DALLAM US 54 (0238-03-061)

Items: 149

County: DALLAM
Length: 0.3700 MILES
Highway: US 54
District: AMARILLO
Control Number: 0238-03-061
DBE Goal: 0.0%
Project: C 238-3-61
Guaranty: $100,000.00
Time: 602 WORKING DAYS
Engineer's Estimate: $21,200,629.95
Date: 10/01/2024 (1 year ago)
Contract Number: 10243005
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00123139
Project Description: REHAB EXISTING FREIGHT CORRIDOR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$21,200,629.95
$25,914,960.65
Over/Under Est: 22.24% $4,714,330.70
Subcontractor Percentage Amount
ALAMO BROTHERS CONCRETE INC 5.48% $1,458,665.20
APOLLO CONSTRUCTORS, INC. 1.81% $481,785.40
TRP CONSTRUCTION GROUP, LLC 1.10% $292,797.76
HJC FARMS, INC. 1.02% $271,503.38
BARRICADES UNLIMITED 0.56% $149,060.68
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.17% $45,250.56
Total: 10.14% $2,699,062.98

Bid Items & Bid Tabulations

149 Total 0 of 149
DALLAM  |  US 54  |  AMARILLO  |  0238-03-061  |  10/01/2024  |  $21,200,629.95  |  C 238-3-61  |  HAZARD ELIM & SAFETY  |  602 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
PREPARING ROW
STA 94.700 $17,500.000 $1,200.000
REMOV CONC (PAV)
SY 8,138.000 $20.000 $50.000
REMOV CONC (DRIVEWAYS)
SY 2,245.000 $20.000 $60.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 4,001.000 $15.000 $35.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 13,799.000 $12.000 $12.000
REMOV CONC (FOUNDATIONS)
CY 4.000 $500.000 $950.000
REMOV CONC (FLUME)
SY 1,433.000 $20.000 $29.000
REMOV CONC (MISC)
EA 4.000 $600.000 $1,265.000
RMV (0"-4") TRT/UNTRT BASE & ASPH PAV
SY 9,323.000 $3.500 $15.000
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
SY 37,084.000 $10.000 $26.000
RMV (12"-16") TRT/UNTRT BASE & ASPH PAV
SY 16,500.000 $12.000 $31.000
EXCAV (ROADWAY)
CY 9,766.000 $28.000 $55.000
EMBANK (FNL)(DC)(TY B)
CY 1,016.000 $38.000 $65.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 36,750.000 $0.290 $0.200
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 29,400.000 $0.600 $0.500
HYDRO MULCH SEED (TEMP_WARM)
SY 29,400.000 $0.600 $0.500
HYDRO MULCH SEED (TEMP_COOL)
SY 29,400.000 $0.600 $0.500
SOIL RET BLKT(SL_STEEP_SAND_SHORT)
SY 458.000 $5.000 $4.500
CEMENT
TON 636.000 $300.000 $350.000
CEMENT TRT (EXIST MATL)(8")
SY 58,612.000 $5.200 $12.000
PRIME COAT (MC-30)
GAL 14,660.000 $7.000 $8.200
D-GR HMA TY-B PG64-22
TON 12,909.000 $200.000 $215.000
PLANE ASPH CONC PAV(0" TO 3")
SY 47,196.000 $4.000 $6.000
CONC PVMT (CRCP) (13")
SY 54,407.000 $159.000 $190.000
FULL - DEPTH REPAIR CRCP (8")
CY 289.000 $1,210.350 $1,400.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 56.000 $600.000 $600.000
RIPRAP (CONC)(4 IN)
CY 180.000 $800.000 $700.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $3,000.000 $6,500.000
MOBILIZATION
LS 1.000 $1,800,000.000 $2,591,400.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 29.000 $35,000.000 $51,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $16,000.000 $57,000.000
TMA (STATIONARY)
DAY 200.000 $250.000 $630.000
TMA (MOBILE OPERATION)
HR 80.000 $125.000 $120.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 224.000 $75.000 $65.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $10.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 580.000 $5.500 $14.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 580.000 $2.000 $8.000
CONSTRUCTING DETOURS
SY 2,071.000 $145.000 $200.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $18,000.000 $9,200.000
CONC CURB (TY II)
LF 143.000 $20.000 $49.250
CONC CURB (MONO) (TY II)
LF 9,683.000 $15.000 $18.000
CONC CURB (TY C1)
LF 285.000 $25.000 $130.000
DRIVEWAYS (CONC)
SY 4,576.000 $118.000 $190.000
CONC SIDEWALKS (4")
SY 5,313.000 $100.000 $95.000
CONC SIDEWALKS (6")
SY 78.000 $120.000 $85.000
CURB RAMPS (TY 1)
EA 1.000 $2,200.000 $2,000.000
CURB RAMPS (TY 2)
EA 5.000 $2,200.000 $2,250.000
CURB RAMPS (TY 5)
EA 14.000 $2,200.000 $2,000.000
CURB RAMPS (TY 7)
EA 13.000 $2,200.000 $2,000.000
CURB RAMPS (TY 10)
EA 39.000 $2,200.000 $2,000.000
MTL W-BEAM GD FEN (STEEL POST)
LF 3,850.000 $39.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $3,500.000 $3,500.000
REMOVE METAL BEAM GUARD FENCE
LF 2,250.000 $5.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $250.000 $255.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 2.000 $250.000 $255.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $4,000.000 $3,600.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 4.000 $575.000 $835.000
CONDT (PVC) (SCH 80) (2")
LF 300.000 $30.000 $27.500
CONDT (PVC) (SCH 80) (2") (BORE)
LF 210.000 $60.000 $40.250
CONDT (PVC) (SCH 80) (3")
LF 130.000 $40.000 $56.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 210.000 $65.000 $67.000
CONDT (PVC) (SCH 80) (4")
LF 50.000 $55.000 $67.000
CONDUIT (PREPARE)
LF 210.000 $10.000 $4.500
ELEC CONDR (NO.12) INSULATED
LF 550.000 $4.000 $2.250
ELEC CONDR (NO.6) BARE
LF 550.000 $4.000 $3.350
ELEC CONDR (NO.4) BARE
LF 150.000 $4.500 $5.100
ELEC CONDR (NO.4) INSULATED
LF 300.000 $5.000 $5.600
GROUND BOX TY D (162922)W/APRON
EA 6.000 $2,200.000 $2,500.000
REMOVE GROUND BOX
EA 1.000 $600.000 $1,200.000
ELC SRV TY D 120/240 070(NS)SS(E)TP(O)
EA 1.000 $8,800.000 $11,000.000
ALUMINUM SIGNS (TY A)
SF 59.500 $37.000 $46.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $1,000.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 21.000 $1,100.000 $1,250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 27.000 $1,100.000 $1,225.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,500.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,500.000 $1,400.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,500.000 $1,600.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 3.000 $1,500.000 $1,650.000
REMOVE SM RD SN SUP&AM
EA 65.000 $110.000 $115.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 39.000 $50.000 $40.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 11,683.000 $0.700 $1.150
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 20,532.000 $0.700 $1.150
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 22,922.000 $1.000 $1.500
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 37,620.000 $1.000 $1.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 4,002.000 $0.700 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 323.000 $20.000 $19.550
WK ZN PAV MRK REMOV (W)(ARROW)
EA 4.000 $250.000 $560.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 3,200.000 $1.620 $1.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 928.000 $1.000 $1.400
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 720.000 $10.000 $9.550
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $200.000 $280.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $265.000 $335.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 4.000 $995.000 $730.000
PAVEMENT SLER 6"
LF 40,710.000 $0.350 $0.400
PAVEMENT SLER 8"
LF 928.000 $0.500 $0.800
PAVEMENT SLER 24"
LF 720.000 $2.400 $5.600
PAVEMENT SLER (ARROW)
EA 8.000 $40.000 $115.000
PAVEMENT SLER (WORD)
EA 6.000 $50.000 $170.000
PAVEMENT SLER (RR XING)
EA 4.000 $180.000 $225.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 16,253.000 $0.800 $0.950
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 3,885.000 $0.800 $0.950
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 20,142.000 $0.800 $0.950
PLOWABLE REFL PAV MRKR TY I-C
EA 92.000 $90.000 $95.000
PLOWABLE REFL PAV MRKR TY II-A-A
EA 509.000 $90.000 $85.000
ELIM EXT PM & MRKS (4")
LF 30,075.000 $1.450 $1.250
ELIM EXT PM & MRKS (12")
LF 120.000 $4.450 $6.700
ELIM EXT PM & MRKS (24")
LF 380.000 $5.000 $8.950
ELIM EXT PM & MRKS (ARROW)
EA 5.000 $51.000 $115.000
ELIM EXT PM & MRKS (WORD)
EA 2.000 $56.000 $170.000
ELIM EXT PM & MRKS (RR XING)
EA 4.000 $150.000 $350.000
PAV SURF PREP FOR MRK (6")
LF 4,636.000 $0.300 $1.700
PAV SURF PREP FOR MRK (8")
LF 275.000 $0.300 $2.250
PAV SURF PREP FOR MRK (24")
LF 102.000 $0.600 $4.000
PAV SURF PREP FOR MRK (ARROW)
EA 3.000 $2.000 $85.000
PAV SURF PREP FOR MRK (WORD)
EA 1.000 $2.000 $115.000
PAV SURF PREP FOR MRK (RR XING)
EA 2.000 $5.000 $170.000
INSTALL HWY TRF SIG (SYSTEM)
EA 1.000 $35,000.000 $50,000.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $4,000.000 $27,000.000
INSTALL HWY TRF SIG (UPGRADE)
EA 1.000 $5,000.000 $30,000.000
TEMP TRAF SIGNALS
EA 1.000 $40,000.000 $60,000.000
VEH SIG SEC (12")LED(GRN)
EA 10.000 $400.000 $450.000
VEH SIG SEC (12")LED(GRN ARW)
EA 4.000 $400.000 $450.000
VEH SIG SEC (12")LED(YEL)
EA 10.000 $400.000 $450.000
VEH SIG SEC (12")LED(YEL ARW)
EA 8.000 $400.000 $450.000
VEH SIG SEC (12")LED(RED)
EA 10.000 $400.000 $450.000
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $400.000 $450.000
PED SIG SEC (LED)(COUNTDOWN)
EA 8.000 $1,000.000 $1,300.000
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 10.000 $150.000 $300.000
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 4.000 $150.000 $335.000
TRF SIG CBL (TY A)(14 AWG)(2 CONDR)
LF 1,370.000 $3.500 $3.350
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 1,458.000 $4.000 $4.250
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 481.000 $4.250 $5.350
TRF SIG CBL (TY A)(14 AWG)(20 CONDR)
LF 785.000 $5.000 $9.250
REMOVE TRF SIG CBL
LF 350.000 $2.000 $1.150
INS TRF SIG PL AM(S)1 ARM(24')LUM
EA 2.000 $20,705.000 $19,000.000
INS TRF SIG PL AM (S)1 ARM(28')
EA 2.000 $20,000.000 $20,500.000
RELOC TRF SG PL AM(S)SNGL MST ARM POLE
EA 1.000 $2,000.000 $12,000.000
PED POLE ASSEMBLY
EA 4.000 $4,000.000 $6,000.000
RELOCATE PED POLE ASSEMBLY
EA 1.000 $2,500.000 $2,500.000
PED DETECT PUSH BUTTON (APS)
EA 8.000 $850.000 $1,400.000
PED DETECTOR CONTROLLER UNIT
EA 1.000 $5,000.000 $5,000.000
VIVDS CAM ASSY FXD LNS
EA 2.000 $500.000 $4,300.000
VIVDS CABLING
LF 377.000 $1.000 $3.500
GROUND BOX (PREPARE)
EA 2.000 $200.000 $200.000
VDS PROSR SYS
EA 1.000 $5,000.000 $11,500.000
HVDS W/FXD LNS
EA 2.000 $500.000 $6,500.000
VDS CNTRL SOFTWARE
EA 1.000 $1,000.000 $1,650.000
VDS ATSPM
EA 1.000 $1,000.000 $5,250.000
VDS CABLING
LF 777.000 $1.000 $2.800
Totals: $21,200,629.950 $25,914,960.650