DALLAS NTTA (06018-NTT-00-GS-IT)
Items: 0
County: DALLAS
Project: 06018
Highway: NTTA
District: DALLAS
Date: 12/05/2025 (6 months ago)
Time:
Engineer's Estimate: $5,000,000.00 - $10,000,000.00
Type: 06018 RFB TRAFFIC AND SECURITY CAMERAS INSTALLATION AND MAINTENANCE SERVICES
NTTA Number: 06018-NTT-00-GS-IT
DBE Goal: N/A
Bid Solicitation #: B2500001002
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,000,000.00 | |||
| $7,384,327.00 |
47.69%
$2,384,327.00
|
|||
| $7,831,592.13 |
56.63%
$2,831,592.13
|
6.06%
$447,265.13
|
||
| $10,065,553.00 |
101.31%
$5,065,553.00
|
36.31%
$2,681,226.00
|
-28.52%
-$2,233,960.87
|
|
| $10,252,301.30 |
105.05%
$5,252,301.30
|
38.84%
$2,867,974.30
|
-1.86%
-$186,748.30
|
|
| $10,708,734.00 |
114.17%
$5,708,734.00
|
45.02%
$3,324,407.00
|
-4.45%
-$456,432.70
|
|
| $12,428,164.53 |
148.56%
$7,428,164.53
|
68.3%
$5,043,837.53
|
-16.06%
-$1,719,430.53
|
|
| $12,563,265.17 |
151.27%
$7,563,265.17
|
70.13%
$5,178,938.17
|
-1.09%
-$135,100.64
|
|
| $13,831,278.90 |
176.63%
$8,831,278.90
|
87.31%
$6,446,951.90
|
-10.09%
-$1,268,013.73
|
|
| $13,922,915.41 |
178.46%
$8,922,915.41
|
88.55%
$6,538,588.41
|
-0.66%
-$91,636.51
|
|
| $18,299,093.29 |
265.98%
$13,299,093.29
|
147.81%
$10,914,766.29
|
-31.43%
-$4,376,177.88
|
E
Engineer's Estimate
$5,000,000.00
$7,384,327.00
Over/Under Est:
47.69%
$2,384,327.00
$7,831,592.13
Over/Under Est:
56.63%
$2,831,592.13
Amt Left:
6.06%
$447,265.13
$10,065,553.00
Over/Under Est:
101.31%
$5,065,553.00
Amt Left:
36.31%
$2,681,226.00
Delta:
-28.52%
-$2,233,960.87
$10,252,301.30
Over/Under Est:
105.05%
$5,252,301.30
Amt Left:
38.84%
$2,867,974.30
Delta:
-1.86%
-$186,748.30
$10,708,734.00
Over/Under Est:
114.17%
$5,708,734.00
Amt Left:
45.02%
$3,324,407.00
Delta:
-4.45%
-$456,432.70
$12,428,164.53
Over/Under Est:
148.56%
$7,428,164.53
Amt Left:
68.3%
$5,043,837.53
Delta:
-16.06%
-$1,719,430.53
$12,563,265.17
Over/Under Est:
151.27%
$7,563,265.17
Amt Left:
70.13%
$5,178,938.17
Delta:
-1.09%
-$135,100.64
$13,831,278.90
Over/Under Est:
176.63%
$8,831,278.90
Amt Left:
87.31%
$6,446,951.90
Delta:
-10.09%
-$1,268,013.73
$13,922,915.41
Over/Under Est:
178.46%
$8,922,915.41
Amt Left:
88.55%
$6,538,588.41
Delta:
-0.66%
-$91,636.51
$18,299,093.29
Over/Under Est:
265.98%
$13,299,093.29
Amt Left:
147.81%
$10,914,766.29
Delta:
-31.43%
-$4,376,177.88