DALLAS IH 30 (0009-11-270)

Items: 24

County: DALLAS
Length: 40.9430 MILES
Highway: IH 30
District: DALLAS
Control Number: 0009-11-270
DBE Goal: 0.0%
Project: STP 2026(098)HES
Guaranty: $23,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $1,144,816.15
Date: 11/05/2025 (7 months ago)
Contract Number: 11253023
Type: INSTALL/REPLACE SIGNS
Project ID: A00193995
Contract Type: Federal
Project Description: INSTALL DYNAMIC SPEED FEEDBACK SIGNS
Mail/Deliver Bids To: N/A
CHRISTOPHER BLAIN
ERIC HERMAN
ANTHONY BLOCK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$1,144,816.15
Over/Under Est: -1.47% -$16,866.72
Over/Under Est: 3.46% $39,667.85
Amt Left: 5.01% $56,534.57
$1,188,584.10
Over/Under Est: 3.82% $43,767.95
Amt Left: 5.38% $60,634.67
Delta: -0.35% -$4,100.10
Over/Under Est: 7.34% $84,048.85
Amt Left: 8.95% $100,915.57
Delta: -3.39% -$40,280.90
Over/Under Est: 13.77% $157,657.25
Amt Left: 15.47% $174,523.97
Delta: -5.99% -$73,608.40
$1,397,375.22
Over/Under Est: 22.06% $252,559.07
Amt Left: 23.89% $269,425.79
Delta: -7.29% -$94,901.82
Over/Under Est: 22.32% $255,485.35
Amt Left: 24.15% $272,352.07
Delta: -0.21% -$2,926.28
Over/Under Est: 34.85% $398,965.35
Amt Left: 36.87% $415,832.07
Delta: -10.25% -$143,480.00
Over/Under Est: 42.16% $482,639.66
Amt Left: 44.28% $499,506.38
Delta: -5.42% -$83,674.31

Bid Items & Bid Tabulations

24 Total 0 of 24
DALLAS  |  IH 30  |  DALLAS  |  0009-11-270  |  11/05/2025  |  $1,144,816.15  |  STP 2026(098)HES  |  INSTL/REPLACE SIGNS  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
VACA UNDERGROUND UTILITIES INC
SICE, INC.
GARRET SHIELDS INFRASTRUCTURE
WG ENGINEERING & CONSTRUCTION, LLC
YUNEX LLC
GREY SKY CONSTRUCTION LLC
MARCOM'S MOWING SERVICE, LLC
STRUCTURAL INTEGRITY GROUP LLC
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 120.000 $350.000 $276.710 $275.000 $388.429 $400.000 $420.000 $679.000 $385.000 $550.000 $258.420
RIPRAP (CONC)(CL B)
CY 5.250 $1,375.000 $937.500 $800.000 $2,395.206 $1,000.000 $720.000 $2,409.000 $650.000 $1,200.000 $3,094.430
MOBILIZATION
LS 1.000 $92,500.000 $42,411.100 $90,000.000 $107,858.284 $100,000.000 $135,200.000 $235,647.000 $120,000.000 $150,000.000 $92,766.780
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,458.450 $15,782.530 $3,500.000 $22,847.943 $5,000.000 $8,520.000 $10,103.000 $12,500.000 $18,000.000 $44,810.080
TMA (STATIONARY)
DAY 100.000 $400.000 $206.640 $150.000 $479.547 $300.000 $348.000 $235.000 $250.000 $350.000 $250.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 300.000 $5.200 $12.500 $1.000 $7.531 $6.000 $5.000 $5.200 $15.000 $8.000 $1.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $1.250 $1.250 $1.000 $1.097 $1.000 $3.000 $1.720 $5.000 $8.000 $1.000
IN RD IL (TY SA) 30T-8 (250W EQ) LED
EA 15.000 $5,100.000 $4,893.300 $4,500.000 $6,362.049 $4,000.000 $4,655.000 $5,093.000 $6,500.000 $7,500.000 $5,326.160
CONDT (PVC) (SCH 40) (2")
LF 318.000 $20.000 $34.610 $12.000 $35.191 $20.000 $24.000 $23.650 $20.000 $25.000 $23.400
CONDT (PVC) (SCH 40) (2") (BORE)
LF 735.000 $25.000 $50.940 $20.000 $41.283 $30.000 $32.000 $43.740 $60.000 $45.000 $38.840
CONDT (PVC) (SCH 80) (2")
LF 103.000 $23.500 $103.380 $15.000 $49.507 $20.000 $36.000 $25.510 $30.000 $30.000 $24.340
ELEC CONDR (NO.8) BARE
LF 1,053.000 $2.000 $3.350 $2.000 $3.885 $3.000 $2.850 $3.470 $3.000 $3.000 $8.620
ELEC CONDR (NO.8) INSULATED
LF 2,276.000 $2.400 $3.410 $2.500 $4.111 $3.500 $3.000 $3.670 $3.000 $3.500 $5.020
ELEC CONDR (NO.4) INSULATED
LF 309.000 $3.300 $6.250 $3.000 $6.118 $5.000 $3.650 $4.570 $3.000 $6.000 $8.000
GROUND BOX TY A (122311)W/APRON
EA 9.000 $1,900.000 $1,794.660 $1,500.000 $1,787.611 $3,000.000 $1,435.000 $2,234.000 $1,150.000 $1,750.000 $1,973.180
ELC SRV TY A 240/480 060(NS)SS(E)GC(O)
EA 5.000 $6,000.000 $11,329.410 $10,000.000 $14,050.742 $15,000.000 $8,485.000 $11,169.000 $12,500.000 $15,000.000 $14,565.250
ALUMINUM SIGNS (TY A)
SF 687.500 $40.000 $31.910 $20.000 $68.013 $50.000 $45.000 $40.010 $30.000 $45.000 $29.680
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 33.000 $725.000 $844.730 $900.000 $1,469.688 $1,000.000 $1,450.000 $1,063.000 $1,150.000 $700.000 $894.860
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,000.000 $957.110 $1,100.000 $1,611.146 $1,000.000 $1,450.000 $1,171.000 $1,150.000 $825.000 $1,371.650
REMOVE SM RD SN SUP&AM
EA 16.000 $160.000 $168.600 $250.000 $353.373 $500.000 $320.000 $115.000 $500.000 $125.000 $199.730
PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE)
LF 400.000 $20.000 $11.400 $50.000 $17.439 $20.000 $30.000 $20.500 $20.000 $72.000 $18.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 30.000 $8,500.000 $7,225.040 $8,500.000 $4,978.040 $5,000.000 $8,230.000 $8,369.000 $8,500.000 $10,300.000 $11,419.510
PED POLE ASSEMBLY
EA 53.000 $4,200.000 $3,448.530 $2,750.000 $2,407.658 $5,000.000 $1,873.000 $3,721.000 $2,500.000 $3,250.000 $2,931.730
INSTALL SOLAR-POWERED DFSSA
EA 53.000 $4,800.000 $5,329.610 $7,500.000 $4,675.531 $6,000.000 $8,035.000 $5,100.000 $8,500.000 $7,200.000 $9,237.810
Totals: $1,144,816.150 $1,127,949.420 $1,184,484.000 $1,188,584.097 $1,228,865.000 $1,302,473.400 $1,397,375.215 $1,400,301.500 $1,543,781.500 $1,627,455.808