Show Job Controls
Bid Cobra

DENTON FM 2499 (2681-01-027)

Items: 109

County: DENTON
Length: 0.2180 MILES
Highway: FM 2499
District: DALLAS
Control Number: 2681-01-027
DBE Goal: 5.0%
Project: CM 2025(533)
Guaranty: $69,000.00
Time: 144 WORKING DAYS
Engineer's Estimate: $3,503,880.98
Date: 03/04/2025 (1 year ago)
Contract Number: 3253019
Type: INTERSECTION IMPROVEMENT
Project ID: A00177327
Contract Type: Federal
Project Description: CONSTRUCT DUAL LEFT TURN LANES ON EASTBOUND,WESTBOUND, AND SOUTHBOUND APPROACHES. CONSTRUCT ADDITIONAL THROUGH LANE NORTHBOUND, RECONFIGURE SIGNALIZATION.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AMANDA MOSER
CHRISTOPHER ROCHA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$3,503,880.98
$3,143,471.81
Over/Under Est: -10.29% -$360,409.17
Over/Under Est: -2.65% -$92,880.53
Amt Left: 8.51% $267,528.64
Over/Under Est: 7.57% $265,131.33
Amt Left: 19.9% $625,540.50
Delta: -10.50% -$358,011.86
Over/Under Est: 9.09% $318,580.02
Amt Left: 21.6% $678,989.19
Delta: -1.42% -$53,448.69
Over/Under Est: 11.03% $386,593.02
Amt Left: 23.76% $747,002.19
Delta: -1.78% -$68,013.00
$4,048,467.70
Over/Under Est: 15.54% $544,586.72
Amt Left: 28.79% $904,995.89
Delta: -4.06% -$157,993.70
Subcontractor Percentage Amount
WG ENGINEERING & CONSTRUCTION, LLC 16.39% $515,215.03
ADVANCED PAVING COMPANY 11.61% $364,957.08
ROAD MASTER STRIPING, LLC 1.44% $45,265.99
ORCA CONCRETE, LLC 0.32% $10,059.11
MEDELLIN HDD LLC 0.31% $9,744.76
Total: 30.07% $945,241.97

Bid Items & Bid Tabulations

109 Total 0 of 109
DENTON  |  FM 2499  |  DALLAS  |  2681-01-027  |  03/04/2025  |  $3,503,880.98  |  CM 2025(533)  |  INTERS IMPRV  |  144 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
O. TREVINO CONSTRUCTION, LLC
ED BELL CONSTRUCTION COMPANY
RAGLE CONSTRUCTION, INC.
GREY SKY CONSTRUCTION LLC
JAGOE-PUBLIC COMPANY
PREPARING ROW
STA 11.510 $26,602.000 $1,000.000 $5,000.000 $6,000.000 $29,500.000 $29,000.000 $1,200.000
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 13.000 $750.000 $1,000.000 $1,000.000 $750.000 $675.000 $2,500.000 $800.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 11.000 $1,200.000 $1,500.000 $1,200.000 $1,050.000 $950.000 $5,000.000 $1,500.000
REMOV CONC (PAV)
SY 1,729.000 $20.000 $40.000 $28.000 $31.500 $26.400 $20.000 $60.000
REMOV CONC (MEDIANS)
SY 299.000 $30.000 $40.000 $18.000 $12.600 $20.000 $20.000 $32.000
REMOV CONC (DRIVEWAYS)
SY 406.000 $30.000 $40.000 $38.000 $18.900 $17.900 $20.000 $32.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 776.000 $30.000 $30.000 $20.000 $21.000 $22.300 $20.000 $32.000
REMOV CONC (CURB)
LF 5,166.000 $15.000 $5.000 $8.000 $1.000 $2.700 $20.000 $1.500
RMV (12"-16") TRT/UNTRT BASE & ASPH PAV
SY 2,952.000 $9.750 $30.000 $20.000 $21.000 $20.700 $20.000 $15.000
EXCAV (ROADWAY)
CY 5,522.000 $25.000 $50.000 $22.000 $21.000 $46.600 $20.000 $44.000
EMBANK (FNL)(DC)(TY C1)
CY 117.000 $20.000 $50.000 $55.000 $31.500 $830.000 $50.000 $110.000
COMPOST MANUF TOPSOIL (4")
SY 2,110.000 $5.000 $5.000 $8.000 $7.490 $9.600 $7.000 $5.000
BLOCK SODDING
SY 2,110.000 $10.000 $10.000 $7.000 $6.630 $9.800 $7.000 $8.000
DRILL SEED (TEMP_WARM_COOL)
SY 2,110.000 $3.000 $1.300 $1.500 $1.390 $0.500 $1.000 $1.000
VEGETATIVE WATERING
TGL 628.000 $10.000 $70.000 $75.000 $1.000 $30.500 $20.000 $5.000
FL BS (CMP IN PLC)(TY D GR 1-2) (10")
SY 6,160.000 $36.520 $30.000 $45.000 $40.000 $26.500 $32.000 $50.000
PRIME COAT (AE-P)
GAL 1,232.000 $6.000 $10.000 $10.500 $4.280 $9.200 $10.000 $1.000
SP MIXES SP-B PG64-22
TON 1,355.000 $165.000 $180.000 $222.000 $155.150 $168.000 $200.000 $170.000
CONC PVMT (CRCP) (9")
SY 5,112.000 $195.000 $140.000 $130.750 $150.000 $114.500 $150.000 $120.000
FLOWABLE BACKFILL
CY 38.000 $360.000 $300.000 $270.000 $630.000 $2,500.000 $350.000 $330.000
TRENCH EXCAVATION PROTECTION
LF 121.000 $50.000 $10.000 $4.500 $21.000 $26.900 $10.000 $1.250
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 88.000 $500.000 $800.000 $850.000 $781.420 $687.550 $650.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 94.000 $120.000 $80.000 $330.000 $450.000 $159.000 $105.000 $150.000
RC PIPE (CL III)(24 IN)
LF 27.000 $150.000 $120.000 $550.000 $650.000 $276.000 $250.000 $170.000
INLET (COMPL)(PCU)(4FT)(BOTH)
EA 5.000 $8,000.000 $8,000.000 $10,000.000 $21,000.000 $8,000.000 $12,500.000 $16,000.000
INLET (COMPL)(PAZD)(RC)(4FTX4FT)
EA 1.000 $10,000.000 $5,000.000 $10,000.000 $18,000.000 $6,460.000 $12,500.000 $18,000.000
ADJUSTING INLETS (CAP)
EA 2.000 $5,000.000 $2,000.000 $4,500.000 $7,500.000 $1,615.000 $2,500.000 $3,000.000
REMOV STR (INLET)
EA 7.000 $1,400.000 $2,000.000 $2,500.000 $2,200.000 $612.000 $2,500.000 $1,100.000
REMOV STR (PIPE)
LF 271.000 $25.000 $20.000 $47.000 $30.000 $22.000 $50.000 $15.000
MOBILIZATION
LS 1.000 $304,631.420 $300,000.000 $340,000.000 $473,000.000 $385,000.000 $400,000.000 $440,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $12,000.000 $5,000.000 $25,000.000 $63,000.000 $55,000.000 $8,500.000 $45,000.000
TMA (STATIONARY)
DAY 50.000 $276.000 $1,000.000 $185.000 $200.000 $346.000 $250.000 $1,000.000
TMA (MOBILE OPERATION)
HR 50.000 $108.000 $100.000 $80.000 $1,000.000 $68.000 $550.000 $50.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 72.000 $40.000 $40.000 $150.000 $55.000 $39.000 $50.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 72.000 $10.000 $10.000 $100.000 $27.500 $30.000 $20.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,015.000 $5.000 $6.000 $4.000 $3.300 $3.500 $4.000 $4.250
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 342.000 $10.000 $6.000 $9.000 $11.000 $8.250 $8.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,357.000 $1.500 $1.000 $2.250 $1.650 $1.100 $2.000 $2.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 342.000 $10.000 $10.000 $8.500 $9.900 $5.750 $18.000 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 342.000 $5.000 $1.000 $3.000 $3.300 $1.250 $9.000 $3.250
COLORED TEXTURED CONC (4")
SY 232.000 $206.000 $120.000 $210.000 $210.000 $84.000 $200.000 $330.000
CONC CURB (MONO) (TY II)
LF 3,850.000 $20.000 $25.000 $10.000 $9.000 $7.600 $20.000 $15.000
CONC CURB & GUTTER (TY II)
LF 132.000 $95.000 $20.000 $60.000 $75.000 $50.000 $55.000 $80.000
DRIVEWAYS (CONC) (HES)
SY 151.000 $250.000 $120.000 $180.000 $175.000 $98.000 $125.000 $190.000
CONC SIDEWALKS (4")
SY 617.000 $95.000 $100.000 $120.000 $90.000 $66.000 $65.000 $110.000
CURB RAMPS (TY 7)
EA 13.000 $2,500.000 $3,000.000 $3,000.000 $3,500.000 $1,700.000 $3,250.000 $5,000.000
RIGHT OF WAY MARKERS
EA 4.000 $350.000 $500.000 $500.000 $450.000 $500.000 $500.000 $500.000
CONDT (PVC) (SCH 40) (3")
LF 190.000 $25.000 $25.000 $28.000 $25.570 $15.320 $40.000 $60.000
CONDT (PVC) (SCH 40) (4")
LF 50.000 $35.000 $30.000 $32.000 $29.100 $26.670 $50.000 $60.000
CONDT (PVC) (SCH 40) (4") (BORE)
LF 615.000 $45.000 $40.000 $46.000 $42.800 $48.650 $80.000 $110.000
ELEC CONDR (NO.12) INSULATED
LF 560.000 $2.000 $3.000 $2.000 $1.930 $1.760 $3.000 $6.000
ELEC CONDR (NO.8) INSULATED
LF 1,170.000 $2.000 $3.000 $3.250 $2.890 $2.210 $3.000 $7.000
ELEC CONDR (NO.6) BARE
LF 885.000 $2.200 $3.000 $3.250 $2.890 $2.680 $3.000 $9.000
ELEC CONDR (NO.6) INSULATED
LF 40.000 $2.000 $5.000 $4.000 $3.640 $2.750 $3.000 $9.000
GROUND BOX TY D (162922)W/APRON
EA 5.000 $1,500.000 $2,500.000 $2,500.000 $2,187.080 $1,668.000 $1,500.000 $5,000.000
ELC SRV TY D 120/240 060(NS)SS(E)PS(U)
EA 1.000 $6,000.000 $12,000.000 $12,000.000 $10,833.750 $10,659.000 $12,500.000 $20,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $855.000 $600.000 $750.000 $679.450 $689.000 $1,500.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $1,500.000 $600.000 $800.000 $715.830 $697.000 $1,500.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 4.000 $687.000 $600.000 $825.000 $765.050 $596.000 $1,500.000 $900.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 3.000 $700.000 $600.000 $850.000 $786.450 $754.000 $1,500.000 $900.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 6.000 $1,200.000 $500.000 $700.000 $652.700 $594.000 $1,000.000 $800.000
RELOCATE SM RD SN SUP&AM TY S80
EA 3.000 $1,200.000 $500.000 $900.000 $829.250 $625.000 $1,000.000 $1,000.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 232.000 $2.000 $3.000 $2.250 $3.300 $3.000 $6.000 $2.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,771.000 $2.000 $2.000 $2.000 $1.650 $1.500 $6.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 660.000 $10.000 $9.000 $10.000 $7.700 $7.000 $20.000 $11.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 26.000 $250.000 $250.000 $250.000 $209.000 $190.000 $250.000 $280.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 25.000 $250.000 $300.000 $300.000 $231.000 $210.000 $250.000 $340.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 1,258.000 $2.000 $2.187 $2.000 $1.100 $1.000 $1.000 $2.250
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 2,480.000 $2.000 $2.187 $2.000 $1.100 $1.000 $1.000 $2.250
PAVEMENT SLER 6"
LF 5,665.000 $2.000 $0.700 $0.550 $0.280 $0.250 $1.000 $0.600
PAVEMENT SLER 8"
LF 4,003.000 $2.000 $1.000 $0.850 $0.390 $0.350 $1.000 $1.000
PAVEMENT SLER 24"
LF 660.000 $2.000 $3.000 $2.250 $1.100 $1.000 $6.000 $2.500
PAVEMENT SLER (ARROW)
EA 26.000 $100.000 $80.000 $85.000 $27.500 $25.000 $150.000 $90.000
PAVEMENT SLER (WORD)
EA 25.000 $100.000 $80.000 $85.000 $27.500 $25.000 $150.000 $90.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 1,927.000 $2.000 $2.000 $2.000 $1.100 $1.000 $1.000 $2.250
REFL PAV MRKR TY I-C
EA 224.000 $10.000 $7.000 $8.000 $5.500 $5.000 $6.000 $9.000
ELIM EXT PM & MRKS (4")
LF 5,058.000 $1.160 $0.800 $0.750 $0.610 $0.550 $1.000 $0.800
ELIM EXT PM & MRKS (8")
LF 3,157.000 $2.070 $0.800 $1.000 $1.100 $1.000 $6.000 $1.000
ELIM EXT PM & MRKS (12")
LF 1,124.000 $2.630 $2.500 $2.250 $1.650 $1.500 $8.000 $2.500
ELIM EXT PM & MRKS (24")
LF 229.000 $4.550 $4.000 $4.000 $3.300 $3.000 $20.000 $3.750
ELIM EXT PM & MRKS (ARROW)
EA 18.000 $110.000 $100.000 $100.000 $71.500 $65.000 $250.000 $110.000
ELIM EXT PM & MRKS (DBL ARROW)
EA 1.000 $175.000 $130.000 $135.000 $132.000 $120.000 $500.000 $150.000
ELIM EXT PM & MRKS (WORD)
EA 18.000 $150.000 $100.000 $100.000 $71.500 $65.000 $250.000 $110.000
PAV SURF PREP FOR MRK (6")
LF 5,665.000 $2.000 $0.500 $0.500 $0.060 $0.050 $1.000 $0.500
PAV SURF PREP FOR MRK (8")
LF 4,003.000 $2.000 $0.600 $0.550 $0.080 $0.070 $1.000 $0.600
PAV SURF PREP FOR MRK (24")
LF 660.000 $5.000 $1.700 $1.750 $0.220 $0.200 $6.000 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 26.000 $100.000 $70.000 $68.000 $11.000 $10.000 $150.000 $80.000
PAV SURF PREP FOR MRK (WORD)
EA 25.000 $100.000 $70.000 $68.000 $11.000 $10.000 $150.000 $80.000
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $4,000.000 $75,000.000 $90,000.000 $78,639.540 $55,430.000 $55,000.000 $50,000.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $30,000.000 $10,000.000 $12,000.000 $9,818.110 $150,000.000 $12,500.000 $11,000.000
VEH SIG SEC (12")LED(GRN)
EA 12.000 $350.000 $500.000 $500.000 $433.350 $465.000 $325.000 $1,300.000
VEH SIG SEC (12")LED(GRN ARW)
EA 12.000 $350.000 $500.000 $500.000 $433.350 $473.000 $325.000 $1,300.000
VEH SIG SEC (12")LED(YEL)
EA 12.000 $350.000 $500.000 $500.000 $433.350 $465.000 $325.000 $1,300.000
VEH SIG SEC (12")LED(YEL ARW)
EA 12.000 $350.000 $500.000 $500.000 $433.350 $473.000 $325.000 $1,300.000
VEH SIG SEC (12")LED(RED)
EA 12.000 $350.000 $500.000 $500.000 $433.350 $465.000 $325.000 $1,300.000
VEH SIG SEC (12")LED(RED ARW)
EA 8.000 $350.000 $500.000 $500.000 $433.350 $473.000 $325.000 $1,300.000
PED SIG SEC (LED)(COUNTDOWN)
EA 8.000 $350.000 $1,000.000 $1,000.000 $836.310 $879.000 $8,500.000 $2,200.000
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 16.000 $275.000 $250.000 $250.000 $222.770 $286.990 $250.000 $490.000
BACKPLATE W/REF BRDR(5 SEC)(VENT)ALUM
EA 4.000 $275.000 $400.000 $400.000 $357.270 $345.000 $300.000 $500.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 1,030.000 $2.000 $3.500 $3.500 $3.210 $3.930 $3.000 $6.000
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 80.000 $3.000 $5.000 $4.500 $3.850 $5.310 $3.000 $7.000
TRF SIG CBL (TY A)(14 AWG)(10 CONDR)
LF 1,615.000 $3.500 $5.000 $5.000 $4.280 $4.630 $3.000 $11.000
TRF SIG CBL (TY A)(14 AWG)(20 CONDR)
LF 840.000 $5.000 $8.000 $9.000 $8.350 $8.880 $3.000 $17.000
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
LF 1,675.000 $2.000 $3.000 $3.000 $2.780 $4.660 $3.000 $6.000
INS TRF SIG PL AM(S)1 ARM(65')LUM
EA 4.000 $40,000.000 $40,000.000 $50,000.000 $40,464.080 $42,502.250 $85,000.000 $70,000.000
PED POLE ASSEMBLY
EA 7.000 $3,600.000 $4,000.000 $4,400.000 $3,737.720 $4,550.000 $6,500.000 $9,000.000
PED DETECT PUSH BUTTON (APS)
EA 8.000 $900.000 $1,600.000 $2,000.000 $1,680.970 $844.000 $1,850.000 $2,900.000
REMOVAL OF TRAFFIC SIGNAL POLE FND
LF 4.000 $500.000 $500.000 $500.000 $392.800 $1,586.000 $2,500.000 $1,800.000
ITS COM CBL (ETHERNET)
LF 190.000 $3.500 $5.000 $3.500 $3.000 $3.800 $6.000 $9.000
Totals: $3,503,880.980 $3,143,471.806 $3,411,000.450 $3,769,012.310 $3,822,461.000 $3,890,474.000 $4,048,467.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
Total: $50,000.00