Show Job Controls
Bid Cobra

DENTON IH 35E (0196-02-132)

Items: 232

County: DENTON
Length: N/A
Highway: IH 35E
District: DALLAS
Control Number: 0196-02-132
DBE Goal: N/A
Project: F 2022(043)
Guaranty: N/A
Time: 252 WORKING DAYS
Engineer's Estimate: $11,761,702.58
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: HIGHWAY OPERATIONS PROGRAM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$11,761,702.58
Over/Under Est: 69.94% $8,226,276.43

Bid Items & Bid Tabulations

232 Total 0 of 232
DENTON  |  IH 35E  |  DALLAS  |  0196-02-132  |  06/29/2022  |  $11,761,702.58  |  F 2022(043)  |  HWY OPERATIONS PROGRAM  |  252 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
PREPARING ROW
STA 112.000 $7,000.000 $16,900.000
REMOVING CONC (PAV)
SY 3,020.000 $6.330 $16.500
REMOVING CONC (RIPRAP)
SY 56.000 $9.950 $65.000
REMOVING CONC (CURB AND GUTTER)
LF 470.000 $2.500 $9.500
REMOVING CONC (CTB)
LF 3,860.000 $5.460 $35.000
REMOVE CONC (WINGWALL)
CY 3.000 $500.000 $430.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 128.000 $15.000 $15.000
REMOVING CONC (FLUME)
SY 46.000 $9.140 $35.000
REMOVING STAB BASE AND ASPH PAV (2")
SY 2,137.000 $2.270 $7.500
REMOVING STAB BASE AND ASPH PAV(4"-16")
SY 10,107.000 $4.260 $13.000
EXCAVATION (ROADWAY)
CY 2,685.000 $20.000 $75.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 8,007.000 $18.000 $10.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 3,206.000 $25.000 $10.000
EMBANKMENT (FINAL)(DENS CONT)(TY C3)
CY 540.000 $54.340 $10.000
COMPOST MANUF TOPSOIL (4")
SY 24,524.000 $1.480 $0.920
BLOCK SODDING
SY 24,524.000 $4.000 $5.500
DRILL SEED (TEMP)(WARM OR COOL)
SY 24,524.000 $0.120 $0.150
VEGETATIVE WATERING
MG 7,300.000 $3.920 $1.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 2,375.000 $1.170 $2.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 343.000 $48.500 $125.000
LIME (HYD, COM, OR QK(SLURRY))
TON 493.000 $170.000 $220.000
LIME TRT(MIX EXST MATL & NEW BASE)(10")
SY 3,627.000 $3.950 $14.000
LIME TRT (SUBGRADE)(12")
SY 16,905.000 $3.500 $4.500
FLEX PAVEMNT STRUCT REPAIR (O" TO 12")
SY 1,500.000 $100.000 $130.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 3,195.000 $110.000 $100.000
FULL - DEPTH REPAIR CRCP (8")
SY 1,000.000 $300.000 $200.000
FULL - DEPTH REPAIR CPCD (8")
SY 1,000.000 $140.000 $200.000
CEM STABIL BKFL
CY 153.000 $141.630 $175.000
TRENCH EXCAVATION PROTECTION
LF 856.000 $7.910 $1.000
TEMPORARY SPL SHORING
SF 2,140.000 $30.000 $40.000
DRILL SHAFT (18 IN)
LF 160.000 $69.720 $250.000
DRILL SHAFT (36 IN)
LF 1,024.000 $160.000 $500.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 8.000 $201.230 $175.000
DRILL SHAFT (SIGN MTS) (30 IN)
LF 66.000 $341.000 $220.000
DRILL SHAFT (SIGN MTS) (36 IN)
LF 36.000 $400.000 $275.000
DRILL SHAFT (HIGH MAST POLE) (66 IN)
LF 45.000 $576.690 $700.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 168.000 $251.590 $285.000
CL B CONC (FLUME)
CY 15.200 $400.000 $790.000
CL C CONC (ABUT)(HPC)(EXTEND)
CY 49.800 $1,500.000 $1,800.000
CL C CONC (CAP)(HPC)
CY 70.100 $1,500.000 $2,750.000
CL C CONC (CAP)(HPC)(EXTEND)
CY 70.400 $2,000.000 $2,300.000
CL C CONC (COLUMN)(HPC)
CY 39.900 $1,500.000 $2,000.000
CL C CONC (RAIL FOUNDATION)
CY 712.000 $450.000 $450.000
REINF CONC SLAB (EXTEND SLAB)(HPC)
SF 19,856.000 $34.000 $42.500
APPROACH SLAB (EXTEND) (HPC)
CY 70.000 $600.000 $680.000
RETAINING WALL (MSE)
SF 865.000 $62.250 $80.000
RETAINING WALL (CAST - IN - PLACE)
SF 221.000 $150.000 $150.000
PRESTR CONC GIRDER (TX28)
LF 1,024.930 $200.000 $350.000
PRESTR CONC GIRDER (TX34)
LF 442.330 $200.000 $300.000
PRESTR CONC GIRDER (TX54)
LF 759.980 $200.000 $500.000
RIPRAP (CONC)(4 IN)
CY 370.000 $500.000 $575.000
RIPRAP (CONC)(5 IN)
CY 8.000 $1,100.000 $800.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 6.000 $200.000 $300.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 204.000 $123.780 $175.000
RIPRAP (MOW STRIP)(4 IN)
CY 110.000 $500.000 $680.000
CLEANING EXISTING JOINTS
LF 272.000 $24.190 $12.000
RAIL (TY T551)
LF 59.000 $49.900 $165.000
RAIL (TY T552)
LF 605.000 $50.000 $110.000
RAIL (TY SSTR)
LF 3,240.000 $60.000 $75.000
RAIL (TY SSTR)(HPC)
LF 1,202.400 $45.000 $85.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 1,797.000 $75.000 $75.000
RETROFIT RAIL (TY SSTR)(HPC)
LF 294.700 $102.770 $225.000
ARMOR JOINT
LF 260.000 $100.000 $105.000
HEADER TYPE EXPANSION JOINT
LF 272.000 $143.410 $98.000
JOINT SEALANT
LF 272.000 $15.440 $11.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 41.000 $112.180 $105.000
RC PIPE (CL III)(18 IN)
LF 323.000 $129.000 $100.000
RC PIPE (CL III)(24 IN)
LF 485.000 $135.000 $130.000
INLET (COMPL)(PCU)(3FT)(NONE)
EA 1.000 $5,706.060 $4,500.000
INLET (COMPL)(PCU)(3FT)(BOTH)
EA 2.000 $7,000.000 $5,800.000
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
EA 7.000 $7,640.060 $5,000.000
INLET (COMPL)(ARMOR CURB SLOT)
EA 1.000 $3,500.000 $5,800.000
REMOV STR (INLET)
EA 7.000 $603.980 $750.000
REMOV STR (PIPE)
LF 602.000 $16.810 $25.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $95,263.340 $1,200,000.000
REMOV STR (APPROACH SLAB)
EA 5.000 $2,000.000 $1,550.000
MOBILIZATION
LS 1.000 $1,100,000.000 $1,990,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $20,000.000 $156,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 300.000 $30.660 $26.500
ROCK FILTER DAMS (REMOVE)
LF 300.000 $8.390 $9.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 2,132.000 $22.870 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 2,132.000 $6.620 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,519.000 $2.450 $2.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,519.000 $0.590 $0.650
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,771.000 $3.030 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,771.000 $0.740 $0.850
CONSTRUCTING DETOURS (TY 1)
SY 737.000 $90.000 $120.000
CONSTRUCTING DETOURS (TY 2)
SY 2,824.000 $100.000 $120.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 20,010.000 $21.000 $20.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 520.000 $34.190 $45.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $34.720 $45.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 37,620.000 $5.000 $20.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 520.000 $6.850 $7.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $7.450 $7.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 20,010.000 $8.000 $9.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 520.000 $8.400 $9.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $10.140 $9.000
PCTB(FUR & INST)(F-SHP TO LOW PROF)TY T
LF 10.000 $291.310 $175.000
PORT CTB(MOVE)(F-SHAPE)(TY T)
LF 10.000 $7.760 $75.000
PORT CTB(REMOVE)(F-SHAPE)(TY T)
LF 10.000 $1,500.000 $90.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 2,713.000 $55.000 $92.500
PERM CTB (F-SHAPE) (TY 1)
LF 120.000 $49.000 $150.000
CONC CURB (MONO) (TY II)
LF 2,019.000 $2.760 $8.000
CONC CURB & GUTTER (TY I)
LF 155.000 $30.000 $35.000
CONC CURB & GUTTER (TY II)
LF 1,040.000 $31.000 $33.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 3,972.000 $0.160 $1.770
RUMBLE STRIPS (SHOULDER) CONCRETE
LF 935.000 $1.480 $7.250
MTL W-BEAM GD FEN (STEEL POST)
LF 1,275.000 $21.000 $33.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,654.500 $2,260.000
REMOVE METAL BEAM GUARD FENCE
LF 2,117.000 $3.360 $5.250
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,462.990 $3,033.000
GUARDRAIL END TREATMENT (REMOVE)
EA 7.000 $250.000 $472.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 35.000 $2,000.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 20.000 $758.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
EA 1.000 $12,630.000 $22,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 18.000 $8,500.000 $8,000.000
CHAIN LINK FENCE (INSTALL) (6')
LF 27.000 $20.760 $22.560
RELOCATE RD IL ASM (BRIDGE MOUNT)
EA 3.000 $750.000 $600.000
RELOCATE RD IL ASM (TRANS-BASE)
EA 14.000 $2,126.760 $2,500.000
IN RD IL AM (TY SA) 40B-8 (250W) S
EA 1.000 $2,500.000 $5,200.000
REPLACE LUMINAIRE W/LED (400W EQ)
EA 19.000 $566.320 $600.000
IN RD IL (TY SP) 48S-12 (400W EQ) LED
EA 1.000 $3,200.000 $6,400.000
REPLC LED HI MST IL(6 FIXT)(SYM)(TY S)
EA 1.000 $24,000.000 $8,052.000
CONDT (PVC) (SCH 40) (2")
LF 4,430.000 $10.850 $12.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 195.000 $24.420 $25.000
CONDT (PVC) (SCH 40) (3")
LF 495.000 $18.000 $15.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 780.000 $12.190 $28.000
CONDT (RM) (1")
LF 330.000 $19.380 $35.000
CONDT (RM) (2")
LF 40.000 $54.830 $45.000
ELEC CONDR (NO.8) BARE
LF 5,535.000 $1.160 $1.570
ELEC CONDR (NO.8) INSULATED
LF 11,285.000 $1.240 $1.630
ELEC CONDR (NO.6) BARE
LF 1,460.000 $2.000 $1.750
ELEC CONDR (NO.6) INSULATED
LF 900.000 $2.000 $1.880
ELEC CONDR (NO.2) INSULATED
LF 2,920.000 $2.070 $3.850
GROUND BOX TY A (122311)
EA 1.000 $597.890 $1,000.000
GROUND BOX TY A (122311)W/APRON
EA 10.000 $1,066.040 $1,100.000
ALUMINUM SIGNS (TY A)
SF 54.000 $29.490 $31.000
ALUMINUM SIGNS (TY O)
SF 655.000 $39.150 $35.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 1,133.000 $27.450 $35.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 13.000 $519.160 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $702.840 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 1.000 $657.850 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $891.000 $1,075.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $977.070 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,056.750 $1,350.000
IN SM RD SN SUP&AM TYS80(1)SB(U-BM)
EA 3.000 $450.000 $1,800.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 2.000 $1,886.520 $2,500.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 3.000 $2,620.000 $4,800.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 13.000 $275.800 $605.000
RELOCATE SM RD SN SUP&AM(RAIL MOUNT)
EA 1.000 $2,330.000 $9,500.000
RELOCATE LRSA
EA 1.000 $2,996.620 $5,800.000
INS OH SN SUP(75 FT BRDG)
EA 1.000 $55,000.000 $58,000.000
INS OH SN SUP(135 FT COMB)
EA 1.000 $81,000.000 $750,000.000
REMOVE OVERHD SIGN SUP
EA 3.000 $10,000.000 $7,800.000
REMOVE OVERHD SIGN SUP (SIGN ONLY)
EA 6.000 $900.000 $2,600.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 40.000 $25.110 $32.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 51.000 $24.160 $32.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 22.000 $25.000 $95.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
EA 11.000 $25.000 $96.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 8.000 $25.000 $105.000
WK ZN PAV MRK REMOV (REFL) TY II-C-R
EA 240.000 $10.000 $5.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 4,782.000 $1.010 $1.250
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 41,636.000 $1.030 $0.750
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 45.000 $9.110 $15.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 30,195.000 $1.410 $0.750
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 385.000 $2.050 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,534.000 $1.000 $1.500
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 702.000 $2.530 $2.500
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,325.000 $3.160 $4.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 250.000 $6.480 $8.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 17.000 $55.680 $50.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 959.000 $0.920 $1.500
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 173.000 $6.000 $9.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 30,796.000 $0.100 $0.200
REFL PAV MRK TY II (W) 6" (BRK)
LF 10,730.000 $0.250 $0.220
REFL PAV MRK TY II (W) 6" (DOT)
LF 385.000 $1.510 $0.500
REFL PAV MRK TY II (W) 8" (SLD)
LF 7,534.000 $0.320 $0.400
REFL PAV MRK TY II (W) 12" (LNDP)
LF 702.000 $1.500 $1.000
REFL PAV MRK TY II (W) 12" (SLD)
LF 1,325.000 $1.650 $1.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 250.000 $2.790 $3.000
REFL PAV MRK TY II (W) 18" (YLD TRI)
EA 17.000 $55.000 $10.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 22,544.000 $0.100 $0.200
REFL PAV MRK TY II (Y) 8" (SLD)
LF 959.000 $0.350 $0.500
REFL PAV MRK TY II (Y) 24" (SLD)
LF 173.000 $2.500 $3.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 30,796.000 $0.460 $0.750
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 10,730.000 $1.000 $1.250
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 22,544.000 $0.460 $0.750
PREFAB PAV MRK TY C (W) (ARROW)
EA 13.000 $216.290 $225.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $350.000 $325.000
PREFAB PAV MRK TY C (W) (WORD)
EA 14.000 $283.760 $350.500
REFL PAV MRKR TY II-C-R
EA 1,176.000 $3.740 $3.520
ELIM EXT PAV MRK & MRKS (4")
LF 58,947.000 $0.710 $0.750
ELIM EXT PAV MRK & MRKS (8")
LF 6,796.000 $0.970 $1.000
ELIM EXT PAV MRK & MRKS (12")
LF 354.000 $2.210 $2.500
PAV SURF PREP FOR MRK (4")
LF 53,340.000 $0.160 $0.160
PAV SURF PREP FOR MRK (6")
LF 11,115.000 $0.080 $0.160
PAV SURF PREP FOR MRK (8")
LF 8,493.000 $0.150 $0.200
PAV SURF PREP FOR MRK (12")
LF 2,009.000 $0.450 $0.750
PAV SURF PREP FOR MRK (24")
LF 423.000 $0.910 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 13.000 $17.490 $35.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 2.000 $32.280 $55.000
PAV SURF PREP FOR MRK (WORD)
EA 14.000 $31.570 $45.000
PAV SURF PREP FOR MRK (18")(YLD TRI)
EA 17.000 $3.950 $1.000
FULL - WIDTH MOWING
CYC 3.000 $4,068.760 $1,250.000
LITTER REMOVAL
CYC 12.000 $1,955.900 $1,250.000
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
CYC 52.000 $1,500.000 $1,250.000
DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS)
CYC 24.000 $1,980.000 $1,250.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
CYC 12.000 $3,500.000 $1,250.000
CLEANING / SWEEPING(ENTRANCE/EXIT RAMP)
CYC 12.000 $2,400.000 $1,250.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 10.000 $1,500.000 $2,500.000
TREE REMOVAL (12" - 18" DIA)
EA 20.000 $100.000 $550.000
REPAIR (REACT)
EA 18.000 $5,000.000 $1,800.000
BRIDGE JOINT REPAIR (ARMOR)
LF 29.000 $600.000 $550.000
SP MIXES SP-B PG64-22
TON 7,728.000 $113.000 $114.870
SP MIXES SP-C PG70-22
TON 1,564.000 $150.000 $140.660
SP MIXES SP-C SAC-B PG70-22
TON 179.000 $140.000 $137.030
TACK COAT
GAL 2,115.000 $4.400 $7.360
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 1,749.000 $150.000 $207.570
PATCHING MILLED CONCRETE RUMBLE STRIPS
LF 1,736.000 $8.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $11,000.000 $24,000.000
FO SPLICE ENCLOSURE (TYPE 1)
EA 3.000 $2,330.000 $1,900.000
FIBER OPTIC FUSION SPLICE
EA 168.000 $31.250 $80.000
RELOCATE FIBER OPTIC CABLE
LF 1,950.000 $13.940 $5.000
ITS MULTI-DUCT CND (PVC-40)
LF 165.000 $4.200 $30.000
ITS MULTI-DUCT CND (PVC-40)(BORE)
LF 260.000 $10.000 $35.000
CONDUIT (PREPARE)
LF 2,075.000 $3.020 $1.500
GROUND BOX (PREPARE)
EA 5.000 $292.920 $250.000
TMA (STATIONARY)
DAY 63.000 $290.000 $850.000
TMA (MOBILE OPERATION)
HR 670.000 $80.000 $150.000
ITS GND BOX(PCAST) TY 1 (243660)W/APRN
EA 4.000 $3,630.000 $6,000.000
REMOVE ITS GROUND BOX
EA 4.000 $1,180.000 $900.000
RELOCATE HIGH MAST LIGHTING ASSEMBLY
EA 1.000 $12,690.000 $21,000.000
Totals: $11,761,702.579 $19,987,979.010