DALLAS IH0035E (6320-62-001)

Items: 55

County: DALLAS
Length: N/A
Highway: IH0035E
District: DALLAS
Control Number: 6320-62-001
DBE Goal: N/A
Project: RMC - 632062001
Guaranty: N/A
Time: 548 CALENDAR DAYS
Engineer's Estimate: $905,020.00
Date: 11/03/2017 (8 years ago)
Contract Number: N/A
Type: ROUTINE MAINT OF MANAGED LANES IN DALLAS & DENTON
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$905,020.00
$1,174,127.00
Over/Under Est: 29.73% $269,107.00
Over/Under Est: 81.15% $734,455.00
Amt Left: 39.63% $465,348.00

Bid Items & Bid Tabulations

55 Total 0 of 55
DALLAS  |  IH0035E  |  DALLAS  |  6320-62-001  |  11/03/2017  |  $905,020.00  |  RMC - 632062001  |  ROUTINE MAINT OF MANAGED LANES IN DA...  |  548 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FIREMAN EXCAVATING, INC.
ROY JORGENSEN ASSOCIATES, INC.
FLEXIBLE PAVEMENT STRUCTURE REPAIR(14")
SY 400.000 $90.000 $80.000 $90.000
FULL - DEPTH REPAIR CRCP (14")
SY 400.000 $295.000 $100.000 $310.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 100.000 $175.000 $200.000 $200.000
CONC STR REPAIR (STANDARD)
SF 1,000.000 $125.000 $50.000 $90.000
CLEANING EXISTING JOINTS
LF 2,000.000 $7.000 $4.000 $15.000
MOBILIZATION
LS 1.000 $90,000.000 $170,000.000 $150,000.000
CONC CURB (TY II)
LF 25.000 $30.000 $100.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $30.000 $30.000 $38.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $1,275.000 $1,200.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,000.000 $2,500.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $280.000 $200.000 $500.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 200.000 $25.000 $60.000 $20.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 500.000 $30.000 $40.000 $40.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 10.000 $710.000 $650.000 $700.000
IN SM RD SN SUP&AM TYS80(1)SB(T)
EA 4.000 $750.000 $650.000 $850.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $1,550.000 $1,500.000 $2,000.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 2.000 $2,000.000 $1,500.000 $2,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 4,000.000 $5.500 $8.000 $5.000
REFL PAV MRK TY I (W)12"(SLD)(060MIL)
LF 3,000.000 $2.000 $2.770 $3.500
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 20.000 $120.000 $150.000 $200.000
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
EA 20.000 $500.000 $350.000 $400.000
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
EA 20.000 $550.000 $450.000 $550.000
RE PV MRK TY I(BLACK)6"(SHADOW)(090MIL)
LF 7,500.000 $0.650 $0.700 $0.900
PAVEMENT SEALER 4"
LF 7,500.000 $0.110 $0.150 $0.250
PAVEMENT SEALER 6"
LF 30,000.000 $0.170 $0.230 $0.300
PAVEMENT SEALER 12"
LF 3,000.000 $0.910 $1.000 $1.100
PAVEMENT SEALER (ENTR GORE)
EA 15.000 $225.000 $300.000 $275.000
PAVEMENT SEALER (EXIT GORE)
EA 15.000 $280.000 $400.000 $375.000
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 200,000.000 $0.190 $0.240 $0.270
RE PM W/RET REQ TY I (W)6"(BRK)(060MIL)
LF 22,500.000 $0.360 $0.420 $0.500
REFL PAV MRK TY I (W)12"(DOT)(060MIL)
LF 4,000.000 $2.000 $2.750 $2.950
REFL PAV MRKR TY I-C
EA 1,300.000 $2.600 $4.000 $4.000
REFL PAV MRKR TY I-R
EA 210.000 $4.000 $4.200 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 20,000.000 $0.260 $0.400 $0.500
ELIM EXT PAV MRK & MRKS (6")
LF 22,500.000 $0.300 $0.450 $0.550
ELIM EXT PAV MRK & MRKS (12")
LF 3,000.000 $0.650 $2.000 $1.900
ELIM EXT PAV MRK & MRKS (ENTR GORE)
EA 15.000 $260.000 $300.000 $325.000
ELIM EXT PAV MRK & MRKS (EXIT GORE)
EA 15.000 $270.000 $400.000 $450.000
PAV SURF PREP FOR MRK (4")
LF 7,500.000 $0.070 $0.120 $0.180
PAV SURF PREP FOR MRK (6")
LF 22,500.000 $0.120 $0.170 $0.230
PAV SURF PREP FOR MRK (12")
LF 3,000.000 $0.600 $0.220 $0.300
PAV SURF PREP FOR MRK (ENTR GORE)
EA 15.000 $25.000 $150.000 $200.000
PAV SURF PREP FOR MRK (EXIT GORE)
EA 15.000 $25.000 $250.000 $275.000
POTHOLE REPAIR (STANDARD)
SY 100.000 $90.000 $85.000 $100.000
JT / CRCK SEAL (HOT - POURED RUBBER)
LF 2,000.000 $1.250 $4.000 $8.000
CRACK CLEANING AND SEALING (JCP)
LF 1,000.000 $2.500 $8.000 $8.000
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 200.000 $100.000 $94.000 $210.000
PAVEMENT EDGES, STRUCTURES & FIXTURES
MI 80.000 $150.000 $70.000 $250.000
CLEANING / SWEEPING (AGGREGATE REMOVAL)
MI 40.000 $150.000 $200.000 $500.000
GRAFFITI REMOVAL (PAINTING)
SF 1,000.000 $0.800 $10.000 $5.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 500.000 $10.000 $40.000 $25.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 100.000 $18.000 $20.000 $50.000
REALIGN EXISTING RAIL
LF 500.000 $13.000 $5.000 $10.000
REMOVE AND REPLACE (TRACC)
EA 60.000 $3,000.000 $7,000.000 $12,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 250.000 $125.000 $250.000 $115.000
Totals: $905,020.000 $1,174,127.000 $1,639,475.000