DALLAS FM 1382 (1047-03-079)
Items: 64
County: DALLAS
Length: N/A
Highway: FM 1382
District: DALLAS
Control Number: 1047-03-079
DBE Goal: N/A
Project: STP 2024(350)TP
Guaranty: N/A
Time: 203 WORKING DAYS
Engineer's Estimate: $4,296,372.22
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,296,372.22 | |||
| $4,250,000.00 |
-1.08%
-$46,372.22
|
|||
| $4,338,488.11 |
0.98%
$42,115.89
|
2.08%
$88,488.11
|
||
| $4,535,091.03 |
5.56%
$238,718.81
|
6.71%
$285,091.03
|
-4.53%
-$196,602.92
|
|
| $4,857,411.00 |
13.06%
$561,038.78
|
14.29%
$607,411.00
|
-7.11%
-$322,319.97
|
|
| $5,974,276.35 |
39.05%
$1,677,904.13
|
40.57%
$1,724,276.35
|
-22.99%
-$1,116,865.35
|
E
Engineer's Estimate
$4,296,372.22
1
Awarded
$4,250,000.00
Over/Under Est:
-1.08%
-$46,372.22
$4,338,488.11
Over/Under Est:
0.98%
$42,115.89
Amt Left:
2.08%
$88,488.11
$4,535,091.03
Over/Under Est:
5.56%
$238,718.81
Amt Left:
6.71%
$285,091.03
Delta:
-4.53%
-$196,602.92
$4,857,411.00
Over/Under Est:
13.06%
$561,038.78
Amt Left:
14.29%
$607,411.00
Delta:
-7.11%
-$322,319.97
$5,974,276.35
Over/Under Est:
39.05%
$1,677,904.13
Amt Left:
40.57%
$1,724,276.35
Delta:
-22.99%
-$1,116,865.35
| Subcontractor | Percentage | Amount |
|---|---|---|
| QUALITY DUMP HAULERS, LLC | 14.12% | $600,100.00 |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 7.91% | $336,175.00 |
| C T & S METAL FABRICATORS INC. | 7.09% | $301,325.00 |
| FARR FOUNDATION, INC. | 0.84% | $35,700.00 |
| TRAFFIC HIGHWAY MAINTENANCE, LLC | 0.75% | $31,875.00 |
| SUPERIOR TRAFFIC CONTROL, LLC | 0.21% | $8,925.00 |
| Total: | 30.92% | $1,314,100.00 |