Show Job Controls
Bid Cobra

CULBERSON IH0010 (6405-12-001)

Items: 42

County: CULBERSON
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6405-12-001
DBE Goal: N/A
Project: RMC - 640512001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $862,630.00
Date: 06/30/2022 (3 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$862,630.00
$921,772.00
Over/Under Est: 6.86% $59,142.00
$996,630.00
Over/Under Est: 15.53% $134,000.00
Amt Left: 8.12% $74,858.00
Over/Under Est: 55.66% $480,111.31
Amt Left: 45.67% $420,969.31
Delta: -34.73% -$346,111.31

Bid Items & Bid Tabulations

42 Total 0 of 42
CULBERSON  |  IH0010  |  EL PASO  |  6405-12-001  |  06/30/2022  |  $862,630.00  |  RMC - 640512001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APACHE BARRICADE & SIGN
MIJELUM, L.L.C.
SYNERGY PROJECT CONTRACTORS, INC.
MOBILIZATION
LS 1.000 $75,000.000 $40,000.000 $50,000.000 $35,250.000
REMOVE METAL BEAM GUARD FENCE
LF 1,960.000 $10.000 $22.000 $15.000 $25.850
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $750.000 $458.000 $400.000 $470.000
CABLE BARRIER SYSTEM (TL-3)
LF 100.000 $24.000 $31.000 $100.000 $70.500
CABLE BARRIER SYSTEM (TL-4)
LF 100.000 $28.000 $31.000 $100.000 $74.030
CABLE BARRIER TERMINAL SECTION (TL-3)
EA 1.000 $3,650.000 $4,166.000 $4,500.000 $5,170.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 1.000 $3,600.000 $4,166.000 $4,500.000 $5,287.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 75.000 $25.000 $15.000 $50.000 $25.850
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 50.000 $30.000 $15.000 $50.000 $29.380
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 25.000 $15.000 $15.000 $50.000 $24.680
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BR)
EA 50.000 $30.000 $15.000 $50.000 $29.380
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,630.000 $35.000 $26.000 $40.000 $39.950
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 100.000 $43.000 $95.000 $50.000 $78.730
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 100.000 $60.000 $34.000 $20.000 $73.790
REM / REPL TIMBER/STL POST W/O CONC FND
EA 370.000 $70.000 $120.000 $150.000 $141.000
REALIGN POSTS
EA 50.000 $50.000 $29.000 $50.000 $30.550
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 230.000 $36.000 $15.000 $20.000 $32.900
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 300.000 $55.000 $31.000 $60.000 $62.280
REPLACE SINGLE GDRAIL TERMINAL POST
EA 50.000 $90.000 $116.000 $150.000 $64.630
REPAIR OF TERMINAL ANCHORS POSTS
EA 30.000 $700.000 $57.000 $150.000 $804.880
REPLACE TERMINAL ANCHOR POSTS
EA 30.000 $900.000 $130.000 $350.000 $804.880
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 10.000 $3,100.000 $3,552.000 $2,900.000 $4,230.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 15.000 $1,800.000 $1,300.000 $1,500.000 $2,350.000
REPLACE SGT OBJECT MARKER
EA 20.000 $65.000 $26.000 $300.000 $41.130
REPLACE POSTS (TL-4)
EA 1,200.000 $200.000 $290.000 $200.000 $391.280
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 2.000 $400.000 $251.000 $300.000 $495.850
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 2.000 $450.000 $251.000 $300.000 $495.850
REPAIR CONCRETE FOUNDATION (TL-4)
EA 2.000 $550.000 $725.000 $500.000 $352.500
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 10.000 $2,000.000 $1,926.000 $1,800.000 $5,287.500
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 30.000 $1,750.000 $1,926.000 $2,000.000 $5,287.500
REPLACE CABLE (TL-3)
LF 1,000.000 $6.000 $4.750 $10.000 $9.400
REPLACE CABLE (TL-4)
LF 1,500.000 $7.000 $5.250 $10.000 $8.810
CHECK / RE-TENSION CABLE
EA 5.000 $500.000 $395.000 $180.000 $705.000
POST AND CABLE FENCE (REMOVAL)
LF 100.000 $5.500 $4.500 $5.000 $4.700
POST AND CABLE FENCE (REMV CONC ANCHOR)
EA 2.000 $100.000 $117.000 $180.000 $105.750
POST AND CABLE FENCE (NEW INSTALLATION)
LF 100.000 $115.000 $58.000 $15.000 $105.750
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 2.000 $350.000 $216.000 $85.000 $440.630
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 80.000 $100.000 $68.000 $75.000 $105.750
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 100.000 $10.000 $29.000 $8.000 $23.500
POST AND CABLE FENCE (REPAIR)
LF 100.000 $15.000 $18.000 $15.000 $24.680
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 85.000 $150.000 $65.000 $500.000 $176.250
TMA (STATIONARY)
DAY 155.000 $250.000 $615.000 $800.000 $411.250
Totals: $862,630.000 $921,772.000 $996,630.000 $1,342,741.310