DALLAS SS 408 (3000-01-028)

Items: 83

County: DALLAS
Length: N/A
Highway: SS 408
District: DALLAS
Control Number: 3000-01-028
DBE Goal: 0.0%
Project: F 2B24(225)
Guaranty: N/A
Time: 292 WORKING DAYS
Engineer's Estimate: $19,305,830.10
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
NATHAN PETTER
DUNG NGUYEN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$19,305,830.10
$16,188,626.00
Over/Under Est: -16.15% -$3,117,204.10
Over/Under Est: -9.75% -$1,882,784.01
Amt Left: 7.63% $1,234,420.09
$20,102,434.50
Over/Under Est: 4.13% $796,604.40
Amt Left: 24.18% $3,913,808.50
Delta: -15.38% -$2,679,388.41
Subcontractor Percentage Amount
HILBASH INVESTMENT LLC 7.63% $1,224,086.12
GIBSON & ASSOCIATES, INC. 3.45% $553,485.86
SUPERIOR TRAFFIC CONTROL, LLC 1.50% $240,646.03
LINEAR TRAFFIC MARKINGS LLC 1.15% $184,495.29
FORTSON CONTRACTING, INC. 0.90% $144,387.62
J. H. ODEN CONTRACTING COMPANY 0.87% $139,574.69
AMERICAN CONCRETE TRUCKING, LLC 0.57% $91,445.49
STOIC CIVIL CONSTRUCTION, INC. 0.37% $59,359.35
SURFACE PREPARATION TECHNOLOGIES, LLC 0.09% $14,438.76
Total: 16.53% $2,651,919.21

Bid Items & Bid Tabulations

83 Total 0 of 83
DALLAS  |  SS 408  |  DALLAS  |  3000-01-028  |  07/09/2024  |  $19,305,830.10  |  F 2B24(225)  |  HAZARD ELIM & SAFETY  |  292 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 6.000 $2,000.000 $100.000 $8,000.000 $100,000.000
REMOVING CONC (RIPRAP)
CY 5.000 $400.000 $1,500.000 $230.000 $3,000.000
REMOVE CONC (WINGWALL)
CY 4.000 $900.000 $1,800.000 $420.000 $5,000.000
BACKFILL (TY A OR B)
STA 182.000 $300.000 $485.000 $690.000 $450.000
COMPOST MANUF TOPSOIL (4")
SY 1,590.000 $1.250 $1.300 $4.200 $10.000
BLOCK SODDING
SY 4,141.000 $4.000 $4.500 $6.750 $10.000
VEGETATIVE WATERING
MG 616.000 $6.000 $80.000 $51.000 $1.000
FLEX PAVEMENT STRUCTURE REPAIR (8"-12")
SY 500.000 $100.000 $250.000 $130.000 $150.000
PLANE ASPH CONC PAV(0" TO 3")
SY 53,170.000 $4.250 $3.000 $3.500 $5.000
FULL - DEPTH REPAIR CPCD (8")
SY 1,900.000 $225.000 $218.000 $260.000 $450.000
FULL - DEPTH REPAIR CPCD (10")
SY 1,400.000 $350.000 $280.000 $285.000 $500.000
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 88.000 $750.000 $910.000 $1,400.000 $1,000.000
FLOWABLE BACKFILL
CY 33.000 $600.000 $580.000 $525.000 $650.000
TEMPORARY SPL SHORING
SF 200.000 $275.000 $106.120 $88.000 $55.000
CL C CONC (WINGWALLS)
CY 4.000 $2,200.000 $4,500.000 $2,500.000 $15,000.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 20.000 $200.000 $200.000 $230.000 $350.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 76.000 $250.000 $205.000 $232.000 $360.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 279.000 $250.000 $245.000 $275.000 $400.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 5.000 $2,100.000 $1,850.000 $1,000.000 $5,000.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 225.000 $200.000 $171.430 $275.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 160.000 $750.000 $595.000 $700.000 $550.000
CLEANING AND SEALING JOINTS (CL 7)
LF 2,867.000 $45.000 $32.000 $52.000 $60.000
(PARAPET)
LF 36.000 $200.000 $1,800.000 $2,000.000 $2,500.000
REMOV STR (WINGWALL PARAPET)
EA 9.000 $6,500.000 $2,600.000 $2,800.000 $5,000.000
MOBILIZATION
LS 1.000 $1,845,252.100 $1,618,862.600 $1,230,653.000 $2,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $25,000.000 $70,000.000 $52,000.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 395.000 $80.000 $65.000 $75.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 395.000 $25.000 $15.000 $21.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 445.000 $40.000 $33.000 $42.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 445.000 $15.000 $12.000 $16.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $10.000 $3.000 $4.250 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $3.000 $1.000 $1.080 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,000.000 $10.000 $4.600 $4.300 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $4.000 $1.100 $1.150 $9.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 1,000.000 $9.000 $8.250 $11.000 $6.000
CONCRETE CURB (SPECIAL)
LF 145.000 $100.000 $60.000 $74.000 $125.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 87,320.000 $0.500 $0.120 $0.130 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 3,000.000 $30.000 $22.750 $25.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $3,600.000 $1,950.000 $2,260.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,600.000 $1,250.000 $1,355.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 2,813.000 $4.500 $2.500 $2.750 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $300.000 $200.000 $220.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $400.000 $250.000 $275.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,600.000 $2,900.000 $3,180.000 $3,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $260.000 $250.000 $275.000 $2,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 31.000 $12.000 $25.000 $28.000 $100.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 20,961.000 $0.500 $0.410 $0.390 $0.500
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 44,611.000 $0.500 $0.390 $0.350 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 44,611.000 $0.500 $0.390 $0.350 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,100.000 $1.000 $0.500 $1.250 $6.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,400.000 $1.000 $2.270 $0.980 $3.000
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 260.000 $0.750 $2.850 $2.700 $6.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 3,000.000 $1.000 $2.750 $2.450 $6.000
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 6.000 $1,000.000 $2,100.000 $925.000 $2,000.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 7.000 $1,000.000 $2,750.000 $1,360.000 $2,000.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 2,250.000 $1.100 $2.800 $3.270 $6.000
PAVEMENT SEALER 6"
LF 13,445.000 $1.300 $0.590 $0.400 $2.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 23,650.000 $0.750 $0.980 $0.650 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 47,300.000 $0.750 $0.970 $0.650 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 47,300.000 $0.750 $0.970 $0.650 $1.000
REFL PAV MRKR TY II-C-R
EA 1,183.000 $6.000 $4.000 $4.350 $6.000
ELIM EXT PAV MRK & MRKS (6")
LF 13,445.000 $0.500 $0.360 $0.700 $2.000
PAV SURF PREP FOR MRK (6")
LF 13,445.000 $0.500 $0.290 $0.460 $2.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 400.000 $90.000 $100.000 $100.000 $40.000
FIBER REINFORCED POLYMER PATCHING MATLS
LB 500.000 $10.000 $25.000 $25.000 $40.000
REP METAL POST W/ BASE PLATE(T4(A)RAIL
EA 48.000 $100.000 $12.000 $290.000 $650.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 110.000 $360.000 $850.000 $965.000 $1,000.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 65.000 $80.000 $55.000 $65.000 $100.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 115.000 $60.000 $168.000 $190.000 $250.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 132.000 $80.000 $125.000 $135.000 $200.000
REP STL BRIDGE MEMBER (PIN NUT)
EA 1.000 $150.000 $500.000 $585.000 $1,000.000
BRIDGE JOINT REPAIR (ARMOR)
LF 59.000 $1,200.000 $925.000 $1,100.000 $1,500.000
CAM (ASPHALT) PG(76-22)
TON 1,392.000 $180.000 $174.600 $190.000 $185.000
CAM (AGGREGATE)
TON 17,401.000 $230.000 $174.600 $190.000 $185.000
SP MIXES SP-C SAC-A PG76-22
TON 36,542.000 $175.000 $124.450 $154.000 $175.000
TACK COAT
GAL 25,311.000 $5.000 $4.000 $4.750 $5.000
TBWC (MEMBRANE)
GAL 63,276.000 $7.000 $4.000 $4.000 $5.000
TBWC PG76-22 SAC-A TY C
TON 13,051.000 $215.000 $172.000 $200.000 $195.000
REPLACE ELASTOMERIC BEARING PADS
EA 11.000 $8,500.000 $9,400.000 $11,000.000 $12,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $18,600.000 $18,500.000 $20,000.000
TMA (STATIONARY)
DAY 584.000 $200.000 $235.990 $5.000 $250.000
TMA (MOBILE OPERATION)
DAY 60.000 $250.000 $25.000 $5.000 $550.000
REML & DISPL DRIFTWOOD & DEBRIS
CY 530.000 $150.000 $150.000 $190.000 $200.000
Totals: $19,305,830.100 $16,188,626.000 $17,423,046.090 $20,102,434.500