DALLAS US0067 (6328-10-001)

Items: 14

County: DALLAS
Length: N/A
Highway: US0067
District: DALLAS
Control Number: 6328-10-001
DBE Goal: N/A
Project: RMC - 632810001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $411,641.45
Date: 07/11/2018 (7 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$411,641.45
1
$324,270.00
Over/Under Est: -21.23% -$87,371.45
Over/Under Est: -13.43% -$55,281.45
Amt Left: 9.9% $32,090.00
$379,720.00
Over/Under Est: -7.75% -$31,921.45
Amt Left: 17.1% $55,450.00
Delta: -6.56% -$23,360.00
Over/Under Est: -2.91% -$11,991.45
Amt Left: 23.25% $75,380.00
Delta: -5.25% -$19,930.00
$408,340.00
Over/Under Est: -0.8% -$3,301.45
Amt Left: 25.93% $84,070.00
Delta: -2.17% -$8,690.00
Over/Under Est: 7.15% $29,423.55
Amt Left: 36.02% $116,795.00
Delta: -8.01% -$32,725.00
Over/Under Est: 39.21% $161,388.54
Amt Left: 76.71% $248,759.99
Delta: -29.92% -$131,964.99

Bid Items & Bid Tabulations

14 Total 0 of 14
DALLAS  |  US0067  |  DALLAS  |  6328-10-001  |  07/11/2018  |  $411,641.45  |  RMC - 632810001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
IIPL USA LLC
GIBSON & ASSOCIATES, INC.
DBI SERVICES, LLC
IOWA BRIDGE & CULVERT, LC
SELECT STRIPING LLC
HIGHWAY 19 CONSTRUCTION LLC
ALTUS CONSTRUCTION LLC
REMOVING CONC (SIDEWALKS)
SY 157.000 $11.000 $20.000 $40.000 $27.000 $25.000 $20.000 $25.000 $18.410
REMOVING CONC (CURB)
LF 1,175.000 $15.500 $10.000 $12.000 $9.000 $25.000 $10.000 $10.000 $21.910
REMOVING CONC (CURB AND GUTTER)
LF 100.000 $13.000 $30.000 $50.000 $14.000 $25.000 $15.000 $10.000 $15.910
FLOWABLE BACKFILL
CY 50.000 $340.000 $300.000 $290.000 $248.000 $600.000 $250.000 $250.000 $257.150
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 330.000 $165.000 $150.000 $155.000 $272.000 $215.000 $200.000 $250.000 $446.420
RIPRAP (CONC)(4 IN)
CY 135.000 $700.000 $500.000 $725.000 $498.000 $750.000 $800.000 $500.000 $613.870
MOBILIZATION
LS 1.000 $37,421.950 $30,000.000 $21,700.000 $23,300.000 $39,000.000 $40,000.000 $60,000.000 $56,671.280
CONC CURB (TY I)
LF 350.000 $32.000 $40.000 $45.000 $30.000 $35.000 $50.000 $40.000 $36.910
CONC CURB (TY II)
LF 825.000 $30.000 $30.000 $35.000 $33.000 $45.000 $34.000 $40.000 $32.940
CONC CURB & GUTTER (TY II)
LF 100.000 $35.000 $50.000 $60.000 $38.000 $75.000 $60.000 $55.000 $50.350
CONC SIDEWALKS (4")
SY 187.000 $55.000 $90.000 $100.000 $78.000 $100.000 $80.000 $70.000 $103.630
REP (CONC PARAPETW/STL POST/RAIL-T4(S))
LF 120.000 $235.000 $300.000 $160.000 $213.000 $325.000 $325.000 $350.000 $57.360
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 168.000 $165.000 $100.000 $110.000 $240.000 $25.000 $80.000 $100.000 $146.060
TMA (STATIONARY)
DAY 155.000 $525.000 $200.000 $250.000 $315.000 $25.000 $300.000 $500.000 $949.390
Totals: $411,641.450 $324,270.000 $356,360.000 $379,720.000 $399,650.000 $408,340.000 $441,065.000 $573,029.990