PREPARING ROW
|
STA
|
112.000
|
$7,000.000
|
$16,900.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
3,020.000
|
$6.330
|
$16.500
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
56.000
|
$9.950
|
$65.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
470.000
|
$2.500
|
$9.500
|
|
|
REMOVING CONC (CTB)
|
LF
|
3,860.000
|
$5.460
|
$35.000
|
|
|
REMOVE CONC (WINGWALL)
|
CY
|
3.000
|
$500.000
|
$430.000
|
|
|
REMOVING CONC (SIDEWALK OR RAMP)
|
SY
|
128.000
|
$15.000
|
$15.000
|
|
|
REMOVING CONC (FLUME)
|
SY
|
46.000
|
$9.140
|
$35.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2")
|
SY
|
2,137.000
|
$2.270
|
$7.500
|
|
|
REMOVING STAB BASE AND ASPH PAV(4"-16")
|
SY
|
10,107.000
|
$4.260
|
$13.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,685.000
|
$20.000
|
$75.000
|
|
|
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
|
CY
|
8,007.000
|
$18.000
|
$10.000
|
|
|
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
|
CY
|
3,206.000
|
$25.000
|
$10.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C3)
|
CY
|
540.000
|
$54.340
|
$10.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
24,524.000
|
$1.480
|
$0.920
|
|
|
BLOCK SODDING
|
SY
|
24,524.000
|
$4.000
|
$5.500
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
24,524.000
|
$0.120
|
$0.150
|
|
|
VEGETATIVE WATERING
|
MG
|
7,300.000
|
$3.920
|
$1.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY F)
|
SY
|
2,375.000
|
$1.170
|
$2.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
343.000
|
$48.500
|
$125.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
493.000
|
$170.000
|
$220.000
|
|
|
LIME TRT(MIX EXST MATL & NEW BASE)(10")
|
SY
|
3,627.000
|
$3.950
|
$14.000
|
|
|
LIME TRT (SUBGRADE)(12")
|
SY
|
16,905.000
|
$3.500
|
$4.500
|
|
|
FLEX PAVEMNT STRUCT REPAIR (O" TO 12")
|
SY
|
1,500.000
|
$100.000
|
$130.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
3,195.000
|
$110.000
|
$100.000
|
|
|
FULL - DEPTH REPAIR CRCP (8")
|
SY
|
1,000.000
|
$300.000
|
$200.000
|
|
|
FULL - DEPTH REPAIR CPCD (8")
|
SY
|
1,000.000
|
$140.000
|
$200.000
|
|
|
CEM STABIL BKFL
|
CY
|
153.000
|
$141.630
|
$175.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
856.000
|
$7.910
|
$1.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,140.000
|
$30.000
|
$40.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
160.000
|
$69.720
|
$250.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,024.000
|
$160.000
|
$500.000
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
8.000
|
$201.230
|
$175.000
|
|
|
DRILL SHAFT (SIGN MTS) (30 IN)
|
LF
|
66.000
|
$341.000
|
$220.000
|
|
|
DRILL SHAFT (SIGN MTS) (36 IN)
|
LF
|
36.000
|
$400.000
|
$275.000
|
|
|
DRILL SHAFT (HIGH MAST POLE) (66 IN)
|
LF
|
45.000
|
$576.690
|
$700.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
168.000
|
$251.590
|
$285.000
|
|
|
CL B CONC (FLUME)
|
CY
|
15.200
|
$400.000
|
$790.000
|
|
|
CL C CONC (ABUT)(HPC)(EXTEND)
|
CY
|
49.800
|
$1,500.000
|
$1,800.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
70.100
|
$1,500.000
|
$2,750.000
|
|
|
CL C CONC (CAP)(HPC)(EXTEND)
|
CY
|
70.400
|
$2,000.000
|
$2,300.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
39.900
|
$1,500.000
|
$2,000.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
712.000
|
$450.000
|
$450.000
|
|
|
REINF CONC SLAB (EXTEND SLAB)(HPC)
|
SF
|
19,856.000
|
$34.000
|
$42.500
|
|
|
APPROACH SLAB (EXTEND) (HPC)
|
CY
|
70.000
|
$600.000
|
$680.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
865.000
|
$62.250
|
$80.000
|
|
|
RETAINING WALL (CAST - IN - PLACE)
|
SF
|
221.000
|
$150.000
|
$150.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
1,024.930
|
$200.000
|
$350.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
442.330
|
$200.000
|
$300.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
759.980
|
$200.000
|
$500.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
370.000
|
$500.000
|
$575.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
8.000
|
$1,100.000
|
$800.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(6 IN)
|
CY
|
6.000
|
$200.000
|
$300.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
204.000
|
$123.780
|
$175.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
110.000
|
$500.000
|
$680.000
|
|
|
CLEANING EXISTING JOINTS
|
LF
|
272.000
|
$24.190
|
$12.000
|
|
|
RAIL (TY T551)
|
LF
|
59.000
|
$49.900
|
$165.000
|
|
|
RAIL (TY T552)
|
LF
|
605.000
|
$50.000
|
$110.000
|
|
|
RAIL (TY SSTR)
|
LF
|
3,240.000
|
$60.000
|
$75.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
1,202.400
|
$45.000
|
$85.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
1,797.000
|
$75.000
|
$75.000
|
|
|
RETROFIT RAIL (TY SSTR)(HPC)
|
LF
|
294.700
|
$102.770
|
$225.000
|
|
|
ARMOR JOINT
|
LF
|
260.000
|
$100.000
|
$105.000
|
|
|
HEADER TYPE EXPANSION JOINT
|
LF
|
272.000
|
$143.410
|
$98.000
|
|
|
JOINT SEALANT
|
LF
|
272.000
|
$15.440
|
$11.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
41.000
|
$112.180
|
$105.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
323.000
|
$129.000
|
$100.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
485.000
|
$135.000
|
$130.000
|
|
|
INLET (COMPL)(PCU)(3FT)(NONE)
|
EA
|
1.000
|
$5,706.060
|
$4,500.000
|
|
|
INLET (COMPL)(PCU)(3FT)(BOTH)
|
EA
|
2.000
|
$7,000.000
|
$5,800.000
|
|
|
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
|
EA
|
7.000
|
$7,640.060
|
$5,000.000
|
|
|
INLET (COMPL)(ARMOR CURB SLOT)
|
EA
|
1.000
|
$3,500.000
|
$5,800.000
|
|
|
REMOV STR (INLET)
|
EA
|
7.000
|
$603.980
|
$750.000
|
|
|
REMOV STR (PIPE)
|
LF
|
602.000
|
$16.810
|
$25.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$95,263.340
|
$1,200,000.000
|
|
|
REMOV STR (APPROACH SLAB)
|
EA
|
5.000
|
$2,000.000
|
$1,550.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,100,000.000
|
$1,990,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$20,000.000
|
$156,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
300.000
|
$30.660
|
$26.500
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
300.000
|
$8.390
|
$9.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
2,132.000
|
$22.870
|
$25.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
2,132.000
|
$6.620
|
$9.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
10,519.000
|
$2.450
|
$2.850
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
10,519.000
|
$0.590
|
$0.650
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,771.000
|
$3.030
|
$3.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,771.000
|
$0.740
|
$0.850
|
|
|
CONSTRUCTING DETOURS (TY 1)
|
SY
|
737.000
|
$90.000
|
$120.000
|
|
|
CONSTRUCTING DETOURS (TY 2)
|
SY
|
2,824.000
|
$100.000
|
$120.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
20,010.000
|
$21.000
|
$20.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$34.190
|
$45.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$34.720
|
$45.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
37,620.000
|
$5.000
|
$20.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$6.850
|
$7.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$7.450
|
$7.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
20,010.000
|
$8.000
|
$9.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$8.400
|
$9.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$10.140
|
$9.000
|
|
|
PCTB(FUR & INST)(F-SHP TO LOW PROF)TY T
|
LF
|
10.000
|
$291.310
|
$175.000
|
|
|
PORT CTB(MOVE)(F-SHAPE)(TY T)
|
LF
|
10.000
|
$7.760
|
$75.000
|
|
|
PORT CTB(REMOVE)(F-SHAPE)(TY T)
|
LF
|
10.000
|
$1,500.000
|
$90.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
2,713.000
|
$55.000
|
$92.500
|
|
|
PERM CTB (F-SHAPE) (TY 1)
|
LF
|
120.000
|
$49.000
|
$150.000
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
2,019.000
|
$2.760
|
$8.000
|
|
|
CONC CURB & GUTTER (TY I)
|
LF
|
155.000
|
$30.000
|
$35.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
1,040.000
|
$31.000
|
$33.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
3,972.000
|
$0.160
|
$1.770
|
|
|
RUMBLE STRIPS (SHOULDER) CONCRETE
|
LF
|
935.000
|
$1.480
|
$7.250
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,275.000
|
$21.000
|
$33.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
10.000
|
$1,654.500
|
$2,260.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,117.000
|
$3.360
|
$5.250
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,462.990
|
$3,033.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
7.000
|
$250.000
|
$472.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
35.000
|
$2,000.000
|
$3,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
20.000
|
$758.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
|
EA
|
1.000
|
$12,630.000
|
$22,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
18.000
|
$8,500.000
|
$8,000.000
|
|
|
CHAIN LINK FENCE (INSTALL) (6')
|
LF
|
27.000
|
$20.760
|
$22.560
|
|
|
RELOCATE RD IL ASM (BRIDGE MOUNT)
|
EA
|
3.000
|
$750.000
|
$600.000
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
14.000
|
$2,126.760
|
$2,500.000
|
|
|
IN RD IL AM (TY SA) 40B-8 (250W) S
|
EA
|
1.000
|
$2,500.000
|
$5,200.000
|
|
|
REPLACE LUMINAIRE W/LED (400W EQ)
|
EA
|
19.000
|
$566.320
|
$600.000
|
|
|
IN RD IL (TY SP) 48S-12 (400W EQ) LED
|
EA
|
1.000
|
$3,200.000
|
$6,400.000
|
|
|
REPLC LED HI MST IL(6 FIXT)(SYM)(TY S)
|
EA
|
1.000
|
$24,000.000
|
$8,052.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
4,430.000
|
$10.850
|
$12.000
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
195.000
|
$24.420
|
$25.000
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
495.000
|
$18.000
|
$15.000
|
|
|
CONDT (PVC) (SCH 40) (3") (BORE)
|
LF
|
780.000
|
$12.190
|
$28.000
|
|
|
CONDT (RM) (1")
|
LF
|
330.000
|
$19.380
|
$35.000
|
|
|
CONDT (RM) (2")
|
LF
|
40.000
|
$54.830
|
$45.000
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
5,535.000
|
$1.160
|
$1.570
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
11,285.000
|
$1.240
|
$1.630
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
1,460.000
|
$2.000
|
$1.750
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
900.000
|
$2.000
|
$1.880
|
|
|
ELEC CONDR (NO.2) INSULATED
|
LF
|
2,920.000
|
$2.070
|
$3.850
|
|
|
GROUND BOX TY A (122311)
|
EA
|
1.000
|
$597.890
|
$1,000.000
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
10.000
|
$1,066.040
|
$1,100.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
54.000
|
$29.490
|
$31.000
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
655.000
|
$39.150
|
$35.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY O)
|
SF
|
1,133.000
|
$27.450
|
$35.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
13.000
|
$519.160
|
$750.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
3.000
|
$702.840
|
$800.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
|
EA
|
1.000
|
$657.850
|
$850.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$891.000
|
$1,075.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$977.070
|
$1,150.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
|
EA
|
1.000
|
$1,056.750
|
$1,350.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(U-BM)
|
EA
|
3.000
|
$450.000
|
$1,800.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
2.000
|
$1,886.520
|
$2,500.000
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
3.000
|
$2,620.000
|
$4,800.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
13.000
|
$275.800
|
$605.000
|
|
|
RELOCATE SM RD SN SUP&AM(RAIL MOUNT)
|
EA
|
1.000
|
$2,330.000
|
$9,500.000
|
|
|
RELOCATE LRSA
|
EA
|
1.000
|
$2,996.620
|
$5,800.000
|
|
|
INS OH SN SUP(75 FT BRDG)
|
EA
|
1.000
|
$55,000.000
|
$58,000.000
|
|
|
INS OH SN SUP(135 FT COMB)
|
EA
|
1.000
|
$81,000.000
|
$750,000.000
|
|
|
REMOVE OVERHD SIGN SUP
|
EA
|
3.000
|
$10,000.000
|
$7,800.000
|
|
|
REMOVE OVERHD SIGN SUP (SIGN ONLY)
|
EA
|
6.000
|
$900.000
|
$2,600.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
40.000
|
$25.110
|
$32.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
51.000
|
$24.160
|
$32.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
22.000
|
$25.000
|
$95.000
|
|
|
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
|
EA
|
11.000
|
$25.000
|
$96.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
8.000
|
$25.000
|
$105.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-C-R
|
EA
|
240.000
|
$10.000
|
$5.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
4,782.000
|
$1.010
|
$1.250
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
41,636.000
|
$1.030
|
$0.750
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
45.000
|
$9.110
|
$15.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
30,195.000
|
$1.410
|
$0.750
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
385.000
|
$2.050
|
$1.250
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
7,534.000
|
$1.000
|
$1.500
|
|
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
|
LF
|
702.000
|
$2.530
|
$2.500
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
1,325.000
|
$3.160
|
$4.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
250.000
|
$6.480
|
$8.000
|
|
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
|
EA
|
17.000
|
$55.680
|
$50.000
|
|
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
|
LF
|
959.000
|
$0.920
|
$1.500
|
|
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
|
LF
|
173.000
|
$6.000
|
$9.000
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
30,796.000
|
$0.100
|
$0.200
|
|
REFL PAV MRK TY II (W) 6" (BRK)
|
LF
|
10,730.000
|
$0.250
|
$0.220
|
|
REFL PAV MRK TY II (W) 6" (DOT)
|
LF
|
385.000
|
$1.510
|
$0.500
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
7,534.000
|
$0.320
|
$0.400
|
|
REFL PAV MRK TY II (W) 12" (LNDP)
|
LF
|
702.000
|
$1.500
|
$1.000
|
|
REFL PAV MRK TY II (W) 12" (SLD)
|
LF
|
1,325.000
|
$1.650
|
$1.000
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
250.000
|
$2.790
|
$3.000
|
|
REFL PAV MRK TY II (W) 18" (YLD TRI)
|
EA
|
17.000
|
$55.000
|
$10.000
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
22,544.000
|
$0.100
|
$0.200
|
|
REFL PAV MRK TY II (Y) 8" (SLD)
|
LF
|
959.000
|
$0.350
|
$0.500
|
|
REFL PAV MRK TY II (Y) 24" (SLD)
|
LF
|
173.000
|
$2.500
|
$3.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
30,796.000
|
$0.460
|
$0.750
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
10,730.000
|
$1.000
|
$1.250
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
22,544.000
|
$0.460
|
$0.750
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
13.000
|
$216.290
|
$225.000
|
|
PREFAB PAV MRK TY C (W) (DBL ARROW)
|
EA
|
2.000
|
$350.000
|
$325.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
14.000
|
$283.760
|
$350.500
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,176.000
|
$3.740
|
$3.520
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
58,947.000
|
$0.710
|
$0.750
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
6,796.000
|
$0.970
|
$1.000
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
354.000
|
$2.210
|
$2.500
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
53,340.000
|
$0.160
|
$0.160
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
11,115.000
|
$0.080
|
$0.160
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
8,493.000
|
$0.150
|
$0.200
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
2,009.000
|
$0.450
|
$0.750
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
423.000
|
$0.910
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
13.000
|
$17.490
|
$35.000
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
2.000
|
$32.280
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
14.000
|
$31.570
|
$45.000
|
|
|
PAV SURF PREP FOR MRK (18")(YLD TRI)
|
EA
|
17.000
|
$3.950
|
$1.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$4,068.760
|
$1,250.000
|
|
|
LITTER REMOVAL
|
CYC
|
12.000
|
$1,955.900
|
$1,250.000
|
|
|
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
|
CYC
|
52.000
|
$1,500.000
|
$1,250.000
|
|
|
DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS)
|
CYC
|
24.000
|
$1,980.000
|
$1,250.000
|
|
|
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
|
CYC
|
12.000
|
$3,500.000
|
$1,250.000
|
|
|
CLEANING / SWEEPING(ENTRANCE/EXIT RAMP)
|
CYC
|
12.000
|
$2,400.000
|
$1,250.000
|
|
|
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
|
AC
|
10.000
|
$1,500.000
|
$2,500.000
|
|
|
TREE REMOVAL (12" - 18" DIA)
|
EA
|
20.000
|
$100.000
|
$550.000
|
|
|
REPAIR (REACT)
|
EA
|
18.000
|
$5,000.000
|
$1,800.000
|
|
|
BRIDGE JOINT REPAIR (ARMOR)
|
LF
|
29.000
|
$600.000
|
$550.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
7,728.000
|
$113.000
|
$114.870
|
|
|
SP MIXES SP-C PG70-22
|
TON
|
1,564.000
|
$150.000
|
$140.660
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
179.000
|
$140.000
|
$137.030
|
|
|
TACK COAT
|
GAL
|
2,115.000
|
$4.400
|
$7.360
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
1,749.000
|
$150.000
|
$207.570
|
|
|
PATCHING MILLED CONCRETE RUMBLE STRIPS
|
LF
|
1,736.000
|
$8.000
|
$10.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
8.000
|
$11,000.000
|
$24,000.000
|
|
|
FO SPLICE ENCLOSURE (TYPE 1)
|
EA
|
3.000
|
$2,330.000
|
$1,900.000
|
|
|
FIBER OPTIC FUSION SPLICE
|
EA
|
168.000
|
$31.250
|
$80.000
|
|
|
RELOCATE FIBER OPTIC CABLE
|
LF
|
1,950.000
|
$13.940
|
$5.000
|
|
|
ITS MULTI-DUCT CND (PVC-40)
|
LF
|
165.000
|
$4.200
|
$30.000
|
|
|
ITS MULTI-DUCT CND (PVC-40)(BORE)
|
LF
|
260.000
|
$10.000
|
$35.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
2,075.000
|
$3.020
|
$1.500
|
|
|
GROUND BOX (PREPARE)
|
EA
|
5.000
|
$292.920
|
$250.000
|
|
|
TMA (STATIONARY)
|
DAY
|
63.000
|
$290.000
|
$850.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
670.000
|
$80.000
|
$150.000
|
|
|
ITS GND BOX(PCAST) TY 1 (243660)W/APRN
|
EA
|
4.000
|
$3,630.000
|
$6,000.000
|
|
|
REMOVE ITS GROUND BOX
|
EA
|
4.000
|
$1,180.000
|
$900.000
|
|
|
RELOCATE HIGH MAST LIGHTING ASSEMBLY
|
EA
|
1.000
|
$12,690.000
|
$21,000.000
|
|
Totals: |
$11,761,702.579
|
$19,987,979.010
|