CULBERSON RM 652 (2451-02-013)

Items: 102

County: CULBERSON
Length: N/A
Highway: RM 652
District: EL PASO
Control Number: 2451-02-013
DBE Goal: N/A
Project: C 2451-2-13
Guaranty: N/A
Time: 480 WORKING DAYS
Engineer's Estimate: $49,437,214.80
Date: 11/04/2020 (5 years ago)
Contract Number: N/A
Type: FULL DEPTH REHAB
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$49,437,214.80
$49,745,889.15
Over/Under Est: 0.62% $308,674.35
$51,986,898.43
Over/Under Est: 5.16% $2,549,683.63
Amt Left: 4.5% $2,241,009.28

Bid Items & Bid Tabulations

102 Total 0 of 102
CULBERSON  |  RM 652  |  EL PASO  |  2451-02-013  |  11/04/2020  |  $49,437,214.80  |  C 2451-2-13  |  FULL DEPTH REHAB  |  480 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
J.D. ABRAMS, L.P.
PREPARING ROW
STA 646.000 $900.000 $1,500.000 $7,500.000
REMOVING STAB BASE AND ASPH PAV (10")
SY 256,802.000 $6.000 $4.000 $6.000
EXCAVATION (ROADWAY)
CY 118,218.000 $20.000 $20.000 $17.500
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 166,395.000 $26.000 $40.000 $28.800
BACKFILL TY A
CY 43,564.000 $35.000 $34.500 $45.000
BLADING
HR 110.000 $175.000 $105.000 $95.800
PROOF ROLLING
HR 110.000 $135.000 $60.000 $56.610
FL BS (RDWY DEL)(TY A GR 5)
TON 220,050.000 $48.000 $35.000 $23.130
PRIME COAT (AE-P)
GAL 51,571.000 $4.500 $7.000 $2.500
EMULS ASPH (EROSN CONT)(MULTI)
GAL 11,649.000 $5.000 $6.500 $3.500
ASPH (MULTI OPTION)
GAL 195,969.000 $4.000 $4.000 $3.270
AGGR(TY-PB GR-4 SAC-B)
CY 2,902.000 $125.000 $200.000 $200.000
D-GR HMA(SQ) TY-D PG64-22
TON 2,367.000 $160.000 $135.000 $250.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 49.000 $2.500 $50.000 $44.900
STRUCT EXCAV (BOX)
CY 8,142.000 $20.000 $1.000 $1.000
FLOWABLE BACKFILL
CY 2,104.000 $175.000 $300.000 $270.110
TRENCH EXCAVATION PROTECTION
LF 953.000 $4.500 $6.500 $1.250
TEMPORARY SPL SHORING
SF 24,178.000 $50.000 $22.000 $37.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 10,029.000 $120.000 $120.000 $118.990
RIPRAP (SPECIAL)
CY 19.000 $150.000 $300.000 $156.030
GABION MATTRESSES (GALV) (24 IN)
SY 26,454.000 $150.000 $135.000 $135.000
CONC BOX CULV (3 FT X 3 FT)
LF 230.000 $240.000 $300.000 $303.910
CONC BOX CULV (4 FT X 2 FT)
LF 112.000 $250.000 $290.000 $304.550
CONC BOX CULV (7 FT X 3 FT)
LF 1,454.000 $425.000 $490.000 $527.660
CONC BOX CULV (10 FT X 8 FT)
LF 312.000 $1,200.000 $1,000.000 $1,387.430
CONC BOX CULV (12 FT X 10 FT)
LF 536.000 $1,300.000 $1,200.000 $1,773.680
RC PIPE (CL III)(36 IN)
LF 1,185.000 $125.000 $150.000 $216.520
RC PIPE (CL IV)(24 IN)
LF 970.000 $130.000 $110.000 $127.830
HEADWALL (CH - FW - 45) (DIA= 36 IN)
EA 2.000 $6,000.000 $9,500.000 $8,698.360
WINGWALL (PW - 1) (HW=15 FT)
EA 2.000 $40,000.000 $130,000.000 $101,742.720
WINGWALL (PW - 2) (HW=11 FT)
EA 4.000 $22,000.000 $45,000.000 $32,268.560
WINGWALL (PW - 2) (HW=12 FT)
EA 4.000 $34,000.000 $50,000.000 $42,276.640
WINGWALL (PW - 2) (HW=13 FT)
EA 2.000 $35,000.000 $95,000.000 $73,422.240
WINGWALL (PW - 2) (HW=6 FT)
EA 12.000 $15,000.000 $25,000.000 $13,198.670
WINGWALL (PW - 2) (HW=7 FT)
EA 4.000 $17,000.000 $22,000.000 $12,573.550
WINGWALL (PW - 2) (HW=9 FT)
EA 2.000 $19,000.000 $35,000.000 $31,187.810
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 4.000 $8,000.000 $6,500.000 $1,481.150
SET (TY I)(S= 7 FT)(HW= 6 FT)(3:1) (C)
EA 4.000 $12,000.000 $9,000.000 $3,207.440
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 46.000 $2,250.000 $1,700.000 $1,728.610
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 30.000 $2,400.000 $3,000.000 $2,202.230
REMOV STR (BOX CULVERT)
EA 12.000 $12,000.000 $5,500.000 $4,627.220
REMOV STR (WINGWALL)
EA 54.000 $1,300.000 $1,400.000 $1,460.080
REMOV STR (PIPE)
LF 1,140.000 $35.000 $15.000 $30.520
MOBILIZATION
LS 1.000 $3,000,000.000 $4,500,000.000 $4,985,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 24.000 $20,000.000 $15,000.000 $9,511.570
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 5,772.000 $20.000 $30.000 $6.290
CONSTRUCTION EXITS (REMOVE)
SY 5,772.000 $8.000 $6.000 $0.880
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,180.000 $4.000 $3.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,180.000 $2.000 $1.000 $1.460
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 24.000 $6,000.000 $5,000.000 $10,000.000
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 960.000 $300.000 $120.000 $42.460
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 10,620.000 $75.000 $65.000 $82.710
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 107,520.000 $6.000 $1.750 $4.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 10,620.000 $8.000 $2.500 $4.000
DRIVEWAYS (CONC)
SY 489.000 $85.000 $100.000 $100.000
DRIVEWAYS (ACP)
SY 5,053.000 $70.000 $75.000 $50.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 128,520.000 $0.200 $0.100 $0.100
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 64,355.000 $0.200 $0.100 $0.110
MTL W-BEAM GD FEN (TIM POST)
LF 14,800.000 $30.000 $18.000 $35.000
MTL W-BEAM GD FEN (STEEL POST)
LF 475.000 $36.000 $20.000 $32.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 18.000 $1,450.000 $1,000.000 $2,200.000
MTL BM GD FEN TRANS (31"-28")
EA 4.000 $625.000 $500.000 $13,000.000
REMOVE METAL BEAM GUARD FENCE
LF 870.000 $4.500 $2.000 $32.000
GUARDRAIL END TREATMENT (INSTALL)
EA 66.000 $3,000.000 $3,000.000 $4,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 200.000 $2,000.000 $600.000 $1,500.000
CRASH CUSH ATTEN (REMOVE)
EA 26.000 $1,000.000 $700.000 $281.110
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 26.000 $12,000.000 $8,000.000 $8,243.860
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 64.000 $700.000 $650.000 $672.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 12.000 $750.000 $850.000 $887.250
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $900.000 $850.000 $892.500
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 5.000 $800.000 $950.000 $966.000
REMOVE SM RD SN SUP&AM
EA 35.000 $120.000 $100.000 $105.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
EA 292.000 $60.000 $80.000 $84.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 125.000 $65.000 $80.000 $84.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 218.000 $30.000 $70.000 $73.500
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 258,120.000 $0.220 $0.150 $0.150
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,300.000 $3.500 $5.350 $5.620
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 5,200.000 $1.400 $1.150 $1.210
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 624.000 $2.950 $4.500 $4.730
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 99,840.000 $1.350 $1.150 $1.210
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 6,455.000 $1.500 $2.000 $0.460
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 6,455.000 $1.500 $2.000 $0.470
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 12.000 $6.000 $4.850 $5.100
REFL PAV MRK TY II (W) 4" (SLD)
LF 126,931.000 $0.250 $0.100 $0.090
REFL PAV MRK TY II (Y) 4" (BRK)
LF 14,250.000 $0.250 $0.120 $0.110
REFL PAV MRK TY II (Y) 4" (SLD)
LF 40,570.000 $0.250 $0.100 $0.090
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 126,931.000 $0.600 $0.600 $0.620
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 14,250.000 $0.600 $0.600 $0.630
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 40,570.000 $0.600 $0.600 $0.620
REFL PAV MRKR TY II-A-A
EA 1,229.000 $3.750 $3.500 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 64,530.000 $1.000 $0.350 $0.350
POTHOLE REPAIR (STANDARD)
SY 650.000 $125.000 $55.000 $106.000
FILTER FABRIC (TY 2)
SY 25.000 $43.000 $6.000 $10.000
GEOGRID BASE REINFORCEMENT
SY 98,318.000 $3.000 $1.750 $3.000
SP MIXES SP-C SAC-A PG70-22
TON 34,727.000 $100.000 $130.000 $121.000
TACK COAT
GAL 47,306.000 $4.000 $5.000 $2.250
CEMENT
TON 2,581.000 $200.000 $180.000 $200.000
ASPHALT BINDER (PG 64-22)
TON 4,729.000 $450.000 $475.000 $690.000
FOAMED ASPHALT TREAT (10")(DC)
SY 360,333.000 $4.000 $4.250 $4.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $20,000.000 $15,000.000 $1.000
TMA (STATIONARY)
DAY 1,920.000 $150.000 $210.000 $135.000
TMA (MOBILE OPERATION)
DAY 104.000 $150.000 $375.000 $455.000
Totals: $49,437,214.800 $49,745,889.150 $51,986,898.430