DENTON SH 114 (0353-09-002)

Items: 146

County: DENTON
Length: N/A
Highway: SH 114
District: DALLAS
Control Number: 0353-09-002
DBE Goal: N/A
Project: C 353-9-2
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $46,908,124.71
Date: 06/04/2021 (5 years ago)
Contract Number: N/A
Type: CONSTRUCT 0 TO 6 LANE GRADE SEPARATION OVER US 377
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (13)
E
Engineer's Estimate
$46,908,124.71
1
$36,943,838.16
Over/Under Est: -21.24% -$9,964,286.55
Over/Under Est: -19.05% -$8,935,974.88
Amt Left: 2.78% $1,028,311.67
Over/Under Est: -15.79% -$7,408,079.26
Amt Left: 6.92% $2,556,207.29
Delta: -4.02% -$1,527,895.62
$39,975,999.98
Over/Under Est: -14.78% -$6,932,124.73
Amt Left: 8.21% $3,032,161.82
Delta: -1.20% -$475,954.53
Over/Under Est: -10.56% -$4,952,683.36
Amt Left: 13.57% $5,011,603.19
Delta: -4.95% -$1,979,441.37
$42,460,336.59
Over/Under Est: -9.48% -$4,447,788.12
Amt Left: 14.93% $5,516,498.43
Delta: -1.20% -$504,895.24
$42,539,349.82
Over/Under Est: -9.31% -$4,368,774.89
Amt Left: 15.15% $5,595,511.66
Delta: -0.19% -$79,013.23
Over/Under Est: -8.67% -$4,066,760.50
Amt Left: 15.96% $5,897,526.05
Delta: -0.71% -$302,014.39
Over/Under Est: -8.61% -$4,037,770.77
Amt Left: 16.04% $5,926,515.78
Delta: -0.07% -$28,989.73
$43,154,479.35
Over/Under Est: -8% -$3,753,645.36
Amt Left: 16.81% $6,210,641.19
Delta: -0.66% -$284,125.41
$44,555,607.06
Over/Under Est: -5.02% -$2,352,517.65
Amt Left: 20.6% $7,611,768.90
Delta: -3.25% -$1,401,127.71
$45,600,100.27
Over/Under Est: -2.79% -$1,308,024.44
Amt Left: 23.43% $8,656,262.11
Delta: -2.34% -$1,044,493.21
Over/Under Est: 0.44% $207,594.82
Amt Left: 27.53% $10,171,881.37
Delta: -3.32% -$1,515,619.26

Bid Items & Bid Tabulations

146 Total 0 of 146
DENTON  |  SH 114  |  DALLAS  |  0353-09-002  |  06/04/2021  |  $46,908,124.71  |  C 353-9-2  |  CONSTRUCT 0 TO 6 LANE GRADE SEPARATI...  |  0 X
Item Code
Description
Unit
Quantity
Engineer's Estimate
WEBBER, LLC
AUSTIN BRIDGE & ROAD SERVICES, LP
ZACHRY CONSTRUCTION CORPORATION
FLUOR HEAVY CIVIL, LLC
ARCHER WESTERN CONSTRUCTION, LLC
SEMA CONSTRUCTION, INC.
J.D. ABRAMS, L.P.
RAGLE CONSTRUCTION, INC.
ED BELL CONSTRUCTION COMPANY
SUNDT CONSTRUCTION, INC.
OHL USA, INC.
COPASA INC
FLATIRON CONSTRUCTORS, INC.
PREPARING ROW
STA 56.900 $5,000.000 $1,070.000 $12,331.390 $28,687.660 $844.500 $1,414.500 $14,500.000 $26,000.000 $60,000.000 $13,500.000 $5,450.000 $32,000.000 $12,500.000 $69,330.170
REMOVING CONC (PAV)
SY 492.000 $7.920 $29.200 $20.740 $10.000 $14.610 $19.200 $14.000 $40.000 $12.750 $20.000 $20.000 $21.000 $8.690 $40.000
REMOVING CONCRETE(MOW STRIP)
LF 465.000 $17.500 $5.250 $2.650 $3.000 $2.470 $3.600 $2.400 $8.000 $4.500 $5.000 $4.000 $17.000 $9.210 $10.000
REMOVING STAB BASE AND ASPH PAV (4")
SY 758.000 $4.150 $7.000 $6.530 $3.000 $3.960 $7.100 $8.000 $7.000 $4.500 $20.000 $8.000 $11.000 $3.690 $15.000
EXCAVATION (ROADWAY)
CY 15,787.000 $8.500 $5.200 $9.500 $7.000 $3.880 $8.900 $5.000 $7.250 $4.000 $15.000 $8.000 $5.110 $7.720 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 14,968.000 $11.000 $11.000 $6.300 $5.000 $7.350 $8.700 $7.500 $17.010 $10.000 $15.000 $16.000 $6.550 $14.090 $15.000
BACKFILL (TY A OR B)
STA 22.200 $214.000 $560.000 $191.250 $250.000 $141.410 $490.400 $360.000 $770.000 $200.000 $275.000 $236.000 $3,000.000 $198.230 $362.160
COMPOST MANUF TOPSOIL (4")
SY 34,029.000 $1.200 $0.600 $0.890 $1.600 $1.030 $1.660 $2.500 $2.200 $0.590 $0.600 $0.620 $5.500 $0.590 $2.470
BLOCK SODDING
SY 34,029.000 $3.000 $2.500 $2.490 $2.600 $2.490 $2.900 $2.900 $2.700 $4.500 $2.600 $2.600 $2.490 $2.490 $2.490
DRILL SEED (TEMP)(WARM OR COOL)
SY 34,029.000 $0.240 $0.100 $0.080 $0.100 $0.080 $0.100 $0.110 $0.100 $0.080 $0.040 $0.090 $0.080 $0.080 $0.080
VEGETATIVE WATERING
MG 6,328.000 $2.500 $25.700 $17.000 $29.000 $17.000 $20.000 $12.500 $0.010 $0.010 $2.100 $26.000 $11.880 $17.000 $17.000
LIME (HYDRATED LIME (SLURRY))
TON 473.000 $185.500 $172.000 $175.500 $160.000 $181.190 $172.000 $150.000 $180.600 $170.000 $175.000 $175.000 $250.000 $172.000 $179.750
LIME TRT (EXST MATL)(10")
SY 20,864.000 $5.250 $3.850 $3.510 $4.200 $3.460 $3.500 $4.650 $4.420 $2.500 $4.000 $5.500 $9.000 $5.460 $5.240
LIME TRT (EXST MATL)(8")
SY 8,934.000 $3.500 $4.150 $3.490 $4.000 $5.660 $3.500 $4.500 $4.810 $2.750 $3.900 $5.500 $9.000 $6.610 $5.300
CONC PVMT (CONT REINF - CRCP) (10")
SY 359.000 $52.530 $78.000 $73.670 $72.000 $88.870 $79.000 $84.000 $88.370 $78.000 $105.000 $110.000 $120.550 $110.170 $114.310
CONC PVMT (CONT REINF - CRCP) (11")
SY 8,732.000 $62.000 $69.250 $67.440 $52.000 $76.490 $81.000 $70.000 $75.000 $75.000 $68.000 $85.000 $100.000 $83.360 $78.220
CONC PVMT (CONT REINF - CRCP) (13")
SY 19,619.000 $85.000 $77.500 $77.740 $58.000 $84.780 $88.000 $73.000 $86.000 $84.000 $75.000 $95.000 $94.000 $93.860 $81.750
CEM STABIL BKFL
CY 941.000 $250.000 $109.000 $126.390 $105.000 $92.220 $135.700 $110.000 $140.000 $78.000 $175.000 $140.000 $138.590 $130.620 $151.290
TRENCH EXCAVATION PROTECTION
LF 1,268.000 $2.500 $1.950 $1.620 $2.000 $0.190 $1.000 $7.000 $3.000 $1.000 $5.000 $1.000 $3.410 $2.900 $1.170
DRILL SHAFT (18 IN)
LF 308.000 $95.000 $50.250 $90.360 $80.000 $80.000 $83.200 $102.000 $100.750 $60.000 $73.500 $110.000 $98.650 $81.390 $100.000
DRILL SHAFT (42 IN)
LF 7,831.000 $330.000 $169.000 $166.640 $188.000 $210.000 $192.500 $190.000 $200.000 $165.000 $190.000 $220.000 $178.210 $290.920 $215.000
DRILL SHAFT (48 IN)
LF 2,515.000 $550.000 $220.000 $224.980 $230.000 $230.000 $220.100 $320.000 $235.000 $200.000 $265.000 $320.000 $209.560 $346.500 $245.000
DRILL SHAFT (SIGN MTS) (30 IN)
LF 104.000 $280.000 $200.000 $200.000 $246.000 $246.000 $248.500 $215.000 $260.000 $212.050 $309.420 $400.000 $283.000 $200.000 $246.000
DRILL SHAFT (SIGN MTS) (42 IN)
LF 14.000 $350.000 $300.000 $300.000 $455.000 $455.000 $459.600 $315.000 $480.000 $318.080 $415.020 $460.000 $358.500 $300.000 $455.000
DRILL SHAFT (SIGN MTS) (48 IN)
LF 66.000 $390.000 $360.000 $360.000 $420.000 $419.000 $423.200 $375.000 $455.000 $381.700 $542.410 $450.000 $409.500 $360.000 $419.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 51.000 $476.000 $420.000 $420.000 $441.000 $441.000 $668.200 $435.000 $465.000 $445.310 $655.620 $445.000 $468.600 $420.000 $441.000
CL C CONC (ABUT)(HPC)
CY 231.700 $988.000 $739.000 $1,152.970 $810.000 $991.520 $685.000 $760.000 $1,100.000 $800.000 $750.000 $950.000 $950.000 $1,300.000 $1,000.000
CL C CONC (CAP)(HPC)
CY 1,576.700 $1,000.000 $654.000 $924.080 $935.000 $708.690 $860.000 $820.000 $950.000 $850.000 $780.000 $1,250.000 $800.710 $1,700.000 $1,100.000
CL C CONC (CAP)(HPC)(EXTEND)
CY 13.500 $2,012.000 $1,460.000 $1,564.060 $1,500.000 $2,752.140 $1,564.300 $1,750.000 $1,773.430 $1,775.000 $1,450.000 $3,000.000 $1,605.060 $2,500.000 $2,700.000
CL C CONC (COLUMN)
CY 14.900 $900.000 $850.000 $724.960 $730.000 $757.680 $795.000 $936.000 $1,082.540 $975.000 $950.000 $1,100.000 $990.380 $1,400.000 $1,100.000
CL C CONC (COLUMN)(HPC)
CY 1,680.100 $1,400.000 $707.000 $779.160 $740.000 $832.470 $650.000 $850.000 $950.000 $650.000 $800.000 $1,100.000 $855.000 $1,500.000 $1,200.000
REINF CONC SLAB (HPC)
SF 340,465.000 $18.000 $15.300 $14.940 $16.000 $15.690 $18.700 $15.500 $17.300 $16.500 $15.000 $17.150 $20.000 $17.870 $14.280
APPROACH SLAB (HPC)
CY 255.000 $425.000 $429.000 $417.920 $460.000 $590.950 $450.000 $460.000 $525.000 $450.000 $500.000 $465.000 $609.710 $500.420 $653.960
PRESTR CONC GIRDER (TX46)
LF 605.090 $134.000 $142.000 $135.760 $140.000 $144.360 $175.000 $156.000 $143.000 $123.000 $175.000 $150.000 $135.240 $149.900 $160.000
PRESTR CONC GIRDER (TX62)
LF 29,778.080 $153.000 $146.000 $141.750 $155.000 $153.140 $170.000 $159.000 $150.000 $123.000 $175.000 $161.000 $147.310 $160.290 $175.000
RIPRAP (CONC)(4 IN)
CY 788.000 $439.000 $416.000 $533.370 $190.000 $479.670 $375.000 $490.000 $470.000 $415.000 $450.000 $447.000 $227.850 $415.160 $433.950
RIPRAP (MOW STRIP)(4 IN)
CY 66.000 $500.000 $416.000 $562.610 $484.000 $591.430 $755.300 $525.000 $590.000 $445.000 $550.000 $550.000 $405.060 $474.550 $462.070
ELASTOMERIC BEARING (EE6)
EA 15.000 $2,570.000 $1,160.000 $1,157.000 $1,500.000 $2,857.980 $2,200.000 $1,400.000 $2,561.690 $2,000.000 $1,450.000 $1,430.000 $1,424.790 $2,154.040 $1,487.920
ELASTOMERIC BEARING (EE7)
EA 4.000 $2,180.000 $1,200.000 $1,200.000 $1,500.000 $2,882.200 $2,300.000 $1,440.000 $2,606.840 $2,000.000 $1,500.000 $1,475.000 $1,702.110 $1,970.360 $1,534.390
ELASTOMERIC BEARING (F7)
EA 19.000 $2,500.000 $2,550.000 $2,554.050 $2,850.000 $4,395.980 $3,700.000 $2,900.000 $4,381.100 $2,000.000 $2,900.000 $2,830.000 $2,818.320 $3,567.300 $2,883.540
SLIDING ELASTOMERIC BEARING (ES 6)
EA 4.000 $2,570.000 $2,010.000 $2,013.000 $2,325.000 $3,957.750 $3,100.000 $2,300.000 $3,460.490 $2,000.000 $2,500.000 $2,290.000 $2,515.110 $3,045.110 $2,347.390
ELASTOMERIC BEARING(EE4)
EA 15.000 $1,200.000 $1,030.000 $1,028.000 $1,350.000 $2,683.110 $2,100.000 $1,300.000 $2,426.240 $2,000.000 $1,300.000 $1,300.000 $1,295.790 $1,933.930 $1,164.130
STR STEEL (PLATE GIRDER)
LB 5,186,700.000 $2.000 $1.750 $1.790 $1.800 $1.900 $1.860 $1.980 $1.730 $1.750 $2.000 $1.760 $1.840 $1.813 $1.860
RAIL (TY SSTR)
LF 3,800.000 $39.000 $40.000 $46.560 $35.000 $45.010 $45.300 $69.000 $58.500 $55.000 $40.000 $45.000 $48.870 $53.070 $52.920
RAIL (TY SSTR)(HPC)
LF 12,601.900 $48.000 $44.500 $50.150 $40.000 $53.570 $54.000 $61.000 $61.500 $55.000 $50.000 $54.000 $57.780 $57.690 $52.830
RAIL (CLF-RO)
LF 1,423.900 $100.000 $121.000 $121.000 $100.000 $240.000 $82.800 $147.000 $132.000 $121.000 $150.000 $121.000 $121.000 $110.990 $85.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 944.000 $115.000 $108.000 $121.320 $143.000 $130.730 $125.800 $114.000 $138.080 $105.000 $80.000 $130.000 $167.440 $112.700 $146.180
SEALED EXPANSION JOINT (5 IN) (SEJ - M)
LF 310.000 $125.000 $109.000 $123.370 $143.000 $130.730 $125.800 $115.000 $138.080 $105.000 $80.000 $130.000 $149.480 $125.080 $146.180
RC PIPE (CL III)(24 IN)
LF 1,339.000 $68.500 $69.250 $56.000 $75.000 $73.850 $86.100 $75.000 $85.000 $65.000 $75.000 $100.000 $78.600 $71.310 $113.400
RC PIPE (CL III)(30 IN)
LF 6.000 $117.870 $307.000 $120.000 $462.000 $403.290 $964.500 $200.000 $330.000 $200.000 $400.000 $600.000 $229.380 $95.930 $484.010
INLET (COMPL)(PSL)(RG)(3FTX3FT)
EA 2.000 $2,500.000 $4,020.000 $3,300.000 $3,800.000 $3,657.400 $4,212.600 $3,400.000 $4,100.000 $4,350.000 $4,500.000 $5,000.000 $3,512.940 $2,500.000 $3,886.250
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
EA 6.000 $5,800.000 $5,020.000 $4,250.000 $4,600.000 $4,582.610 $5,030.600 $4,400.000 $5,100.000 $5,250.000 $5,750.000 $5,800.000 $4,455.080 $4,835.970 $4,374.640
REMOV STR (INLET)
EA 4.000 $700.000 $571.000 $500.000 $900.000 $587.560 $634.500 $550.000 $915.000 $450.000 $500.000 $600.000 $1,864.820 $594.600 $418.820
REMOV STR (PIPE)
LF 487.000 $15.500 $14.200 $8.000 $17.000 $14.190 $13.700 $16.000 $15.500 $13.500 $20.000 $20.000 $35.030 $14.360 $14.610
MOBILIZATION
LS 1.000 $4,720,000.000 $3,016,884.000 $2,661,673.140 $3,000,000.000 $3,540,000.000 $3,680,000.000 $3,700,000.000 $2,825,000.000 $3,600,000.000 $3,377,551.000 $4,250,000.000 $3,900,000.000 $4,080,000.000 $3,965,541.110
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $7,000.000 $4,480.000 $3,681.020 $10,000.000 $2,843.330 $9,630.000 $22,000.000 $8,000.000 $50,000.000 $21,000.000 $6,000.000 $12,406.020 $1,000.000 $3,343.450
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 522.000 $28.000 $20.600 $20.600 $57.000 $20.600 $26.300 $29.000 $31.000 $20.600 $278.500 $22.000 $20.600 $20.600 $20.600
ROCK FILTER DAMS (REMOVE)
LF 522.000 $7.000 $6.800 $6.790 $6.000 $6.790 $6.900 $11.000 $10.000 $6.790 $12.500 $7.500 $6.790 $6.790 $6.790
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 246.000 $21.400 $16.700 $16.740 $17.000 $16.740 $22.700 $21.000 $28.000 $16.740 $22.000 $18.000 $16.740 $16.740 $16.740
CONSTRUCTION EXITS (REMOVE)
SY 246.000 $9.400 $5.900 $5.920 $6.000 $5.920 $6.000 $6.000 $11.000 $5.920 $10.000 $6.500 $5.920 $5.920 $5.920
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,712.000 $2.500 $1.750 $1.750 $1.750 $1.750 $3.100 $2.500 $2.500 $1.750 $2.000 $1.850 $1.750 $1.750 $1.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,712.000 $0.600 $0.300 $0.290 $0.300 $0.290 $0.300 $0.450 $0.700 $0.290 $0.100 $0.300 $0.290 $0.290 $0.290
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 605.000 $5.750 $6.100 $6.100 $6.000 $6.100 $11.600 $4.600 $6.500 $6.100 $3.500 $6.500 $6.100 $6.100 $6.100
BIODEG EROSN CONT LOGS (REMOVE)
LF 605.000 $1.050 $0.300 $0.320 $0.350 $0.320 $0.300 $0.650 $1.250 $0.320 $1.000 $0.350 $0.320 $0.320 $0.320
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 4,110.000 $23.500 $24.200 $14.970 $6.000 $8.750 $7.500 $15.500 $12.500 $25.000 $7.000 $30.000 $6.690 $37.000 $21.220
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 4,170.000 $5.000 $7.050 $4.900 $5.000 $5.320 $5.000 $9.500 $6.000 $8.000 $7.000 $6.250 $3.070 $6.000 $6.500
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 3,027.000 $61.000 $57.500 $57.090 $65.000 $65.220 $58.100 $73.000 $83.000 $55.000 $65.000 $65.750 $90.000 $59.000 $64.020
PERM CTB (SGL SLOPE) (TY 3) (42 )
LF 285.000 $260.000 $150.000 $165.900 $128.000 $180.020 $172.100 $196.000 $185.000 $1.000 $315.000 $188.000 $250.000 $160.000 $200.930
MTL W-BEAM GD FEN (STEEL POST)
LF 950.000 $25.500 $22.300 $22.250 $23.000 $25.000 $33.300 $24.000 $24.000 $24.000 $25.750 $22.500 $22.250 $24.000 $22.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,830.000 $1,600.000 $1,600.000 $1,600.000 $1,900.000 $2,234.500 $1,700.000 $1,900.000 $1,700.000 $2,250.000 $1,650.000 $1,600.000 $1,700.000 $1,600.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,150.000 $979.000 $979.000 $980.000 $1,100.000 $1,318.100 $1,050.000 $1,100.000 $1,000.000 $1,100.000 $1,000.000 $979.000 $1,000.000 $979.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $2.570 $1.750 $1.750 $2.000 $3.000 $2.500 $1.850 $2.000 $3.000 $5.000 $5.000 $1.750 $3.000 $1.750
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $242.000 $175.000 $175.000 $175.000 $250.000 $150.600 $185.000 $185.000 $125.000 $312.000 $300.000 $175.000 $125.000 $175.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,570.000 $2,400.000 $2,395.000 $2,400.000 $2,795.000 $2,862.100 $2,500.000 $2,600.000 $2,350.000 $3,000.000 $2,400.000 $2,395.000 $2,350.000 $2,395.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $244.000 $175.000 $175.000 $175.000 $250.000 $150.600 $182.000 $185.000 $250.000 $300.000 $300.000 $175.000 $250.000 $175.000
CRASH CUSH ATTEN (REMOVE)
EA 3.000 $751.440 $700.000 $700.000 $700.000 $850.000 $957.600 $715.000 $570.000 $750.000 $750.000 $525.000 $700.000 $750.000 $700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $8,200.000 $8,000.000 $8,000.000 $8,000.000 $10,000.000 $7,072.110 $7,500.000 $8,400.000 $7,700.000 $9,500.000 $7,000.000 $8,000.000 $7,700.000 $8,000.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 4.000 $1,215.000 $1,300.000 $1,575.000 $1,630.000 $1,630.000 $1,646.500 $1,350.000 $1,720.000 $1,378.360 $1,071.200 $1,650.000 $1,663.100 $1,300.000 $1,630.000
CONDT (PVC) (SCH 40) (2")
LF 389.000 $9.250 $9.000 $9.160 $17.500 $17.500 $17.700 $9.500 $18.500 $9.540 $11.480 $18.000 $17.860 $9.000 $17.500
CONDT (PVC) (SCH 40) (2") (BORE)
LF 51.000 $22.750 $23.000 $21.550 $41.050 $41.050 $41.500 $24.000 $43.500 $24.390 $24.850 $41.500 $41.880 $23.000 $41.050
CONDT (PVC) (SCH 80) (2")
LF 57.000 $9.950 $13.000 $11.900 $23.650 $23.650 $23.900 $13.500 $25.000 $13.780 $19.660 $24.000 $24.130 $13.000 $23.650
CONDT (RM) (1")
LF 232.000 $20.950 $20.000 $41.500 $33.700 $33.700 $34.000 $21.000 $36.000 $21.210 $25.760 $34.000 $34.380 $20.000 $33.700
CONDT (RM) (2")
LF 266.000 $35.400 $30.000 $52.000 $36.700 $36.700 $37.100 $32.000 $39.000 $31.810 $40.970 $37.000 $37.450 $30.000 $36.700
ELEC CONDR (NO.12) BARE
LF 232.000 $1.000 $0.950 $0.670 $1.450 $1.450 $1.500 $1.000 $1.550 $1.010 $1.380 $1.500 $1.480 $0.950 $1.450
ELEC CONDR (NO.12) INSULATED
LF 464.000 $1.150 $1.000 $0.820 $1.500 $1.500 $1.500 $1.100 $1.600 $1.060 $1.450 $1.550 $1.530 $1.000 $1.500
ELEC CONDR (NO.8) BARE
LF 706.000 $1.250 $1.100 $1.040 $2.000 $2.050 $2.100 $1.150 $2.200 $1.170 $1.840 $2.100 $2.090 $1.100 $2.050
ELEC CONDR (NO.8) INSULATED
LF 1,412.000 $1.500 $1.250 $1.450 $2.000 $2.050 $2.100 $1.300 $2.200 $1.330 $1.730 $2.100 $2.090 $1.250 $2.050
GROUND BOX TY A (122311)W/APRON
EA 2.000 $987.000 $950.000 $1,160.500 $1,405.000 $1,405.000 $1,419.200 $1,000.000 $1,500.000 $1,007.260 $987.070 $1,425.000 $1,433.530 $950.000 $1,405.000
GROUND BOX TY D (162922)W/APRON
EA 1.000 $1,157.000 $1,100.000 $1,203.300 $1,490.000 $1,490.000 $1,505.100 $1,200.000 $1,600.000 $1,166.300 $1,087.530 $1,525.000 $1,520.250 $1,100.000 $1,490.000
ELC SRV TY A 120/240 060(NS)SS(E)GC(O)
EA 1.000 $6,200.000 $4,200.000 $6,210.000 $7,425.000 $7,425.000 $7,500.000 $4,500.000 $7,800.000 $4,453.140 $6,892.860 $7,550.000 $7,575.760 $4,200.000 $7,425.000
ELC SRV TY D 120/240 060(NS)SS(N)PS(U)
EA 1.000 $6,931.000 $5,200.000 $6,477.500 $7,665.000 $7,665.000 $7,742.400 $5,350.000 $8,100.000 $5,513.420 $6,415.760 $7,750.000 $7,820.630 $5,200.000 $7,665.000
ALUMINUM SIGNS (TY O)
SF 1,503.250 $25.000 $26.000 $26.000 $27.000 $24.000 $27.400 $27.000 $29.000 $27.570 $29.950 $27.500 $25.430 $26.000 $27.100
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 4.950 $19.500 $17.000 $17.000 $160.000 $40.000 $161.600 $18.000 $170.000 $18.020 $55.380 $162.000 $25.000 $17.000 $160.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $557.000 $550.000 $550.000 $955.000 $540.000 $611.400 $570.000 $1,050.000 $583.150 $430.310 $560.000 $530.000 $550.000 $955.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $648.680 $630.000 $630.000 $970.000 $575.000 $646.000 $650.000 $1,100.000 $667.970 $443.810 $600.000 $560.000 $630.000 $970.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $810.900 $685.000 $685.000 $1,120.000 $745.000 $830.600 $710.000 $1,200.000 $726.290 $602.870 $775.000 $720.000 $685.000 $1,120.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $880.000 $1,050.000 $1,050.000 $1,420.000 $975.000 $980.600 $1,100.000 $1,500.000 $1,113.290 $798.620 $1,025.000 $850.000 $1,050.000 $1,420.000
IN SM RD SN SUP&AM TYS80(2)SB(P)
EA 1.000 $1,212.000 $900.000 $900.000 $2,495.000 $1,700.000 $1,730.400 $1,000.000 $2,650.000 $954.250 $1,363.220 $1,750.000 $1,500.000 $900.000 $2,495.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 3.000 $2,198.100 $1,800.000 $1,800.000 $2,925.000 $1,800.000 $2,954.600 $1,900.000 $3,100.000 $1,908.490 $2,058.420 $1,850.000 $1,824.410 $1,800.000 $2,925.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 5.000 $3,100.000 $2,500.000 $2,500.000 $5,100.000 $3,300.000 $5,151.500 $2,600.000 $5,400.000 $2,650.680 $4,811.560 $3,400.000 $1,836.670 $2,500.000 $5,100.000
INS OH SN SUP(25 FT CANT)
EA 1.000 $18,330.000 $13,500.000 $13,500.000 $18,365.000 $18,365.000 $18,550.500 $14,000.000 $19,500.000 $14,313.680 $17,030.100 $19,000.000 $18,737.880 $13,500.000 $18,365.000
INS OH SN SUP(30 FT CANT)
EA 2.000 $22,500.000 $23,000.000 $23,000.000 $51,610.000 $51,610.000 $52,131.300 $24,000.000 $53,000.000 $24,386.270 $44,499.890 $53,000.000 $52,657.890 $23,000.000 $51,610.000
INS OH SN SUP(40 FT CANT)
EA 3.000 $25,100.000 $24,000.000 $24,000.000 $27,110.000 $27,110.000 $27,383.800 $25,000.000 $29,000.000 $25,446.540 $24,926.250 $27,385.000 $27,660.440 $24,000.000 $27,110.000
INS OH SN SUP(95 FT BRDG)
EA 1.000 $45,000.000 $54,000.000 $54,000.000 $42,175.000 $42,175.000 $42,601.000 $56,000.000 $45,000.000 $57,254.710 $47,293.170 $50,000.000 $43,031.320 $54,000.000 $42,175.000
INS OH SN SUP(105 FT BRDG)
EA 1.000 $47,000.000 $56,000.000 $56,000.000 $50,125.000 $50,125.000 $50,631.300 $58,000.000 $53,000.000 $59,375.260 $56,101.810 $55,000.000 $51,142.740 $56,000.000 $50,125.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 47.000 $20.160 $23.000 $22.000 $23.000 $15.000 $23.400 $23.000 $23.100 $23.330 $25.000 $20.000 $19.660 $22.000 $15.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 46.000 $26.000 $20.000 $23.000 $20.000 $15.000 $26.100 $24.000 $24.150 $24.390 $27.500 $20.000 $20.000 $23.000 $15.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 103.000 $20.000 $23.000 $21.000 $23.000 $15.000 $23.400 $22.000 $22.050 $22.270 $25.000 $20.000 $19.940 $21.000 $15.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 1,020.000 $0.890 $0.750 $0.750 $1.000 $0.800 $3.100 $0.820 $0.830 $0.800 $0.830 $0.750 $3.000 $1.000 $1.400
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 5,384.000 $0.400 $0.750 $0.750 $1.000 $0.800 $1.000 $0.820 $0.830 $0.800 $0.830 $0.750 $1.000 $1.000 $1.000
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 655.000 $1.350 $1.150 $1.150 $1.150 $1.220 $3.600 $1.250 $1.280 $1.220 $1.270 $1.150 $3.500 $2.000 $1.850
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 5,729.000 $0.850 $0.750 $0.750 $1.000 $0.800 $1.000 $0.820 $0.830 $0.800 $0.830 $0.750 $1.000 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,782.000 $0.300 $0.800 $0.780 $0.850 $0.830 $1.100 $0.850 $0.870 $0.830 $0.860 $0.780 $1.050 $0.850 $1.000
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 242.000 $2.900 $2.850 $2.850 $2.850 $3.030 $2.200 $3.100 $3.170 $3.030 $3.150 $2.850 $2.150 $3.500 $2.390
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $139.330 $190.000 $190.000 $190.000 $201.890 $204.100 $206.000 $212.000 $201.890 $209.960 $190.000 $200.000 $133.000 $100.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $164.540 $190.000 $190.000 $190.000 $201.890 $204.100 $206.000 $212.000 $201.890 $209.960 $190.000 $200.000 $160.000 $135.000
PAVEMENT SEALER 4"
LF 28,703.000 $0.190 $0.150 $0.140 $0.150 $0.150 $0.100 $0.160 $0.160 $0.150 $0.150 $0.140 $0.140 $0.140 $0.120
PAVEMENT SEALER 6"
LF 1,694.000 $0.150 $0.150 $0.160 $0.200 $0.170 $0.200 $0.180 $0.180 $0.170 $0.180 $0.160 $0.180 $0.200 $0.300
PAVEMENT SEALER 8"
LF 4,782.000 $0.400 $0.200 $0.200 $0.200 $0.210 $0.300 $0.220 $0.220 $0.210 $0.220 $0.200 $0.280 $0.300 $0.350
PAVEMENT SEALER 12"
LF 242.000 $1.150 $1.000 $1.000 $1.000 $1.060 $0.800 $1.100 $1.110 $1.060 $1.110 $1.000 $168.340 $1.350 $1.000
PAVEMENT SEALER (ARROW)
EA 2.000 $26.580 $70.000 $70.000 $70.000 $74.380 $51.000 $77.000 $78.000 $74.380 $77.360 $70.000 $50.000 $55.000 $40.000
PAVEMENT SEALER (WORD)
EA 2.000 $37.500 $70.000 $70.000 $70.000 $74.380 $51.000 $77.000 $78.000 $74.380 $77.360 $70.000 $50.000 $55.000 $45.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 170.000 $0.790 $0.400 $0.380 $0.500 $0.400 $0.500 $0.420 $0.420 $0.400 $0.420 $0.380 $0.500 $1.000 $0.480
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 13,263.000 $0.400 $0.350 $0.340 $0.500 $0.360 $0.500 $0.380 $0.380 $0.360 $0.380 $0.340 $0.490 $0.500 $0.440
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,694.000 $0.600 $0.500 $0.500 $1.000 $0.530 $0.700 $0.540 $0.560 $0.530 $0.550 $0.500 $0.670 $1.000 $0.650
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 15,270.000 $0.380 $0.350 $0.340 $0.500 $0.360 $0.500 $0.380 $0.380 $0.360 $0.380 $0.340 $0.490 $0.500 $0.440
REFL PAV MRKR TY II-C-R
EA 328.000 $3.600 $3.450 $3.450 $4.000 $3.670 $5.100 $3.750 $3.840 $3.670 $3.810 $3.450 $5.000 $4.000 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 14,711.000 $0.400 $0.300 $0.280 $0.550 $0.300 $0.500 $0.320 $0.310 $0.300 $0.310 $0.280 $0.500 $0.550 $0.400
PAV SURF PREP FOR MRK (4")
LF 28,703.000 $0.050 $0.300 $0.320 $0.350 $0.340 $0.100 $0.350 $0.360 $0.340 $0.350 $0.320 $0.020 $0.070 $0.120
PAV SURF PREP FOR MRK (6")
LF 1,694.000 $0.100 $0.300 $0.280 $0.300 $0.300 $0.100 $0.320 $0.310 $0.300 $0.310 $0.280 $0.020 $0.120 $0.180
PAV SURF PREP FOR MRK (8")
LF 4,782.000 $0.150 $0.300 $0.280 $0.300 $0.300 $0.100 $0.320 $0.310 $0.300 $0.310 $0.280 $0.080 $0.150 $0.250
PAV SURF PREP FOR MRK (12")
LF 242.000 $0.680 $0.400 $0.400 $0.400 $0.430 $0.300 $0.450 $0.440 $0.430 $0.440 $0.400 $0.310 $0.500 $0.750
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $21.400 $50.000 $50.000 $50.000 $53.130 $30.600 $54.000 $56.000 $53.130 $55.260 $50.000 $30.000 $50.000 $30.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $32.200 $50.000 $50.000 $50.000 $53.130 $30.600 $54.000 $56.000 $53.130 $55.260 $50.000 $30.000 $50.000 $35.000
SPOT MOWING
AC 20.000 $197.800 $300.000 $250.000 $169.000 $325.000 $408.200 $550.000 $160.000 $325.000 $400.000 $425.000 $890.560 $206.320 $325.000
NO. OF WORKING DAYS
$/D 11,000.000 $528.000 $416.000 $416.000 $416.000 $416.000 $468.000 $480.000 $528.000 $498.000 $528.000 $416.000 $468.000 $416.000 $528.000
SP MIXES SP-B PG64-22
TON 6,557.700 $80.000 $57.000 $68.230 $57.000 $57.000 $74.100 $63.000 $61.000 $77.350 $60.000 $57.000 $86.000 $73.250 $57.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,730.000 $17,210.000 $7,500.000 $15,000.000 $9,772.000 $1,786.100 $15,400.000 $8,100.000 $20,000.000 $15,000.000 $10,000.000 $8,000.000 $12,000.000 $17,320.000
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $71,220.000 $30,000.000 $65,750.000 $98,150.000 $98,150.000 $99,141.400 $31,200.000 $100,000.000 $31,808.170 $93,100.800 $100,000.000 $100,142.840 $30,000.000 $98,150.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 1.000 $5,134.000 $6,000.000 $7,275.000 $9,875.000 $9,875.000 $9,974.800 $6,400.000 $10,500.000 $6,361.630 $7,849.660 $10,000.000 $10,075.500 $6,000.000 $9,875.000
ITS RADIO (SNGL)(5 GHZ)-C-P
EA 1.000 $2,400.000 $5,000.000 $3,415.000 $7,890.000 $7,890.000 $7,969.700 $5,400.000 $8,200.000 $5,301.360 $5,020.030 $8,000.000 $8,050.200 $5,000.000 $7,890.000
ITS POLE (60 FT)(90 MPH)
EA 1.000 $13,781.000 $16,500.000 $15,625.000 $18,885.000 $18,885.000 $19,075.800 $17,200.000 $20,000.000 $17,494.500 $17,351.880 $19,500.000 $19,268.440 $16,500.000 $18,885.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 1.000 $6,245.000 $4,200.000 $5,150.000 $5,150.000 $5,150.000 $5,202.000 $4,500.000 $5,500.000 $4,453.140 $5,605.860 $5,250.000 $5,254.570 $4,200.000 $5,150.000
TMA (STATIONARY)
DAY 161.000 $200.000 $280.000 $171.570 $500.000 $109.390 $150.000 $165.000 $130.000 $200.000 $150.000 $290.000 $254.600 $158.490 $162.380
TMA (MOBILE OPERATION)
DAY 4.000 $120.000 $697.000 $469.220 $2,100.000 $500.210 $695.000 $505.000 $1,285.000 $615.000 $1,000.000 $800.000 $613.240 $128.470 $752.340
ITS RVSD (DATA COLLECT & WWA) SYS
EA 1.000 $9,975.000 $9,000.000 $8,755.500 $14,075.000 $14,075.230 $14,217.200 $9,500.000 $15,000.000 $9,542.450 $9,178.520 $14,250.000 $14,360.780 $9,000.000 $14,075.000
Totals: $46,908,124.715 $36,943,838.160 $37,972,149.870 $39,500,045.454 $39,976,000.005 $41,955,441.350 $42,460,336.590 $42,539,349.831 $42,841,364.226 $42,870,353.948 $43,154,479.355 $44,555,607.085 $45,600,100.287 $47,115,719.547