIZED PAVMT MRK  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TOTAL HIGHWAY MAINTENANCE, LLC
STRIPING TECHNOLOGY, L.P.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $25,000.000 $2,700.000 $30,000.000 $25,000.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,375.000 $1.030 $0.700 $1.000 $1.500
PAVEMENT SEALER 4"
LF 273,522.000 $0.150 $0.010 $0.150 $0.150
PAVEMENT SEALER 8"
LF 1,375.000 $0.400 $0.200 $0.500 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 23,892.000 $0.510 $0.310 $0.420 $0.400
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,325.000 $0.580 $0.480 $0.750 $0.750
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 2,375.000 $0.390 $0.430 $0.750 $0.750
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,320.000 $0.660 $0.370 $0.600 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 16,634.000 $0.520 $0.310 $0.460 $0.400
ELIM EXT PAV MRK & MRKS (4")
LF 125,430.000 $0.570 $0.400 $0.420 $0.350
ELIM EXT PAV MRK & MRKS (6")
LF 78,570.000 $0.800 $0.300 $0.500 $0.450
ELIM EXT PAV MRK & MRKS (8")
LF 26,344.000 $0.920 $0.650 $0.600 $0.850
PAV SURF PREP FOR MRK (4")
LF 1,320.000 $0.090 $0.250 $0.200 $0.250
PAV SURF PREP FOR MRK (6")
LF 3,700.000 $0.080 $0.300 $0.200 $0.500
PAV SURF PREP FOR MRK (8")
LF 1,375.000 $0.290 $0.350 $0.200 $1.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 97,711.000 $0.410 $0.430 $0.500 $0.550
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 30,396.000 $0.900 $0.500 $0.500 $0.550
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 26,344.000 $1.080 $0.750 $1.000 $1.000
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 103,568.000 $0.390 $0.430 $0.500 $0.550
Totals: $387,057.180 $235,675.250 $345,576.580 $348,080.850