CULBERSON RM 652 (1314-02-014)

Items: 78

County: CULBERSON
Length: N/A
Highway: RM 652
District: EL PASO
Control Number: 1314-02-014
DBE Goal: N/A
Project: STP 2020(467)
Guaranty: N/A
Time: 300 WORKING DAYS
Engineer's Estimate: $18,564,731.95
Date: 01/09/2020 (6 years ago)
Contract Number: N/A
Type: FULL DEPTH REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$18,564,731.95
$17,231,368.56
Over/Under Est: -7.18% -$1,333,363.39
Over/Under Est: 4.18% $776,338.90
Amt Left: 12.24% $2,109,702.29
Over/Under Est: 14.77% $2,741,418.79
Amt Left: 23.65% $4,074,782.18
Delta: -10.16% -$1,965,079.89
$26,297,118.78
Over/Under Est: 41.65% $7,732,386.83
Amt Left: 52.61% $9,065,750.22
Delta: -23.43% -$4,990,968.04

Bid Items & Bid Tabulations

78 Total 0 of 78
CULBERSON  |  RM 652  |  EL PASO  |  1314-02-014  |  01/09/2020  |  $18,564,731.95  |  STP 2020(467)  |  FULL DEPTH REHAB  |  300 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LESNA CONSTRUCTION, INC.
INTERNATIONAL EAGLE ENTERPRISES, INC.
JAMES HAMILTON CONSTRUCTION CO.
J.D. ABRAMS, L.P.
PREPARING ROW
STA 231.000 $900.000 $700.000 $700.000 $550.000 $2,275.000
REMOVING STAB BASE & ASPH PAV (4"-22")
SY 112,868.000 $6.000 $4.500 $3.000 $4.700 $5.700
EXCAVATION (ROADWAY)
CY 12,158.000 $20.000 $8.000 $21.500 $15.000 $29.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 92,430.000 $26.000 $23.000 $34.000 $54.000 $82.000
BACKFILL TY A
CY 17,204.000 $35.000 $22.000 $34.000 $59.000 $72.000
BLADING
HR 40.000 $175.000 $120.000 $180.000 $250.000 $111.000
PROOF ROLLING
HR 40.000 $135.000 $90.000 $160.000 $140.000 $93.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 4,189.000 $5.000 $6.500 $5.250 $3.800 $6.000
ASPH (MULTI OPTION)
GAL 61,635.000 $4.000 $6.500 $5.250 $4.400 $2.500
AGGR(TY-PB GR-4 SAC-B)
CY 1,041.000 $125.000 $115.000 $143.000 $250.000 $144.000
TOM (ASPHALT) PG 76-22
TON 389.000 $900.000 $1,200.000 $1,100.000 $800.000 $890.000
TOM-C (AGGREGATE) SAC-A
TON 5,895.000 $90.000 $95.000 $85.000 $110.000 $97.000
TACK COAT
GAL 18,089.000 $4.000 $7.000 $5.250 $4.000 $3.900
STRUCT EXCAV (BOX)
CY 2,583.000 $20.000 $15.000 $10.000 $48.000 $5.000
FLOWABLE BACKFILL
CY 807.000 $175.000 $190.000 $240.000 $210.000 $175.000
TEMPORARY SPL SHORING
SF 10,929.000 $50.000 $12.000 $12.000 $35.000 $31.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 3,478.000 $150.000 $80.000 $135.000 $145.000 $116.000
RIPRAP (SPECIAL)
CY 1,667.000 $150.000 $80.000 $220.000 $195.000 $116.000
GABION MATTRESSES (GALV) (24 IN)
SY 973.000 $180.000 $180.000 $180.000 $215.000 $85.000
CONC BOX CULV (4 FT X 2 FT)
LF 1,524.000 $250.000 $380.000 $270.000 $280.000 $367.000
CONC BOX CULV (8 FT X 6 FT)
LF 410.000 $600.000 $980.000 $700.000 $700.000 $795.000
RC PIPE (CL III)(24 IN)
LF 240.000 $70.000 $110.000 $110.000 $160.000 $141.000
RC PIPE (CL IV)(24 IN)
LF 98.000 $115.000 $130.000 $170.000 $180.000 $178.000
WINGWALL (PW - 2) (HW=4 FT)
EA 4.000 $8,000.000 $8,000.000 $7,000.000 $7,500.000 $15,500.000
WINGWALL (PW - 2) (HW=9 FT)
EA 2.000 $30,000.000 $19,000.000 $20,000.000 $46,000.000 $83,600.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 36.000 $5,000.000 $1,200.000 $6,000.000 $5,300.000 $7,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 8.000 $2,000.000 $1,500.000 $3,400.000 $1,000.000 $1,700.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $2,800.000 $2,250.000 $3,400.000 $1,400.000 $2,200.000
REMOV STR (BOX CULVERT)
EA 1.000 $12,000.000 $10,000.000 $2,400.000 $8,800.000 $9,300.000
REMOV STR (PIPE)
LF 123.000 $35.000 $25.000 $26.000 $60.000 $46.500
MOBILIZATION
LS 1.000 $2,000,000.000 $1,800,000.000 $1,800,000.000 $1,810,000.000 $1,972,280.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $20,000.000 $15,000.000 $14,000.000 $7,000.000 $24,100.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 2,222.000 $20.000 $30.000 $25.000 $21.000 $51.000
CONSTRUCTION EXITS (REMOVE)
SY 2,222.000 $8.000 $8.000 $10.000 $8.000 $15.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,440.000 $4.000 $4.500 $15.000 $4.000 $11.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,440.000 $2.000 $1.000 $10.000 $1.000 $6.400
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 15.000 $6,000.000 $5,500.000 $6,000.000 $4,500.000 $4,400.000
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 95.000 $300.000 $250.000 $300.000 $230.000 $232.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 5,670.000 $65.000 $75.000 $90.000 $74.000 $80.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 41,430.000 $6.000 $6.000 $7.500 $9.000 $3.500
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 5,670.000 $8.000 $15.000 $9.000 $9.500 $6.000
DRIVEWAYS (ACP)
SY 501.000 $70.000 $90.000 $65.000 $152.000 $132.000
MTL W-BEAM GD FEN (TIM POST)
LF 825.000 $30.000 $32.000 $50.000 $33.000 $40.000
MTL W-BEAM GD FEN (STEEL POST)
LF 150.000 $36.000 $60.000 $60.000 $33.000 $58.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 4.000 $1,450.000 $1,200.000 $3,000.000 $4,500.000 $1,580.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,000.000 $3,050.000 $3,500.000 $2,900.000 $3,700.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 52.000 $2,000.000 $1,200.000 $900.000 $2,500.000 $2,630.000
CRASH CUSH ATTEN (REMOVE)
EA 10.000 $1,000.000 $800.000 $1,100.000 $2,000.000 $1,880.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $12,000.000 $11,000.000 $20,000.000 $17,500.000 $10,700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $700.000 $475.000 $880.000 $950.000 $888.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $750.000 $550.000 $880.000 $1,025.000 $956.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $900.000 $650.000 $880.000 $1,150.000 $1,066.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $800.000 $750.000 $880.000 $1,260.000 $1,180.000
REMOVE SM RD SN SUP&AM
EA 12.000 $120.000 $150.000 $350.000 $70.000 $105.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
EA 53.000 $60.000 $70.000 $80.000 $85.000 $79.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 30.000 $65.000 $80.000 $85.000 $85.000 $79.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 73.000 $30.000 $37.000 $75.000 $55.000 $10.500
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 46,140.000 $0.220 $0.650 $1.500 $0.650 $0.660
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 240.000 $2.950 $4.500 $1.500 $13.200 $4.400
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 46,140.000 $0.220 $0.650 $1.000 $0.650 $0.660
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 500.000 $3.500 $5.000 $14.000 $11.000 $5.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 2,000.000 $1.400 $1.800 $1.400 $0.220 $1.760
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 38,400.000 $1.350 $1.800 $1.400 $0.220 $1.760
REFL PAV MRK TY II (W) 4" (SLD)
LF 46,184.000 $0.250 $0.300 $1.400 $0.220 $0.220
REFL PAV MRK TY II (Y) 4" (BRK)
LF 5,270.000 $0.250 $0.320 $1.500 $0.220 $0.270
REFL PAV MRK TY II (Y) 4" (SLD)
LF 11,802.000 $0.250 $0.300 $1.300 $0.220 $0.260
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 46,184.000 $0.850 $1.060 $1.400 $0.220 $1.080
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 5,270.000 $0.850 $1.060 $1.400 $0.220 $1.080
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 11,802.000 $0.850 $1.060 $1.400 $0.220 $1.080
REFL PAV MRKR TY II-A-A
EA 409.000 $3.750 $5.000 $30.000 $11.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 23,070.000 $1.000 $0.850 $1.400 $0.950 $0.850
POTHOLE REPAIR (STANDARD)
SY 250.000 $125.000 $95.000 $100.000 $7.300 $242.000
FILTER FABRIC (TY 2)
SY 18,499.000 $43.000 $3.500 $5.000 $2.000 $3.100
GEOGRID BASE REINFORCEMENT
SY 20,320.000 $2.000 $3.500 $15.000 $2.300 $5.400
EMULSIFIED ASPHALT BASE (PT MX) 10"
SY 127,556.000 $45.000 $50.000 $50.000 $46.300 $61.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $20,000.000 $15,500.000 $14,000.000 $20,000.000 $6,500.000
TMA (STATIONARY)
DAY 463.000 $150.000 $110.000 $215.000 $850.000 $111.000
TMA (MOBILE OPERATION)
DAY 40.000 $150.000 $90.000 $350.000 $1,000.000 $345.000
Totals: $18,564,731.950 $17,231,368.560 $19,341,070.850 $21,306,150.740 $26,297,118.780