Show Job Controls
Bid Cobra

DEAF SMITH FM 1259 (1243-02-031)

Items: 64

County: DEAF SMITH
Length: N/A
Highway: FM 1259
District: AMARILLO
Control Number: 1243-02-031
DBE Goal: N/A
Project: BR 2023(820)
Guaranty: N/A
Time: 145 WORKING DAYS
Engineer's Estimate: $4,749,688.80
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JOE CHAPPELL
CC SYSOMBATH
KENNETH PETR
LADENIA JEWITT
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$4,749,688.80
$5,827,413.20
Over/Under Est: 22.69% $1,077,724.40
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 5.82% $343,870.34
ALAMO BROTHERS CONCRETE INC 4.87% $287,740.30
TORO BRAVO CONSTRUCTION, LLC 0.37% $21,861.17
HJC FARMS, INC. 0.34% $20,088.65
TRP CONSTRUCTION GROUP, LLC 0.30% $17,725.28
PRIMATE CONSTRUCTION, LP 0.20% $11,816.85
FC TRAFFIC CONTROL, INC. 0.16% $9,453.48
Total: 12.06% $712,556.07

Bid Items & Bid Tabulations

64 Total 0 of 64
DEAF SMITH  |  FM 1259  |  AMARILLO  |  1243-02-031  |  06/01/2023  |  $4,749,688.80  |  BR 2023(820)  |  BRIDGE REPL  |  145 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 31.000 $200.000 $200.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 68.000 $1,000.000 $1,100.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 8.000 $2,500.000 $2,400.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 3.000 $4,000.000 $4,850.000
REMOVING CONC (RIPRAP)
SY 20.000 $50.000 $92.000
REMOVING CONC (SIDEWALKS)
SY 150.000 $30.000 $53.000
REMOVING CONC (CURB AND GUTTER)
LF 924.000 $20.000 $14.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 13.000 $18.000 $290.000
REMOVING STAB BASE & ASPH PAV (12")
SY 540.000 $20.000 $27.500
EXCAVATION (ROADWAY)
CY 1,626.000 $25.000 $39.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 402.000 $35.000 $56.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 697.000 $55.000 $115.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 402.000 $2.500 $14.000
FL BS(CMP IN PLC)(TY A,B OR D GR4)(12")
SY 148.000 $100.000 $97.000
PRIME COAT (MC-30)
GAL 38.000 $10.000 $40.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,245.000 $15.000 $11.000
PLANE ASPH CONC PAV(2" TO 4")
SY 1,424.000 $15.000 $11.000
DRILL SHAFT (18 IN)
LF 180.000 $179.000 $146.000
DRILL SHAFT (36 IN)
LF 1,519.000 $325.000 $340.000
CL C CONC (ABUT)(HPC)
CY 111.400 $2,200.000 $1,900.000
CL C CONC (CAP)(HPC)
CY 74.700 $1,800.000 $2,700.000
CL C CONC (COLUMN)(HPC)
CY 39.300 $1,800.000 $2,700.000
REINF CONC SLAB (HPC)
SF 19,579.000 $42.000 $44.000
BRIDGE SIDEWALK (HPC)
SF 6,554.000 $20.200 $21.000
APPROACH SLAB (HPC)
CY 134.800 $1,500.000 $1,100.000
INTEGRAL ABUT BKWL (HPC)
CY 24.200 $2,300.000 $3,600.000
PRESTR CONC GIRDER (TX34)
LF 2,630.000 $275.000 $325.000
RIPRAP (CONC)(5 IN)
CY 344.000 $650.000 $595.000
STR STEEL (MISC NON - BRIDGE)
LB 602.000 $20.000 $60.000
RAIL (TY C221)(HPC)
LF 546.200 $190.000 $310.000
RC PIPE (CL III)(24 IN)
LF 23.000 $200.000 $385.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 1.000 $7,000.000 $7,100.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $2,000.000 $5,200.000
GRATE & FRAME
EA 11.000 $3,400.000 $1,500.000
ADJUSTING INLETS
EA 1.000 $8,500.000 $10,500.000
REMOV STR (PIPE)
LF 24.000 $30.000 $125.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $200,000.000 $450,000.000
REMOVE STR (CONC)
EA 2.000 $5,000.000 $8,800.000
REMOV STR (TIMBER PILING)
EA 16.000 $100.000 $380.000
REMOV STR (WOOD FENCE & POSTS)
LF 120.000 $10.000 $25.000
MOBILIZATION
LS 1.000 $425,000.000 $580,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $15,000.000 $44,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 160.000 $5.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 160.000 $3.000 $4.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 400.000 $10.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 400.000 $3.000 $6.000
CONC CURB & GUTTER (TY II)
LF 804.000 $40.000 $32.500
DRIVEWAYS (CONC)
SY 56.000 $200.000 $170.000
CONC SIDEWALKS (5")
SY 1,098.000 $105.000 $75.000
CURB RAMPS (TY 10)
EA 4.000 $2,300.000 $1,665.000
MTL W-BEAM GD FEN (STEEL POST)
LF 50.000 $40.000 $42.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,800.000 $3,950.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,500.000 $3,980.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $50.000 $22.250
PAVEMENT SEALER 6"
LF 819.000 $2.000 $7.800
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 350.000 $2.000 $7.800
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 1,400.000 $2.000 $7.800
SP MIXES SP-D SAC-A PG70-28
TON 670.000 $210.000 $270.000
TACK COAT
GAL 748.000 $10.000 $9.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $920.000
GEOGRID BASE REINFORCEMENT (TY I)
SY 4,060.000 $5.000 $18.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $16,500.000 $14,000.000
TMA (STATIONARY)
DAY 20.000 $300.000 $560.000
TMA (MOBILE OPERATION)
HR 16.000 $120.000 $110.000
Totals: $4,749,688.800 $5,827,413.200