DENTON FM 2499 (2681-01-027)
Items: 109
County: DENTON
Length: 0.2180 MILES
Highway: FM 2499
District: DALLAS
Control Number: 2681-01-027
DBE Goal: 5.0%
Project: CM 2025(533)
Guaranty: $69,000.00
Time: 144 WORKING DAYS
Engineer's Estimate: $3,503,880.98
Date: 03/04/2025 (1 year ago)
Contract Number: 3253019
Type: INTERSECTION IMPROVEMENT
Project ID: A00177327
Contract Type: Federal
Project Description: CONSTRUCT DUAL LEFT TURN LANES ON EASTBOUND,WESTBOUND, AND SOUTHBOUND APPROACHES. CONSTRUCT ADDITIONAL THROUGH LANE NORTHBOUND, RECONFIGURE SIGNALIZATION.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AMANDA MOSER
CHRISTOPHER ROCHA
DENTON FM 2499 (2681-01-027)
Project Name: N/A
Project: CM 2025(533)
Length: 0.2180 MILES
Project Type: CONSTRUCTION
Limits From: AT FM 407 (JUSTIN ROAD)
Limits To: .
Project Description: CONSTRUCT DUAL LEFT TURN LANES ON EASTBOUND,WESTBOUND, AND SOUTHBOUND APPROACHES. CONSTRUCT ADDITIONAL THROUGH LANE NORTHBOUND, RECONFIGURE SIGNALIZATION.
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,503,880.98 | |||
| $3,143,471.81 |
-10.29%
-$360,409.17
|
|||
| $3,411,000.45 |
-2.65%
-$92,880.53
|
8.51%
$267,528.64
|
||
| $3,769,012.31 |
7.57%
$265,131.33
|
19.9%
$625,540.50
|
-10.50%
-$358,011.86
|
|
| $3,822,461.00 |
9.09%
$318,580.02
|
21.6%
$678,989.19
|
-1.42%
-$53,448.69
|
|
| $3,890,474.00 |
11.03%
$386,593.02
|
23.76%
$747,002.19
|
-1.78%
-$68,013.00
|
|
| $4,048,467.70 |
15.54%
$544,586.72
|
28.79%
$904,995.89
|
-4.06%
-$157,993.70
|
E
Engineer's Estimate
$3,503,880.98
1
Awarded
$3,143,471.81
Over/Under Est:
-10.29%
-$360,409.17
$3,411,000.45
Over/Under Est:
-2.65%
-$92,880.53
Amt Left:
8.51%
$267,528.64
$3,769,012.31
Over/Under Est:
7.57%
$265,131.33
Amt Left:
19.9%
$625,540.50
Delta:
-10.50%
-$358,011.86
$3,822,461.00
Over/Under Est:
9.09%
$318,580.02
Amt Left:
21.6%
$678,989.19
Delta:
-1.42%
-$53,448.69
$3,890,474.00
Over/Under Est:
11.03%
$386,593.02
Amt Left:
23.76%
$747,002.19
Delta:
-1.78%
-$68,013.00
$4,048,467.70
Over/Under Est:
15.54%
$544,586.72
Amt Left:
28.79%
$904,995.89
Delta:
-4.06%
-$157,993.70
| Subcontractor | Percentage | Amount |
|---|---|---|
| WG ENGINEERING & CONSTRUCTION, LLC | 16.39% | $515,215.03 |
| ADVANCED PAVING COMPANY | 11.61% | $364,957.08 |
| ROAD MASTER STRIPING, LLC | 1.44% | $45,265.99 |
| ORCA CONCRETE, LLC | 0.32% | $10,059.11 |
| MEDELLIN HDD LLC | 0.31% | $9,744.76 |
| Total: | 30.07% | $945,241.97 |
Bid Items & Bid Tabulations
109
Total
0 of 109
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |
| Total: | $50,000.00 |