DALLAS US0080 (6328-09-001)

Items: 18

County: DALLAS
Length: N/A
Highway: US0080
District: DALLAS
Control Number: 6328-09-001
DBE Goal: N/A
Project: RMC - 632809001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $364,604.75
Date: 07/10/2018 (7 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$364,604.75
$335,413.00
Over/Under Est: -8.01% -$29,191.75
Over/Under Est: 12.11% $44,150.25
Amt Left: 21.87% $73,342.00
$419,750.00
Over/Under Est: 15.12% $55,145.25
Amt Left: 25.14% $84,337.00
Delta: -2.69% -$10,995.00
Over/Under Est: 30.21% $110,130.25
Amt Left: 41.54% $139,322.00
Delta: -13.10% -$54,985.00
Over/Under Est: 68.24% $248,806.30
Amt Left: 82.88% $277,998.05
Delta: -29.21% -$138,676.05

Bid Items & Bid Tabulations

18 Total 0 of 18
DALLAS  |  US0080  |  DALLAS  |  6328-09-001  |  07/10/2018  |  $364,604.75  |  RMC - 632809001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
GIBSON & ASSOCIATES, INC.
IIPL USA LLC
HIGHWAY 19 CONSTRUCTION LLC
O. TREVINO CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 252.000 $49.000 $26.000 $80.000 $50.000 $25.000 $52.000
REMOVING CONC (MEDIANS)
SY 25.000 $12.000 $26.000 $100.000 $20.000 $30.000 $80.000
REMOVING CONC (SIDEWALKS)
SY 400.000 $14.000 $26.000 $40.000 $20.000 $25.000 $21.000
REMOVING CONC (CURB)
LF 1,495.000 $12.000 $9.000 $16.000 $10.000 $10.000 $18.500
REMOVING CONC (CURB AND GUTTER)
LF 100.000 $13.000 $13.000 $50.000 $30.000 $10.000 $44.000
FLOWABLE BACKFILL
CY 35.000 $340.000 $230.000 $610.000 $300.000 $250.000 $448.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 425.000 $165.000 $160.000 $150.000 $200.000 $250.000 $154.000
RIPRAP (CONC)(4 IN)
CY 28.000 $700.000 $470.000 $765.000 $800.000 $500.000 $1,073.000
RIPRAP (MOW STRIP)(4 IN)
CY 20.300 $440.000 $470.000 $900.000 $500.000 $450.000 $1,118.500
MOBILIZATION
LS 1.000 $35,564.750 $22,000.000 $37,000.000 $40,000.000 $60,000.000 $116,000.000
CONC CURB (TY I)
LF 100.000 $32.000 $30.000 $50.000 $40.000 $40.000 $40.000
CONC CURB (TY II)
LF 1,395.000 $30.000 $31.000 $44.000 $30.000 $40.000 $37.000
CONC CURB & GUTTER (TY II)
LF 100.000 $35.000 $36.000 $60.000 $50.000 $55.000 $88.000
CONC SIDEWALKS (4")
SY 400.000 $55.000 $75.000 $70.000 $100.000 $70.000 $115.000
CONC MEDIAN
SY 25.000 $50.000 $94.000 $125.000 $200.000 $80.000 $125.000
REP (CONC PARAPETW/STL POST/RAIL-T4(S))
LF 250.000 $235.000 $215.000 $150.000 $300.000 $350.000 $504.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 133.000 $165.000 $195.000 $110.000 $100.000 $100.000 $355.000
TMA (STATIONARY)
DAY 95.000 $300.000 $215.000 $250.000 $300.000 $500.000 $222.000
Totals: $364,604.750 $335,413.000 $408,755.000 $419,750.000 $474,735.000 $613,411.050