DENTON US 380 (0134-09-069)
Items: 75
County: DENTON
Length: 7.8600 MILES
Highway: US 380
District: DALLAS
Control Number: 0134-09-069
DBE Goal: 0.0%
Project: C 134-9-69
Guaranty: $100,000.00
Time: 170 WORKING DAYS
Engineer's Estimate: $9,565,920.77
Date: 07/01/2025 (11 months ago)
Contract Number: 7253004
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00196911
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AMANDA MILLER
CHRISTOPHER ROCHA
DENTON US 380 (0134-09-069)
Project Name: N/A
Project: C 134-9-69
Length: 7.8600 MILES
Project Type: CONSTRUCTION
Limits From: WISE COUNTY LINE
Limits To: WEST OF FM 156
Project Description: OVERLAY
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$9,565,920.77 | |||
| $7,632,633.60 |
-20.21%
-$1,933,287.17
|
|||
| $8,391,095.25 |
-12.28%
-$1,174,825.52
|
9.94%
$758,461.65
|
||
| $8,462,089.83 |
-11.54%
-$1,103,830.94
|
10.87%
$829,456.23
|
-0.85%
-$70,994.58
|
|
| $8,904,456.81 |
-6.91%
-$661,463.96
|
16.66%
$1,271,823.21
|
-5.23%
-$442,366.98
|
|
| $9,652,310.64 |
0.9%
$86,389.87
|
26.46%
$2,019,677.04
|
-8.40%
-$747,853.83
|
|
| $9,969,784.66 |
4.22%
$403,863.89
|
30.62%
$2,337,151.06
|
-3.29%
-$317,474.02
|
|
| $12,470,835.70 |
30.37%
$2,904,914.93
|
63.39%
$4,838,202.10
|
-25.09%
-$2,501,051.04
|
E
Engineer's Estimate
$9,565,920.77
1
Awarded
$7,632,633.60
Over/Under Est:
-20.21%
-$1,933,287.17
$8,391,095.25
Over/Under Est:
-12.28%
-$1,174,825.52
Amt Left:
9.94%
$758,461.65
$8,462,089.83
Over/Under Est:
-11.54%
-$1,103,830.94
Amt Left:
10.87%
$829,456.23
Delta:
-0.85%
-$70,994.58
$8,904,456.81
Over/Under Est:
-6.91%
-$661,463.96
Amt Left:
16.66%
$1,271,823.21
Delta:
-5.23%
-$442,366.98
$9,652,310.64
Over/Under Est:
0.9%
$86,389.87
Amt Left:
26.46%
$2,019,677.04
Delta:
-8.40%
-$747,853.83
$9,969,784.66
Over/Under Est:
4.22%
$403,863.89
Amt Left:
30.62%
$2,337,151.06
Delta:
-3.29%
-$317,474.02
$12,470,835.70
Over/Under Est:
30.37%
$2,904,914.93
Amt Left:
63.39%
$4,838,202.10
Delta:
-25.09%
-$2,501,051.04
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRAFFIC HIGHWAY MAINTENANCE, LLC | 2.40% | $187,363.89 |
| STRIPE-A-ZONE, LLC | 2.40% | $187,363.89 |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 1.91% | $149,110.43 |
| MARCOMS CONSTRUCTION LLC | 1.46% | $113,979.70 |
| SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. | 0.90% | $70,261.46 |
| ACT SAW CUTTING & REMOVAL | 0.75% | $58,551.22 |
| DUSTROL, INC. | 0.70% | $54,647.80 |
| FC TRAFFIC CONTROL, INC. | 0.33% | $25,762.54 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.18% | $14,052.29 |
| Total: | 11.03% | $861,093.22 |
Bid Items & Bid Tabulations
75
Total
0 of 75
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $50,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $50,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $50,000.00 |
| Total: | $150,000.00 |