DALLAS IH 20 (2374-03-098)

Items: 73

County: DALLAS
Length: N/A
Highway: IH 20
District: DALLAS
Control Number: 2374-03-098
DBE Goal: N/A
Project: C 2374-3-98
Guaranty: N/A
Time: 219 WORKING DAYS
Engineer's Estimate: $17,263,456.82
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
NATHAN PETTER
DUNG NGUYEN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$17,263,456.82
$20,222,498.00
Over/Under Est: 17.14% $2,959,041.18
Over/Under Est: 17.62% $3,040,973.75
Amt Left: 0.41% $81,932.57
Over/Under Est: 22.91% $3,954,652.38
Amt Left: 4.92% $995,611.20
Delta: -4.50% -$913,678.63
Subcontractor Percentage Amount
GIBSON & ASSOCIATES, INC. 4.82% $974,724.40
DIIBS SPECIALISTS, LLC 3.88% $784,632.92
DUSTROL, INC. 3.55% $717,898.68
LINEAR TRAFFIC MARKINGS LLC 1.54% $311,426.47
MACIAS SPECIALTY CONTRACTING LLC 0.45% $91,001.24
AWP SAFETY 0.13% $26,289.25
RELIABLE CONCRETE CUTTING LLC 0.12% $24,267.00
ACT SAW CUTTING & REMOVAL 0.12% $24,267.00
PENHALL COMPANY 0.12% $24,267.00
KING GEORGE TRAFFIC SOLUTIONS LLC 0.10% $20,222.50
C. GREEN SCAPING, L.P. 0.07% $14,155.75
WEST TEXAS RUMBLE STRIP LLC 0.07% $14,155.75
Total: 14.97% $3,027,307.96

Bid Items & Bid Tabulations

73 Total 0 of 73
DALLAS  |  IH 20  |  DALLAS  |  2374-03-098  |  06/01/2023  |  $17,263,456.82  |  C 2374-3-98  |  REHAB EXIST ROADWAY  |  219 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNH CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
AUSTIN BRIDGE & ROAD SERVICES, LP
REMOVING CONC (RIPRAP)
SY 503.000 $25.000 $50.000 $42.000 $25.000
COMPOST MANUF TOPSOIL (4")
SY 1,550.000 $2.300 $10.000 $2.700 $4.180
BLOCK SODDING
SY 1,550.000 $7.000 $10.000 $6.850 $7.390
VEGETATIVE WATERING
MG 231.000 $13.750 $50.000 $45.000 $65.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(9")
SY 1,766.000 $85.000 $90.000 $91.000 $105.440
PLAN ASPH CONC PAV(0" TO 2.25")
SY 489,540.000 $2.000 $3.000 $2.900 $4.000
FULL - DEPTH REPAIR CRCP (9")
SY 3,134.000 $310.000 $300.000 $388.000 $351.000
FLOWABLE BACKFILL
CY 49.000 $400.000 $350.000 $525.000 $350.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 588.000 $190.000 $200.000 $182.000 $220.000
CONC STR REPAIR (STANDARD)
SF 10.000 $500.000 $500.000 $222.000 $254.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 99.000 $624.000 $650.000 $740.000 $823.040
RIPRAP (STONE PROTECTION)(18 IN)
CY 84.000 $184.000 $185.000 $345.000 $338.800
RIPRAP (MOW STRIP)(4 IN)
CY 1,113.000 $525.000 $500.000 $700.000 $904.180
CLEANING AND SEALING JOINTS (CL 7)
LF 1,511.000 $35.000 $90.000 $51.000 $30.000
RETROFIT RAIL (TY SSTR)
LF 2,218.000 $205.000 $125.000 $185.000 $347.500
HEADER TYPE EXPANSION JOINT
CF 460.000 $400.000 $650.000 $475.000 $429.590
JOINT SEALANT
LF 2,740.000 $40.000 $60.000 $39.000 $19.000
RAISING EXIST STRUCT
LS 1.000 $85,000.000 $35,000.000 $33,000.000 $108,675.000
MOBILIZATION
LS 1.000 $1,569,405.170 $1,800,000.000 $919,804.000 $2,121,810.920
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $40,000.000 $8,500.000 $38,918.000 $75,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 330.000 $69.000 $50.000 $69.000 $98.000
ROCK FILTER DAMS (REMOVE)
LF 330.000 $16.000 $15.000 $21.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 468.000 $35.000 $40.000 $37.570 $42.560
CONSTRUCTION EXITS (REMOVE)
SY 468.000 $14.000 $20.000 $16.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,000.000 $5.500 $4.000 $3.750 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,000.000 $2.100 $2.000 $0.950 $0.790
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,000.000 $5.780 $18.000 $4.200 $4.150
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $2.100 $9.000 $1.600 $0.790
PTB (FUR & INST)(STEEL)
LF 500.000 $50.000 $100.000 $31.000 $28.860
PTB (MOVE)(STEEL)
LF 1,800.000 $25.000 $20.000 $26.000 $1.000
PTB (REMOVE)(STEEL)
LF 500.000 $12.000 $20.000 $26.000 $5.490
CONCRETE CURB (SPECIAL)
LF 200.000 $50.000 $80.000 $44.000 $100.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 120,124.000 $0.200 $0.500 $0.160 $0.110
MTL W-BEAM GD FEN (TIM POST)
LF 20,718.000 $22.000 $23.000 $22.000 $20.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 47.000 $1,925.000 $2,000.000 $2,200.000 $1,775.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 35.000 $1,320.000 $2,000.000 $1,100.000 $1,000.000
REMOVE METAL BEAM GUARD FENCE
LF 22,149.000 $2.000 $5.000 $2.200 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 16.000 $125.000 $850.000 $133.000 $125.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 19.000 $125.000 $850.000 $80.000 $75.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 7.000 $245.000 $850.000 $215.000 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 39.000 $3,000.000 $3,250.000 $2,900.000 $2,775.000
GUARDRAIL END TREATMENT (REMOVE)
EA 41.000 $225.000 $850.000 $210.000 $200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $2,100.000 $3,500.000 $1,050.000 $25.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,300.000 $2,500.000 $777.000 $953.650
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
EA 1.000 $45,000.000 $50,000.000 $38,000.000 $27,960.070
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $9,300.000 $21,000.000 $8,000.000 $7,597.230
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 100.000 $20.000 $100.000 $21.000 $20.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 100.000 $20.000 $100.000 $21.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 452.000 $30.000 $100.000 $26.500 $25.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 26,892.000 $1.200 $3.000 $1.050 $1.250
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 12.000 $850.000 $1,250.000 $600.000 $550.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 13.000 $1,500.000 $2,000.000 $1,000.000 $925.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 52,020.000 $0.850 $1.250 $0.660 $0.630
PAVEMENT SEALER 6"
LF 31,760.000 $0.200 $0.500 $0.260 $0.240
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 52,020.000 $0.650 $1.000 $0.640 $0.610
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 69,286.000 $0.750 $1.000 $0.640 $0.610
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 69,286.000 $0.750 $1.000 $0.640 $0.610
PREFAB PAV MRK TY C (MULTI) (SHIELD)
EA 9.000 $6,000.000 $5,000.000 $2,200.000 $2,065.000
REFL PAV MRKR TY II-C-R
EA 2,598.000 $5.400 $6.000 $4.000 $3.700
ELIM EXT PAV MRK & MRKS (4")
LF 18,080.000 $0.660 $1.000 $0.620 $0.590
ELIM EXT PAV MRK & MRKS (6")
LF 13,680.000 $0.730 $1.000 $0.730 $0.690
PAV SURF PREP FOR MRK (6")
LF 31,760.000 $0.230 $1.000 $0.140 $0.130
FIBER REINFORCED POLYMER PATCHING MATLS
LB 14,558.000 $4.500 $12.000 $13.500 $13.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 35.000 $98.000 $1,000.000 $80.000 $120.000
BRIDGE JOINT REPAIR (ARMOR)
LF 354.000 $500.000 $1,000.000 $475.000 $421.000
BRIDGE JOINT REPLACEMENT (ARMOR)
LF 82.000 $615.000 $1,000.000 $800.000 $567.000
MEMBRANE UNDERSEAL
GAL 97,908.000 $4.000 $5.000 $3.850 $3.800
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 66,639.000 $135.000 $160.000 $178.000 $155.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $410.000 $1,500.000 $310.000 $2,116.960
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $20,000.000 $16,500.000 $14,000.000 $16,250.000
TMA (STATIONARY)
DAY 438.000 $350.000 $250.000 $370.000 $160.000
TMA (MOBILE OPERATION)
DAY 219.000 $350.000 $350.000 $0.010 $5.120
REML & DISPL DRIFTWOOD & DEBRIS
LS 1.000 $15,000.000 $85,000.000 $24,500.000 $35,000.000
Totals: $17,263,456.820 $20,222,498.000 $20,304,430.570 $21,218,109.200