STONE-MTRX-ASPH SMA-C SAC-A PG76-22
|
TON
|
200.000
|
$125.000
|
$85.000
|
$150.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(14")
|
SY
|
150.000
|
$190.000
|
$85.000
|
$100.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 4")
|
SY
|
7,040.000
|
$5.000
|
$1.000
|
$7.000
|
|
|
FULL - DEPTH REPAIR CRCP (14")
|
SY
|
150.000
|
$325.000
|
$210.000
|
$300.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
600.000
|
$180.000
|
$175.000
|
$130.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
150.000
|
$200.000
|
$63.000
|
$100.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
555.000
|
$13.500
|
$5.000
|
$20.000
|
|
|
CLEANING EXISTING JOINTS
|
LF
|
1,500.000
|
$4.000
|
$10.000
|
$15.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$300,000.000
|
$350,000.000
|
$400,000.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
225.000
|
$70.000
|
$140.000
|
$90.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
113.000
|
$20.000
|
$20.000
|
$30.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
225.000
|
$40.000
|
$9.000
|
$50.000
|
|
|
PORT CTB (ALIGNING)
|
LF
|
675.000
|
$20.000
|
$25.000
|
$20.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
1,000.000
|
$0.500
|
$2.000
|
$5.000
|
|
|
RUMBLE STRIPS (SHOULDER) CONCRETE
|
LF
|
1,000.000
|
$2.000
|
$2.000
|
$5.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
150.000
|
$30.000
|
$19.000
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$1,600.000
|
$1,000.000
|
$1,500.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$5,000.000
|
$2,250.000
|
$4,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$180.000
|
$150.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
16.000
|
$5,000.000
|
$1,000.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
16.000
|
$15,000.000
|
$23,000.000
|
$17,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(R)(N)(TL2)
|
EA
|
2.000
|
$17,000.000
|
$1,000.000
|
$10,000.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY A)
|
SF
|
75.000
|
$25.000
|
$26.000
|
$30.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY O)
|
SF
|
188.000
|
$40.000
|
$30.000
|
$30.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
|
EA
|
4.000
|
$700.000
|
$550.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(T)
|
EA
|
2.000
|
$1,000.000
|
$800.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)UA(P)
|
EA
|
2.000
|
$600.000
|
$400.000
|
$700.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
2.000
|
$3,000.000
|
$750.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
29.000
|
$400.000
|
$390.000
|
$1,000.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
750.000
|
$6.000
|
$12.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
50.000
|
$24.000
|
$16.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
50.000
|
$20.000
|
$16.000
|
$30.000
|
|
REFL PAV MRK TY I (W)12"(SLD)(060MIL)
|
LF
|
2,250.000
|
$3.090
|
$3.780
|
$5.000
|
|
REFL PAV MRK TY I (W)(WORD)(090MIL)
|
EA
|
15.000
|
$150.000
|
$265.000
|
$100.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
|
EA
|
15.000
|
$640.000
|
$730.000
|
$500.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
|
EA
|
15.000
|
$800.000
|
$835.000
|
$750.000
|
|
RE PV MRK TY I(BLACK)6"(SHADOW)(090MIL)
|
LF
|
24,670.000
|
$0.500
|
$0.800
|
$1.500
|
|
|
PAVEMENT SEALER 4"
|
LF
|
5,625.000
|
$0.460
|
$0.130
|
$0.500
|
|
|
PAVEMENT SEALER 6"
|
LF
|
22,500.000
|
$0.460
|
$0.190
|
$0.500
|
|
|
PAVEMENT SEALER 12"
|
LF
|
2,250.000
|
$2.000
|
$0.480
|
$1.000
|
|
|
PAVEMENT SEALER (ENTR GORE)
|
EA
|
11.000
|
$250.000
|
$265.000
|
$200.000
|
|
|
PAVEMENT SEALER (EXIT GORE)
|
EA
|
11.000
|
$350.000
|
$370.000
|
$250.000
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
|
LF
|
26,100.000
|
$0.650
|
$0.650
|
$0.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
|
LF
|
150,000.000
|
$0.400
|
$0.270
|
$0.250
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(060MIL)
|
LF
|
16,875.000
|
$0.600
|
$0.550
|
$0.500
|
|
REFL PAV MRK TY I (W)12"(DOT)(060MIL)
|
LF
|
2,250.000
|
$2.500
|
$3.250
|
$3.000
|
|
REFL PAV MRKR TY I-R
|
EA
|
158.000
|
$10.300
|
$16.000
|
$5.000
|
|
REFL PAV MRKR TY II-C-C
|
EA
|
1,950.000
|
$5.150
|
$6.500
|
$3.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
15,000.000
|
$0.460
|
$0.750
|
$0.500
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
16,875.000
|
$0.520
|
$0.580
|
$0.500
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
2,250.000
|
$1.240
|
$1.050
|
$1.000
|
|
|
ELIM EXT PAV MRK & MRKS (ENTR GORE)
|
EA
|
16.000
|
$350.000
|
$400.000
|
$300.000
|
|
|
ELIM EXT PAV MRK & MRKS (EXIT GORE)
|
EA
|
16.000
|
$550.000
|
$500.000
|
$500.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
5,625.000
|
$0.700
|
$0.120
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
16,875.000
|
$0.700
|
$0.170
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
2,250.000
|
$1.390
|
$0.480
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (ENTR GORE)
|
EA
|
11.000
|
$150.000
|
$130.000
|
$200.000
|
|
|
PAV SURF PREP FOR MRK (EXIT GORE)
|
EA
|
11.000
|
$250.000
|
$210.000
|
$300.000
|
|
|
POTHOLE REPAIR (STANDARD)
|
SY
|
75.000
|
$105.000
|
$72.000
|
$100.000
|
|
|
POTHOLE REPAIR (SAW - CUT)
|
SY
|
250.000
|
$80.000
|
$60.000
|
$100.000
|
|
|
JT / CRCK SEAL (HOT - POURED RUBBER)
|
LF
|
1,500.000
|
$4.000
|
$6.000
|
$5.000
|
|
|
CRACK CLEANING AND SEALING (JCP)
|
LF
|
750.000
|
$8.000
|
$5.000
|
$10.000
|
|
|
SPALLING REPAIR (HYDRAULIC CEMENT)
|
CF
|
150.000
|
$250.000
|
$50.000
|
$100.000
|
|
|
SPALLING REPAIR (POLYMERIC) (FLEXIBLE)
|
GAL
|
1,500.000
|
$55.000
|
$30.000
|
$50.000
|
|
|
FIBER REINFORCED POLYMER PATCHING MATLS
|
LB
|
500.000
|
$8.000
|
$2.000
|
$10.000
|
|
|
PAVEMENT EDGES, STRUCTURES & FIXTURES
|
MI
|
60.000
|
$275.000
|
$200.000
|
$100.000
|
|
|
GRAFFITI REMOVAL (PAINTING)
|
SF
|
150.000
|
$5.000
|
$7.500
|
$10.000
|
|
|
REPAIR RAIL ELEMENT (W - BEAM)
|
LF
|
375.000
|
$50.000
|
$9.000
|
$20.000
|
|
|
REPAIR RAIL ELEMENT (THRIE - BEAM)
|
LF
|
75.000
|
$35.000
|
$12.000
|
$20.000
|
|
|
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
|
LF
|
18.000
|
$25.000
|
$17.000
|
$150.000
|
|
|
REALIGN EXISTING RAIL
|
LF
|
375.000
|
$10.000
|
$4.000
|
$5.000
|
|
|
REM / REPL TIMBER/STL POST W/O CONC FND
|
EA
|
450.000
|
$55.000
|
$25.000
|
$40.000
|
|
|
REM / REPL TIMBER / STL POST W/CONC FND
|
EA
|
30.000
|
$40.000
|
$40.000
|
$55.000
|
|
|
REPAIR STEEL POST WITH BASE PLATE
|
EA
|
19.000
|
$130.000
|
$50.000
|
$200.000
|
|
|
REALIGN POSTS
|
EA
|
19.000
|
$25.000
|
$5.000
|
$200.000
|
|
|
REMOVE & REPLACE BLOCKOUT
|
EA
|
188.000
|
$20.000
|
$12.000
|
$20.000
|
|
|
REPLACE SINGLE GDRAIL TERMINAL RAIL
|
LF
|
2,775.000
|
$25.000
|
$15.000
|
$20.000
|
|
|
REPLACE SINGLE GDRAIL TERMINAL POST
|
EA
|
278.000
|
$55.000
|
$40.000
|
$40.000
|
|
|
REPLACE TERMINAL ANCHOR POSTS
|
EA
|
1.000
|
$40.000
|
$45.000
|
$1,000.000
|
|
|
REMOVE GDRAIL END TRT / REPL WITH SGT
|
EA
|
3.000
|
$3,100.000
|
$1,750.000
|
$2,000.000
|
|
|
REPL SINGLE GDRAIL TERM IMPACT HEAD
|
EA
|
8.000
|
$1,250.000
|
$1,000.000
|
$1,500.000
|
|
|
REM & RESET SGT IMPACT HEAD
|
EA
|
30.000
|
$110.000
|
$150.000
|
$500.000
|
|
|
REPLACE SGT CABLE ASSEMBLY
|
EA
|
62.000
|
$45.000
|
$70.000
|
$100.000
|
|
|
REPLACE SGT CABLE ANCHOR
|
EA
|
31.000
|
$40.000
|
$68.000
|
$100.000
|
|
|
REPLACE SGT STRUT
|
EA
|
38.000
|
$38.000
|
$57.000
|
$100.000
|
|
|
REPLACE SGT OBJECT MARKER
|
EA
|
11.000
|
$30.000
|
$20.000
|
$150.000
|
|
|
REPAIR SINGLE GUARDRAIL TERMINAL
|
EA
|
7.500
|
$1,000.000
|
$500.000
|
$500.000
|
|
|
REMOVE AND REPLACE (SMTC) (N)
|
EA
|
15.000
|
$25,000.000
|
$23,000.000
|
$17,500.000
|
|
|
REMOVE AND REPLACE (SMTC) (W)
|
EA
|
4.000
|
$29,700.000
|
$5,000.000
|
$15,000.000
|
|
|
REPAIR (SMTC) (N)
|
LF
|
2,322.000
|
$200.000
|
$125.000
|
$100.000
|
|
|
REACT DECAL
|
EA
|
38.000
|
$425.000
|
$1.000
|
$400.000
|
|
|
REACT CABLE 350 (9 BAY)
|
EA
|
8.000
|
$1,600.000
|
$1.000
|
$1,000.000
|
|
|
CABLE RELEASE POST
|
EA
|
8.000
|
$650.000
|
$1.000
|
$750.000
|
|
|
ANCHOR POST
|
EA
|
75.000
|
$880.000
|
$1.000
|
$550.000
|
|
|
REACT 350 CABLE HOLDERS
|
EA
|
180.000
|
$400.000
|
$1.000
|
$350.000
|
|
|
FAST TRACK CENTER PANELS
|
EA
|
8.000
|
$1,300.000
|
$1.000
|
$1,500.000
|
|
|
REPAIR (NARROW REACT 350)
|
EA
|
8.000
|
$500.000
|
$1.000
|
$3,500.000
|
|
|
REPAIR (QUAD - ELITE) WIDE
|
EA
|
8.000
|
$500.000
|
$300.000
|
$750.000
|
|
|
REPAIR (SMTC)(W) (BAY)
|
EA
|
180.000
|
$100.000
|
$1.000
|
$500.000
|
|
|
REPAIR (SMTC) (W)
|
LF
|
200.000
|
$185.000
|
$1.000
|
$150.000
|
|
|
REM/REPLACE CURB GUIDANCE SYSTEM
|
EA
|
50.000
|
$200.000
|
$100.000
|
$200.000
|
|
|
REM/REPLACE DELINEATOR POST ASSEMBLY
|
EA
|
3,000.000
|
$50.000
|
$34.000
|
$40.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
113.000
|
$200.000
|
$1.000
|
$100.000
|
|
|
TMA (STATIONARY)
|
DAY
|
250.000
|
$500.000
|
$1.000
|
$100.000
|
|
|
PERF BASED OPER & MAINT MANAGED LANES
|
MO
|
24.000
|
$100,000.000
|
$60,000.000
|
$90,000.000
|
|
Totals: |
$5,537,543.900
|
$3,650,661.750
|
$4,822,547.500
|